Kellogg Brown & Root Services, Inc.

Armed Services Board of Contract Appeals·Decided November 19, 2018·No. ASBCA No. 57530, 58161·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Kellogg Brown & Root Services, Inc. ) ASBCA Nos. 57530, 58161 ) Under Contract No. DAAA09-02-D-0007 )

APPEARANCES FOR THE APPELLANT: Craig D. Margolis, Esq. Christian D. Sheehan, Esq. Arnold & Porter Kaye Scholer LLP Washington, DC

Amy L. Riella, Esq. Carla Jordan-Detamore, Esq. Christina J. Ferma, Esq. Vinson & Elkins LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Arthur M. Taylor, Esq. DCMA Chief Trial Attorney Carol Matsunaga, Esq. Senior Trial Attorney Kara M. Klaas, Esq. Trial Attorney Defense Contract Management Agency Carson, CA

Russell B. Kinner, Esq. Patrick M. Klein, Esq. David W. Tyler, Esq. Trial Attorneys U.S. Department of Justice Washington, DC

OPINION BY ADMINISTRATIVE JUDGE MELNICK

This appeal involves the government's LOGCAP III contract with Kellogg Brown & Root Services, Inc. (KBR). Through this contract, the government acquired support services during United States military operations in Iraq. KBR seeks the costs it incurred settling two requests for equitable adjustment submitted by a subcontractor providing accommodations to house military personnel. Because KBR has failed to demonstrate that the costs were reasonable, it is not entitled to recover. FINDINGS OF FACT

1. In 2001, the United States Army awarded Contract No. DAAA09-02-D-0007, commonly called LOGCAP III, to KBR (originally Brown & Root Services, Division of Kellogg Brown & Root, Inc.) (app. supp. R4, tab 47). LOGCAP III required KBR to perform various support services for the government through individual task orders (app. supp. R4. tab 4 7 at 4668, 4 718-19). See Kellogg Brown & Root Servs., Inc. v. United States, 728 F .3d 1348, 1353 (Fed. Cir. 2013). Among the clauses incorporated into LOGCAP III were Federal Acquisition Regulation (FAR) 52.216-7, ALLOW ABLE COST AND PAYMENT (MAR 2000 ); and FAR 52.244-6, SUBCONTRACTS FOR COMMERCIAL ITEMS AND COMMERCIAL COMPONENTS (OCT 1998) (app. supp. R4, tab 47 at 4699, 4708). 1 Section H-16 ofthe contract's special provisions for contingency operations provided that, while performing contract duties, the Service Theater Commander would "provide force protection to contractor employees commensurate with that given to Service/Agency ... civilians in the operations area" unless otherwise stated in a task order (id. at 4759).

2. In early August 2003, after United States forces entered Iraq, the government executed LOGCAP III Task Order (TO) 59 (R4, tab 201). TO 59 was a cost-plus-fixed-fee order for services from KBR in support of operations in Iraq (id. at 200009). On October 10, 2003, the government executed Statement of Work Change 5 (incorporated into Modification No. 06 to TO 59) (R4, tab 225). Among many things, Change 5 required KBR to provide living accommodations to CJTF-7 and other coalition forces in various locations in Iraq (id. at 200293). CJTF-7 was the combined joint task force designated as the command and control headquarters for the Iraq theater of war (tr. 2/71).

3. Change 5 stated that it was "the Commander's intent to rapidly bed down the remainder of CJTF[-]7 soldiers .. .in accordance with established and provided priorities'' (R4, tab 225 at 200293 ). Prior to this effort, soldiers slept wherever they could in temperatures that could exceed 100 degrees. The locations included abandoned schools, public buildings, homes, tents, vehicles, the ground, or any other place soldiers could put a sleeping bag. (Tr. 2/110-11) The military sought to provide facilities to escape harsh conditions so soldiers could recharge for future missions (tr. 2/112). The accommodations constituted over 18,000 containers or trailers containing specified furnishings, environmental units, lighting, and meeting other requirements, to be delivered to multiple sites in Iraq (R4, tab 225 at 200297-329; tr. 3/70). 2 The Commander established an aggressive goal to "bed down" all the soldiers by Christmas of 2003 (tr. 2/112). Accordingly, with exceptions not relevant here, Change 5 required the trailers to be

