Ohio Power Co. v. Burns

2022 Ohio 4713, 215 N.E.3d 527, 171 Ohio St. 3d 84
CourtOhio Supreme Court
DecidedDecember 29, 2022
Docket2021-1168
StatusPublished
Cited by16 cases

This text of 2022 Ohio 4713 (Ohio Power Co. v. Burns) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio Power Co. v. Burns, 2022 Ohio 4713, 215 N.E.3d 527, 171 Ohio St. 3d 84 (Ohio 2022).

Opinion

[Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as Ohio Power Co. v. Burns, Slip Opinion No. 2022-Ohio-4713.]

NOTICE This slip opinion is subject to formal revision before it is published in an advance sheet of the Ohio Official Reports. Readers are requested to promptly notify the Reporter of Decisions, Supreme Court of Ohio, 65 South Front Street, Columbus, Ohio 43215, of any typographical or other formal errors in the opinion, in order that corrections may be made before the opinion is published.

SLIP OPINION NO. 2022-OHIO-4713 OHIO POWER COMPANY, APPELLANT, v. BURNS ET AL, APPELLEES. [Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as Ohio Power Co. v. Burns, Slip Opinion No. 2022-Ohio-4713.] Necessity of easements sought by agency through eminent domain—Applicability of necessity presumptions in R.C. 163.09(B)(1)—The term “appropriation” in R.C. 163.09(B)(1) means the appropriation of the specific property, or right therein, that is subject to the taking by the agency as set forth in its petition filed under R.C. 163.05—Agency did not “abandon” appropriation proceedings under R.C. 163.21(A) when it conceded that a term in proposed easements was unnecessary. (No. 2021-1168—Submitted August 2, 2022—Decided December 29, 2022.) APPEAL from the Court of Appeals for Washington County, Nos. 20CA19 through 20CA22, 2021-Ohio-2714. __________________ SUPREME COURT OF OHIO

FISCHER, J. {¶ 1} This discretionary appeal involves a dispute between appellant, Ohio Power Company, a public utility and subsidiary of American Electric Power, and appellees, Michael and Misty Burns, Ronald and Barbara Bohlen, Jeffrey and Holly Dexter, and Ryan and Denay May (“the landowners”), over the necessity of easements sought by Ohio Power through eminent domain to upgrade electric- transmission lines. The main issue in this case is whether Ohio Power, a private agency authorized to appropriate property under R.C. 163.01(B) and (C), was entitled to any of the necessity presumptions set forth in R.C. 163.09(B)(1). And the secondary issue is whether the landowners are entitled to fees associated with Ohio Power’s concession that one of the easement terms, the right to install distribution lines, was not necessary. {¶ 2} We hold that the term “appropriation” in R.C. 163.09(B)(1) means the appropriation of the “parcel or contiguous parcels in a single common ownership, or interest or right therein,” as identified in the petition filed by an agency under R.C. 163.05. Because in this case neither Ohio Power’s board of directors (“Power Board”) nor the Ohio Siting Board (“Siting Board”) reviewed the appropriations (i.e., the proposed easement terms), Ohio Power was not entitled to a rebuttable presumption under R.C. 163.09(B)(1)(a) or an irrebuttable presumption under R.C. 163.09(B)(1)(c). However, we hold that Ohio Power was entitled to a rebuttable presumption under R.C. 163.09(B)(1)(b) because it provided evidence of the necessity for the appropriations. Therefore, we agree with the appellate court’s determination that the trial court erred in holding that the presumptions under R.C. 163.09(B)(1)(a) and (c) apply, and we agree with the appellate court’s determination that the trial court needs to make a separate necessity finding with regard to each easement term. Thus, we affirm the court of appeals’ judgment reversing the trial court’s determination that the appropriations are necessary. We agree with the appellate court that the matter must be remanded to the trial court

