Manshul Construction Corp. v. United States

687 F. Supp. 60, 1988 U.S. Dist. LEXIS 4732, 1988 WL 54026
CourtDistrict Court, E.D. New York
DecidedMay 18, 1988
DocketMisc. 88-183
StatusPublished
Cited by5 cases

This text of 687 F. Supp. 60 (Manshul Construction Corp. v. United States) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manshul Construction Corp. v. United States, 687 F. Supp. 60, 1988 U.S. Dist. LEXIS 4732, 1988 WL 54026 (E.D.N.Y. 1988).

Opinion

MEMORANDUM OPINION

DEARIE, District Judge.

The King, it was held at English common law, could do no wrong. When “a long train of abuses and usurpations” by George III proved otherwise, events were set in motion that culminated in the formation of a government that, by the terms of its constitutive document, could do wrong if it exceeded its limited powers. That the rights of individuals against the government can meaningfully be vindicated at all in courts that are organs of that government is one of the miracles of American constitutional democracy.

The Framers’ thaumaturgy, however, was less than complete: the hoary tradition endures that redress against the government can be had only by its consent, in the forum of its choice, and for only such relief to which it acquiesces. The immunity thus granted to the sovereign, whatever its virtues, has undeniably produced an uneven topography of standing and jurisdiction that leaves some litigants on terra firma while others languish in the twilight zone. *61 The petitioner presently before the Court, which may well have a valid contract claim against the government, is among those who, despite the possible merit of their complaints, find themselves deprived of any real-world court that is empowered to grant relief to them.

FACTS

Petitioner, Manshul Construction Corporation, alleges that it bid on a contract to construct barracks for the Navy in Staple-ton, Staten Island, New York. Although Manshul was the low bidder, the Navy rejected its bid and announced that the contract would be negotiated. After protracted negotiations, Manshul won the contract.

The petition further alleges that, as the groundbreaking date approached, the Navy informed Manshul that stringent contractor quality control procedures would have to be implemented at Manshul’s expense. Manshul, which in its negotiated price had allotted only $30,000 for quality control— allegedly because the Navy had apparently agreed that others would be responsible for much of that work — found itself facing a job some twenty times more expensive. After protests to the Navy proved fruitless, Manshul filed an action for rescission in the United States Claims Court.

As that suit winds its way through heavy judicial traffic, out-of-court events threaten to overtake it. Manshul, which has refused to perform any portion of the contract except under protest, Petition Exs. G-R, now faces imminent risk of being declared in default under the contract. Manshul alleges that it presently has but two, equally unpalatable, choices: either (1) to fail to perform and risk huge financial penalties if the Claims Court does hot rescind the contract or (2) to perform and risk being es-topped from obtaining rescission in the Claims Court. Manshul petitioned this Court for a temporary injunction that would preclude the Navy from requiring performance or declaring a default until Manshul’s rescission claim is finally adjudicated. For the reasons stated below, Man-shul’s application for a preliminary injunction was denied, and the petition was dismissed, by an Order of this Court dated May 13, 1988.

DISCUSSION

Manshul’s contract with the Navy is subject to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613. Petitioner’s Brief at 5; Respondent’s Brief at 2. That act provides that in a contract dispute with a federal agency other than the Tennessee Valley Authority, “a contractor may bring an action directly on the claim in the United States Claims Court....” 41 U.S.C. § 609(a)(1); see 28 U.S.C. § 1491(a). Indeed, Manshul has done so. But the Claims Court apparently lacks the power to grant the injunction that petitioner seeks here. United States v. John C. Grimberg Co., 702 F.2d 1362, 1374 (Fed.Cir.1983) (equitable power of Claims Court limited by 28 U.S.C. § 1491(a)(3) to granting injunctions before contract award); see also, e.g., Brown v. United States, 3 Cl.Ct. 31 (1983), aff'd, 741 F.2d 1374 (Fed.Cir.1984); La Strada Inn, Inc. v. United States, 12 Cl.Ct. 110 (1987) (same re: implied contract); Wasko Aff. in Support of Petition ¶ 4 (Senior Deputy Clerk of Claims Court told Manshul’s attorney that application for injunctive relief “would probably be dismissed for lack of jurisdiction”). Therefore, the instant petition was brought before this Court, whose power to grant equitable relief is not similarly limited. Petitioner’s Brief at 1.

The general power to grant injunctions, however, does not carry with it the authority to hear any suit in which a petitioner feels injunctive relief is required. The Court’s equitable powers may be exercised only in cases that are within its statutorily-defined jurisdiction, and this case lies outside it. Accordingly, petitioner’s application for a preliminary injunction must be denied, and the petition must be dismissed. 1

Prior to enactment of the Contract Disputes Act, the Tucker Act, 28 U.S.C. *62 § 1346(a)(2), would have vested this Court with jurisdiction over Manshul’s claim, concurrent with the Claims Court. As amended by the Contract Disputes Act, however, § 1346(a) now reads, in pertinent part:

The district courts shall have original jurisdiction, concurrent with the United States Claims Court, of ... (2) Any ... claim against the United States, not exceeding $10,000 in amount, founded ... upon any express or implied contract with the United States, ... except that the district courts shall not have jurisdiction of any civil action or claim against the United States founded upon any express or implied contract with the United States ... which are [sic] subject to sections 8(g)(1) and 10(a)(1) of the Contract Disputes Act of 1978 [41 U.S.C. §§ 607(g)(1), 609(a)(1)].

Manshul concedes that its “underlying” claim for rescission is therefore committed to the exclusive jurisdiction of the Claims Court, Petitioner’s Brief at 4-5, but contends that its petition to this Court is not “founded upon any express or implied contract with the United States.” Rather, Manshul argues that the instant action is founded upon its statutory and common law right to bring its contract action in the Claims Court, unimpaired by the Navy’s out-of-court efforts to compel performance. This creative recharacterization cannot permit petitioner to elude the jurisdictional strictures of the Contract Disputes Act.

A government contractor may, of course, seek relief in the District Court for a claim that bears some relation to a contract if the essential nature of the claim is not contractual.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
687 F. Supp. 60, 1988 U.S. Dist. LEXIS 4732, 1988 WL 54026, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manshul-construction-corp-v-united-states-nyed-1988.