1 The contract states the clause is dated "OCT/2001" (app. supp. R4, tab 47 at 4708). No such clause was discovered. The version of the clause dated "OCT 1998," which was in existence at the time of contract award and bears the same title as the referenced clause in the contract, is deemed applicable. 2 All of the accommodations are referred to as trailers. 2 provided "[n]o later than" December 15, 2003 (R4, tab 225 at 200296-97). Change 5 stated that "[t]he government [would] provide for the security of contractor personnel in convoys and on site, commensurate with the threat, and [in accordance with] the applicable Theater Anti-Terrorism/Force Protection guidelines" (id. at 200294).

4. One of the numerous sites described in Change 5 was "Site A'", known as Camp Anaconda (R4, tab 225 at 200296, -298; app. prop. finding 17). Camp Anaconda (also called Balad) was the main supply and logistics base for Iraq (tr. 2/89). KBR was to provide, set-up, operate, and maintain 2,252 trailers at Camp Anaconda. It was also required to perform site preparation and produce a site layout (with the assistance of appropriate government engineers). (R4, tab 225 at 200304-05)

5. KBR defined a minimum standard for its trailers based upon a design from a Saudi Arabian contractor named Red Sea. However, Red Sea would not deliver the trailers to sites in Iraq, and KBR did not have the resources to perform that function itself. So it decided to subcontract out the complex logistical issues associated with purchasing the units, transporting them under extremely hazardous conditions that threatened life and equipment, installing them, and assuming the associated risks. (R4, tab 625; tr. 8/39-40)

6. On October 17, 2003, one week after Change 5 was issued by the government, KBR and First Kuwaiti Co. of Kuwait (FKTC) executed a firm-fixed-price subcontract (Subcontract 11) in the amount of $80,978,562 for the procurement and delivery to Camp Anaconda of 2,252 prefabricated trailers (app. supp. R4, tab 62). The subcontract was to be construed and governed by the laws of Texas (id. at 4937). FKTC was to manufacture the trailers and then transport them to a staging yard bordering Iraq. From there, FKTC would transport them and their contents in convoys to Camp Anaconda. "Security of Subcontractor personnel in convoys and on site, [would] be provided commensurate with the threat, and [in accordance with] the applicable Theater Anti-Terrorism/Force Protection guidelines." FKTC would provide all equipment and labor to set-up and install the trailers. (Id. at 4923-30) FKTC represented that Red Sea would be its main trailer manufacturer (app. supp. R4, tab 56 at 4905; tr. 5/124). KBR considered the transportation component of the subcontract price to cover all movement costs, including any "prolonged delays at border crossing sites" (app. supp. R4, tab 270 at 8330).

7. Section 4.0 of the subcontract was titled "TIME OF PERFORMANCE." Section 4.1 required FKTC to begin work the next day, October 18. In accordance with Change 5 it was to complete all work by December 15. However, the section recognized that allowances would be made "for delays in KBR convoy coordination and support." Section 4.2 required FKTC to "make whatever adjustments in working hours, manpower, equipment, etc., deemed necessary by" KBR. The costs of those adjustments would be to FKTC's account. (App. supp. R4, tab 62 at 4924)

3 8. The subcontract contained General Conditions, supplemented by Special Conditions. In the event of conflict, the Special Conditions took precedence (app. supp. R4, tab 62 at 4943).

Free access — add to your briefcase to read the full text and ask questions with AI

Kellogg Brown & Root Services, Inc., (asbca 2018).

Kellogg Brown & Root Services, Inc. (Kellogg Brown & Root Services, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related