Kellogg Brown & Root Services, Inc.

Armed Services Board of Contract Appeals·Decided June 8, 2017·No. ASBCA No. 56358, 57151, 57327, 58583·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Kellogg Brown & Root Services, Inc. ) ASBCA Nos. 56358, 57151 ) 57327,58583 ) Under Contract No. DAAA09-02-D-0007 )

APPEARANCES FOR THE APPELLANT: Jason N. Workmaster, Esq. Raymond B. Biagini, Esq. Alejandro L. Sarria, Esq. Herbert L. Fenster, Esq. John E. Hall, Esq. Covington & Burling LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney ChristinaLynn E. McCoy, Esq. MAJ Lawrence Gilbert, JA Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE O'SULLIVAN ON THE GOVERNMENT'S MOTION TO DISMISS AND APPELLANT'S MOTION FOR SUMMARY JUDGMENT

These appeals involve costs incurred by Kellogg Brown & Root Services, Inc. (KBRS) and its subcontractors for private security to accompany company officials and convoys used to deliver food and other supplies to U.S. and coalition troops in Iraq during military operations in the 2003-2006 timeframe. Starting in 2007, the Army withheld a total of $44,059,024.49 from KBRS billings under the contract to recoup previously paid costs of private security that the government had determined were unallowable. Three of the appeals, ASBCA Nos. 56358, 57151 and 57327, are before us on remand from the United States Court of Appeals for the Federal Circuit, which held that the contract prohibited the use of private security companies (PS Cs) but, in order to fully resolve the dispute, remanded the appeals to the Board to decide whether KBRS "properly raised its breach and remedy allegations, and if so, to rule on those contentions." McHugh v. Kellogg Brown & Root Services, Inc., 626 F. App 'x 974, 978 (Fed. Cir. 2015).

The fourth appeal, ASBCA No. 58583, is before the Board following KBRS's appeal from a deemed denial of its 29 September 2011 certified claim for breach of contract. This appeal was not decided by the Board and was consolidated with the other three appeals only after the appellate remand. On 19 January 2016 the Board denied the government's pending motion to dismiss this appeal for lack of jurisdiction. Kellogg Brown & Root Services, Inc., ASBCA No. 58583, 16-1 BCA ~ 36,233.

Following the Board's denial of the government's motion to dismiss in ASBCA No. 58583, KBRS filed a first amended and consolidated complaint (FACC) in all four appeals. 1 Thereafter the government filed a motion to dismiss as to all counts and appellant filed a motion for summary judgment. Oral argument was held on the motions on 23 August 2016.

DISCUSSION

KBRS in its F ACC asserts the following:

Count I-the government's recovery on its claim is time-barred because the contracting officer's 30 January 2013 final decision was issued more than six years after the government's claim accrued, which was no later than 10 June 2005.

Count II-KBRS is entitled to judgment because the Army breached its contractual obligation to provide adequate force protection and the use of PSCs was a permissible remedy.

Count III-the Army breached the contract by requiring KBRS to perform beyond the original scope and the use of PSCs was a permissible remedy.

Count IV-the Army breached the contract by failing to comply with the FAR 16.301-3 requirement to have available adequate resources to manage a cost reimbursement contract and use of PSCs was a permissible remedy.

Count V-KBRS is entitled to judgment because the contract prohibition relied on by the Army applies only in peacetime, not during war.

1 Prior to the filing of the FACC, KBRS's amended complaints in ASBCA Nos. 56358, 57151, and 573 2 7, filed 16 January 2013, contained three counts: Count I (Breach of Contract), Count II (Waiver/Ratification), and Count III (Bad Faith).

2 Count VI-KBRS is entitled to judgment because the government waived the contract prohibition on the use of PSCs.

Count VII-KBRS is entitled to judgment because the Army cannot reopen the firm-fixed-price subcontracts at issue.

Count VIII-under a cost-reimbursement contract, KBRS is entitled to recover all of its incurred costs so long as they were not incurred due to fraud, lack of good faith, or willful misconduct.

Count IX-KBRS is entitled to judgment because the Army released KBRS from all claims related to the pricing and award of the ESS subcontracts.

