La Strada Inn, Inc. v. United States

34 Cont. Cas. Fed. 75,246, 12 Cl. Ct. 110, 1987 U.S. Claims LEXIS 52
CourtUnited States Court of Claims
DecidedMarch 31, 1987
DocketNo. 671-85C
StatusPublished
Cited by11 cases

This text of 34 Cont. Cas. Fed. 75,246 (La Strada Inn, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
La Strada Inn, Inc. v. United States, 34 Cont. Cas. Fed. 75,246, 12 Cl. Ct. 110, 1987 U.S. Claims LEXIS 52 (cc 1987).

Opinion

OPINION

WIESE, Judge.

Plaintiff, the low bidder on a Government solicitation for a contract to furnish meals and lodging to prospective military personnel, was found ineligible for award on account of deficiencies noted during a pre-award facilities survey. In this suit, [112]*112filed here some ten months after award of the contract in question, plaintiff asks for recovery of (i) bid preparation costs, (ii) lost profits, and (iii) attorney’s fees, expenses, and court costs. Additionally, the court is asked to redirect award of the contract’s remaining term to plaintiff or, in the alternative, to require the agency to resolicit the contract in its entirety.

Defendant has moved for summary judgment, and plaintiff opposes. Based on the parties’ written submissions and the argument heard on February 27,1987, the court concludes that defendant is entitled to summary judgment on all issues in the case, except the claim for bid preparation costs. As to the latter, more facts are needed.

Facts

Plaintiff operates a hotel in New Orleans, Louisiana. In August 1984, it submitted what turned out to be the lowest bid in a solicitation by the Corps of Engineers for a fixed-price contract to provide meals and lodging for armed forces applicants in the New Orleans area. As required by regulation, a pre-award survey of plaintiff's facilities was conducted by the Defense Contract Administration Services Management Area (“DCASMA”) to determine whether plaintiff was a responsible bidder, ie., whether it possessed the requisite financial, technical, production and managerial resources to perform the work in accordance with the requirements given in the solicitation. Based on this on-site survey, DCASMA prepared a report recommending against award of the contract to plaintiff because of shortcomings in quality assurance standards.1

In addition to the survey of the hotel’s physical condition, the report form also contained an entry asking whether the prospective contractor had previously furnished similar services to the Government. In response to that entry, DCASMA’s report noted: “Offeror performed on Contract Number DACA-29-80-D-0305 for similar service, however extreme difficulties were experienced by the government.” No further explanation of these difficulties was given.

As indicated, the on-site survey resulted in a recommendation against award to plaintiff. A no-award recommendation also was made with respect to the next lowest bidder, Gold Key International, Ltd., though in this latter case, the disqualification was for financial reasons. The Government turned next to the Warwick Hotel, the third lowest bidder. Here the on-site inspection proved satisfactory, and a contract award to this organization followed soon afterward.

In the meantime, however, because of the delay caused by the several on-site surveys, the Government found it necessary to postpone the contract award date. To that end, it requested all bidders—plaintiff included—to extend the time for bid acceptance beyond the originally-specified date of November 4, 1984. Plaintiff agreed to this request, though at the time it did so, it was unaware of its adverse pre-award survey and the no-award recommendation.

On February 21, 1985, the Corps formally rejected plaintiff’s bid and awarded the contract to the Warwick Hotel. Plaintiff, after several unsuccessful efforts to obtain relief administratively—including a protest of the award to the contracting officer and the submission of a claim for bid costs and lost profits—brought suit in this court.

Discussion

A contractor who responds to a Government invitation for bids is entitled to fair and honest consideration of its submission. Keco Industries, Inc. v. United States, 192 Ct.Cl. 773, 780, 428 F.2d 1233, 1237 (1970); Heyer Products Co. v. United States, 135 Ct.Cl. 63, 69, 140 F.Supp. 409, [113]*113412 (1956). Failure on the Government’s part to honor this implied obligation is re-dressable in this court through either of two avenues. The bidder can obtain injunc-tive relief under 28 U.S.C. § 1491(a)(3) (1982)—but only if such relief is sought before the contract is awarded—or it can recover bid preparation costs under 28 U.S.C. § 1491(a)(1), pursuant to an implied contract theory. We consider each of these avenues in turn.

So far as plaintiff’s demand to set aside the contract award is concerned, § 1491(a)(3) permits this court to grant injunctive relief on an implied contract claim only if the claim is “brought before the [underlying] contract is awarded”. There is no dispute that suit here was not commenced until months after award of the contract in question. Hence, jurisdiction to entertain plaintiff’s demand is plainly lacking.

The argument is made, however, that the court should look beyond the actual date on which the complaint was filed and recognize that it was the contracting agency’s “belated” announcement of plaintiff’s ineligibility for award—that news first came forth on the same day that the contract award was announced—that accounts for plaintiff’s late appearance in this court. By not disclosing the adverse survey results prior to the award date, plaintiff argues, the contracting agency was able to foreclose a timely injunction suit here and, in so doing, undermine the legislative purpose expressed in the grant of pre-award injunctive authority to the Claims Court. Plaintiff therefore urges us to “reassert” our equitable power to remedy what it has characterized as a “possible case of denial of due process in the administration of public contracts in a circumstance where the plaintiff should have had the opportunity to protest.”

We cannot give this argument any heed. There is no escaping the fact that this court has no power to act where the demand for injunctive relief first surfaces after the challenged award has been made. By narrowly limiting the Claims Court’s equitable powers under § 1491(a)(3), Congress has given the district courts exclusive jurisdiction over post-award claims for injunctive relief. And if this statutory scheme allows the Government to structure bid review procedures so as to effectively route claims for equitable relief by disappointed bidders into the district courts, that is a circumstance that only Congress may change.

Precisely the same question was presented in United States v. John C. Grimberg Co., 702 F.2d 1362 (Fed.Cir.1983) (en banc), and there the appellate court answered the point this way:

The * * * possibility that a contract may be awarded before an implied contract claim can be filed in court cannot be substituted for the constitutional requirement that courts shall exercise only those powers granted by Congress and shall do so only at the times specified by Congress; nor can such a possibility authorize us to expand by fiat that which has been authorized by Congress. [Id. at 1373.]

This court clearly has no power to assert injunctive powers that it has not been given by statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Goodin v. United States Postal Inspection Service
393 F. Supp. 2d 869 (D. Minnesota, 2005)
Gentex Corp. v. United States
61 Fed. Cl. 49 (Federal Claims, 2004)
Compubahn, Inc. v. United States
40 Cont. Cas. Fed. 76,804 (Federal Claims, 1995)
Advanced Seal Technology, Inc. v. Perry
873 F. Supp. 1144 (N.D. Illinois, 1995)
Finley v. United States
39 Cont. Cas. Fed. 76,688 (Federal Claims, 1994)
Grumman Data Systems Corp. v. United States
39 Cont. Cas. Fed. 76,550 (Federal Claims, 1993)
Manshul Construction Corp. v. United States
687 F. Supp. 60 (E.D. New York, 1988)
Paxson Electric Co. v. United States
34 Cont. Cas. Fed. 75,483 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,246, 12 Cl. Ct. 110, 1987 U.S. Claims LEXIS 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/la-strada-inn-inc-v-united-states-cc-1987.