In re Letter of Notification Application of Columbia Gas of Ohio, Inc.

2024 Ohio 4747, 248 N.E.3d 235, 176 Ohio St. 3d 548
CourtOhio Supreme Court
DecidedOctober 3, 2024
Docket2023-0649
StatusPublished
Cited by1 cases

This text of 2024 Ohio 4747 (In re Letter of Notification Application of Columbia Gas of Ohio, Inc.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Letter of Notification Application of Columbia Gas of Ohio, Inc., 2024 Ohio 4747, 248 N.E.3d 235, 176 Ohio St. 3d 548 (Ohio 2024).

Opinion

[This opinion has been posted in Ohio Official Reports at 176 Ohio St.3d 548.]

IN RE LETTER OF NOTIFICATION APPLICATION OF COLUMBIA GAS OF OHIO, INC., FOR THE FORD STREET PIPELINE PROJECT; YORKTOWN MANAGEMENT, L.L.C., APPELLANT; OHIO POWER SITING BOARD, APPELLEE; COLUMBIA GAS OF OHIO, INC., INTERVENING APPELLEE. [Cite as In re Letter of Notification Application of Columbia Gas of Ohio, Inc., 2024-Ohio-4747.] Public utilities—Gas-pipeline construction—R.C. 4906.03(F)—R.C. 4906.10(A)(2) and (A)(3)—Adm.Code Ch. 4906-6—Ohio Power Siting Board properly approved application for construction of natural-gas-distribution pipeline under accelerated-review process set forth in R.C. 4906.03(F) for a gas pipeline that is not more than five miles long—Order affirmed. (No. 2023-0649—Submitted July 23, 2024—Decided October 3, 2024.) APPEAL from the Power Siting Board, Nos. 22-1145-EL-BLN and 22-1145-GA-BLN. __________________ STEWART, J., authored the opinion of the court, which KENNEDY, C.J., and FISCHER, DEWINE, DONNELLY, BRUNNER, and DETERS, JJ., joined.

STEWART, J. {¶ 1} In the proceedings below, the Ohio Power Siting Board granted the application of intervening appellee, Columbia Gas of Ohio, Inc. (“Columbia”), to construct the Ford Street Pipeline Project, a 3.7-mile natural-gas-distribution pipeline in the City of Maumee in Lucas County. The board approved the pipeline project under R.C. 4906.03(F)(3), which provides an accelerated-review process for a proposed gas pipeline that is not more than five miles long. SUPREME COURT OF OHIO

{¶ 2} Appellant, Yorktown Management, L.L.C. (“Yorktown”), which owns land and a commercial office building adjacent to property that contains a portion of the approved route of the pipeline, has appealed. Yorktown contends that the board failed to consider and resolve safety and environmental concerns related to the pipeline’s siting in proximity to the western boundary of Yorktown’s property. Specifically, Yorktown questions the placement of the pipeline and the width of the easements necessary to safely construct, maintain, and operate the pipeline. {¶ 3} As discussed below, Yorktown’s arguments lack merit. We therefore affirm the board’s decision. I. FACTS AND PROCEDURAL BACKGROUND {¶ 4} R.C. 4906.04 provides that no person shall construct a major utility facility in Ohio without first having obtained a construction certificate from the board. The proposed Ford Street Pipeline Project is described as a 3.7-mile natural- gas pipeline to be constructed in Maumee using a combination of private easements and public-road rights-of-way. The pipeline will be 30 inches in diameter and is classified as a high-pressure distribution pipeline with a maximum allowable operating pressure of 145 pounds per square inch gauge. The length and operating pressure of the pipeline make it a “major utility facility” requiring the board’s approval. See R.C. 4906.01(B)(1)(c) and 4906.04. {¶ 5} R.C. 4906.03(F)(3) directs the board to adopt rules for conducting an accelerated review of an application for a construction certificate for a gas pipeline that is not more than five miles long. Consistent with that statutory provision, the board adopted Adm.Code Ch. 4906-6. Under the statute and the administrative rules, the board is required to approve an accelerated application no later than 90 days after its filing, unless review of the application is suspended for good cause shown. R.C. 4906.03(F)(3); Adm.Code 4906-6-09(A) and 4906-6-10(A) and (B).