Count X-KBRS is entitled to judgment because the Army contracting officer's 30 January 2013 final decision was invalid.

Count XI-the Army's damages calculation is inaccurate and unsupported.

Count XII-the Army acted in bad faith in its decision to recapture funds from KBRS.

KBRS has moved for summary judgment only on Counts II (breach of contract) and VI (waiver).

The affirmative defenses asserted by KBRS on 25 March 2013 in its complaint in ASBCA No. 58583 largely foreshadow the affirmative defenses articulated in KBRS's FACC. The only new counts in the FACC are Counts IV, V, and VII.

Before considering the parties' arguments, we address the parameters governing what is, and what is not, properly before us in these consolidated appeals. On appeal from our 2014 decision, the United States Court of Appeals for the Federal Circuit (hereinafter "court" or "Federal Circuit") was asked to decide two issues: ( 1) whether the Board erred in deciding that the contract did not prohibit the use of PSCs, and therefore that KBRS was entitled to payment for the use of PSCs; and (2) whether the Board erred in deciding that the Army's affirmative claim against KBRS contained in the contracting officer's final decision (COFD) issued 30 January 2013 was barred by the CDA's six-year statute of limitations. McHugh, 626 F. App'x at 976. The court affirmed the Board on the second issue, finding that the Army's 30 January 2013 affirmative claim was time-barred, but reversed the Board's holding that the contract did not prohibit the use of PSCs. Id. at 977, 979. The court recognized that "[t]his

3 narrow contract interpretation based on the weapons prohibition ... may not fully resolve the dispute," and remanded to the Board to determine whether "KBR properly raised its breach and remedy allegations, and if so, to rule on those contentions." Id. at 978. In ascertaining the proper scope of the appeals now before us, we are mindful that our appellate mandate constitutes the law of the case on all issues that were explicitly or implicitly decided by the court. Exxon Corp. v. United States, 931 F.2d 874, 877 n.7 (Fed. Cir. 1991) (citing lB J. MOORE, J. LUCAS & T. CURRIER, MOORE'S FEDERAL PRACTICE ii 0.404[10] at 172-74 (2d ed. 1988)). However, we do not read the court's opinion to foreclose the Board from considering and deciding other issues presented in these appeals that were not previously decided by the Board and were therefore never appealed.

I. The Government's Motion to Dismiss

The government has moved to dismiss all counts ofKBRS's FACC and KBRS has responded in opposition. A short discussion of the approach taken by the government and how we intend to decide the motion to dismiss is in order. The government's motion, with respect to some counts of the FACC, asserts that they fail to state a claim upon which relief can be granted. With respect to other counts, the government asserts that the Board lacks jurisdiction to entertain them; and with respect to the remainder, the government argues that they are foreclosed either by law of the case or by the Federal Circuit's mandate.

Free access — add to your briefcase to read the full text and ask questions with AI

Kellogg Brown & Root Services, Inc., (asbca 2017).

Kellogg Brown & Root Services, Inc. (Kellogg Brown & Root Services, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Secretary of the Army v. Tecom, Inc.
566 F.3d 1037 (Federal Circuit, 2009)
Long Island Savings Bank, FSB v. United States
503 F.3d 1234 (Federal Circuit, 2007)
Ruby Conway v. Chemical Leaman Tank Lines, Inc.
644 F.2d 1059 (Fifth Circuit, 1981)
Exxon Corporation v. The United States
931 F.2d 874 (Federal Circuit, 1991)
Barron Bancshares, Inc. v. United States
366 F.3d 1360 (Federal Circuit, 2004)
Kellogg Brown & Root Services, Inc. v. United States
728 F.3d 1348 (Federal Circuit, 2013)
Anchor Hocking Corp. v. Jacksonville Electric Authority
419 F. Supp. 992 (M.D. Florida, 1976)
Laguna Construction Company v. Defense
828 F.3d 1364 (Federal Circuit, 2016)
Northern Helex Co. v. United States
455 F.2d 546 (Court of Claims, 1972)
Grumman Aerospace Corp. v. United States
549 F.2d 767 (Court of Claims, 1977)
National Helium Corp. v. Morton
455 F.2d 650 (Tenth Circuit, 1971)