2 January Term, 2024

{¶ 6} In December 2022, Columbia filed an accelerated application to construct the Ford Street pipeline. In January 2023, Yorktown filed a motion to intervene and initial comments in opposition to the proposed pipeline. Although no part of the proposed pipeline crosses or encroaches on Yorktown’s property, Yorktown argued that it would suffer irreparable financial harm if the proposed pipeline is constructed along its western property line and so close to its commercial office building. In March 2023, an administrative-law judge granted Yorktown’s motion to intervene. {¶ 7} Under Adm.Code 4906-6-06(B), the board’s staff is required to investigate each accelerated certificate application and submit a written report no less than seven days before the automatic-approval date. This rule also requires the board’s staff to include in its report recommended findings under R.C. 4906.10, which, in turn, requires the board to make certain substantive findings before issuing a certificate for the construction, operation, and maintenance of a major utility facility. {¶ 8} On March 10, 2023, the board’s staff issued its “Report of Investigation,” recommending that the project be automatically approved on March 17, subject to four conditions. The board’s staff found that Columbia had satisfied the necessary criteria under R.C. 4906.10(A) for approval of its accelerated application, including demonstrating the need for the pipeline. The report also included the board staff’s analysis of the project’s probable impacts on land use, safety, cultural resources, surface waters, and threatened and endangered species. {¶ 9} On March 14, 2023, Yorktown filed a motion to suspend the board’s consideration of Columbia’s accelerated application. See R.C. 4906.03(F)(3); Adm.Code 4906-6-09. Among other claims, Yorktown argued that Columbia’s application and the board’s staff report failed to address safety concerns regarding construction of the proposed pipeline along the entire western boundary of Yorktown’s property and less than 50 feet from its commercial office building.

3 SUPREME COURT OF OHIO

Columbia had already secured a permanent 30-foot easement and a temporary 50- foot construction easement from Yorktown’s neighbor for the portion of the pipeline that would run along Yorktown’s western property line. Yorktown asserted that these easements were not wide enough for Columbia to safely construct, operate, and maintain the pipeline. Yorktown requested that the board conduct a full hearing to develop the factual record and resolve these safety concerns as required by R.C. 4906.10(A)(2) (by determining “[t]he nature of the probable environmental impact” of the project) and R.C. 4906.10(A)(3) (by determining “[t]hat the [proposed project] represents the minimum adverse environmental impact”). {¶ 10} Because the board did not act on the accelerated application before the automatic-approval date recommended in the board’s staff report, the application was deemed automatically approved by the board under Adm.Code 4906-6-10(B), subject to the staff’s recommended conditions. {¶ 11} On March 23, 2023, Yorktown filed an application for rehearing of the board’s automatic approval of Columbia’s accelerated application. See R.C. 4903.10; Adm.Code 4906-2-32(C). Yorktown argued that the board had failed to address the safety concerns created by the proposed pipeline’s proximity to Yorktown’s property and thus violated R.C. 4906.10(A)(2) and (A)(3). The board denied rehearing on April 20, 2023. In re Letter of Notification Application of Columbia Gas of Ohio, Inc., Power Siting Board No. 22-1145-EL-BLN, 2023 WL 3095408, *1. {¶ 12} Yorktown appealed. The board filed a brief in defense of its order denying the application for rehearing. We granted Columbia’s motion for leave to intervene, 2023-Ohio-2453, and Columbia filed a brief urging affirmance of the board’s order.

4 January Term, 2024

II. STANDARD OF REVIEW {¶ 13} Under R.C. 4906.12, we apply the same standard of review to determinations of the Power Siting Board that we apply to orders of the Public Utilities Commission. Under that standard, we will reverse, vacate, or modify an order of the board only when, upon consideration of the record, we find the board’s order to be unlawful or unreasonable. R.C. 4903.13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Utility Service Partners, Inc. v. Public Utilities Commission
2009 Ohio 6764 (Ohio Supreme Court, 2009)
In re Application of Buckeye Wind, L.L.C.
2012 Ohio 878 (Ohio Supreme Court, 2012)
Sunoco, Inc. (R & M) v. Toledo Edison Co.
2011 Ohio 2720 (Ohio Supreme Court, 2011)
In re Application of Columbus S. Power Co.
2011 Ohio 2638 (Ohio Supreme Court, 2011)
In re Application of Ohio Power Co. (Slip Opinion)
2014 Ohio 4271 (Ohio Supreme Court, 2014)
In re Complaint of Pilkington N. Am., Inc. (Slip Opinion)
2015 Ohio 4797 (Ohio Supreme Court, 2015)
In re Application of Champaign Wind, L.L.C. (Slip Opinion)
2016 Ohio 1513 (Ohio Supreme Court, 2016)
In re Application of Icebreaker Windpower, Inc.
2022 Ohio 2742 (Ohio Supreme Court, 2022)
Ohio Power Co. v. Burns
2022 Ohio 4713 (Ohio Supreme Court, 2022)
Columbia Gas of Ohio, Inc. v. Holloway
2023 Ohio 4257 (Ohio Court of Appeals, 2023)
Ohio Edison Co. v. Pub. Util. Comm.
1997 Ohio 196 (Ohio Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
2024 Ohio 4747, 248 N.E.3d 235, 176 Ohio St. 3d 548, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-letter-of-notification-application-of-columbia-gas-of-ohio-inc-ohio-2024.