2 January Term, 2022

but do not agree that another hearing is required. Rather, we remand the cause to the trial court for it to consider the appropriations and separately determine whether they are necessary. {¶ 3} Additionally, we hold that the landowners are not entitled to the fees associated with abandonment of appropriation proceedings under R.C. 163.21(A), because Ohio Power did not abandon the appropriation proceedings when it conceded that the distribution-line term in the easement was unnecessary. Any arguments concerning an award of fees under R.C. 163.09(G) and 163.21(B) with regard to the distribution-line term were not raised below by the landowners and were thus forfeited. The landowners, therefore, are not entitled to fees under R.C. 163.21(B), and we reverse the portion of the Fourth District Court of Appeals’ judgment holding otherwise. {¶ 4} We affirm the appellate court’s judgment in part and reverse it in part and remand the cause to the trial court for further proceedings consistent with this opinion. I. BACKGROUND A. The landowners contest the necessity of easements sought by Ohio Power {¶ 5} Sometime in 2017, Ohio Power determined that ten miles of electric- transmission lines in Washington County had aged significantly and that the current lines could no longer support the electrical load necessary to adequately service the community. Ohio Power designed a project to replace the aging 23-kilovolt electric-transmission system with a new 138-kilovolt electric-transmission system. However, to successfully complete the project, Ohio Power needed supplemental easements from various property owners, including the landowners in this case. {¶ 6} When negotiations with the landowners failed, Ohio Power sought supplemental easements by eminent domain under R.C. 163.05. Ohio Power filed verified petitions for appropriation against each of the landowners. In each verified petition, Ohio Power identified the need for the supplemental easement and the

3 SUPREME COURT OF OHIO

rights sought in relation to the construction and maintenance of the new electric- transmission system. {¶ 7} The landowners opposed the easements in general, alleging that the appropriations were overly broad and unnecessary, and they challenged the need for several of the easement terms specifically, including the need for distribution lines. B. The trial court holds a necessity hearing {¶ 8} The Washington County Court of Common Pleas held a necessity hearing, at which Ohio Power’s lead transmission-right-of-way agent for the project, Kelly Sue Rentschler, explained the need for the project. She said that the wooden poles supporting the current electric-transmission lines present a safety hazard to the technicians and the public and that the existing 23-kilovolt network was no longer strong enough to support the electrical load required in the area. Rentschler noted that between 2015 and 2017, there were over 30 power outages on that line. So Ohio Power sought to upgrade the system entirely, by replacing the wooden-pole system with a steel-pole system, which would require less maintenance and be more reliable in the long run, and by increasing the electrical- voltage capacity from 23 to 138 kilovolts, to ensure that the new line could supply adequate power to Marietta and the surrounding township. {¶ 9} Rentschler then explained Ohio Power’s approach to acquiring the rights needed for the project. She said that generally, Ohio Power would seek easement terms to acquire more rights than were necessary for the project. But if the matter proceeded to litigation, then Ohio Power would change the easement terms to only those that were necessary. Rentschler maintained that the easements at issue in this case were prepared with reference to the project plans and specifications. Rentschler also noted that the easements in this case mirrored an easement that had been proposed by the landowners’ counsel in another necessity challenge in a different county.

4 January Term, 2022

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New v. Jordan
2025 Ohio 1458 (Ohio Court of Appeals, 2025)
Naiman v. Cleveland Elec. Illum., Co.
2025 Ohio 1060 (Ohio Court of Appeals, 2025)
Luckey v. T&S Agriventures, L.L.C.
2025 Ohio 871 (Ohio Court of Appeals, 2025)
729 W. 130th St., L.L.C. v. Hinckley Twp. Bd. of Zoning Appeals
2024 Ohio 3349 (Ohio Court of Appeals, 2024)
WBL SPO I, L.L.C. v. D-V.I.P. Properties & Mgt. Group, L.L.C.
2024 Ohio 3300 (Ohio Court of Appeals, 2024)
Ohio Power Co. v. Burns
2024 Ohio 3364 (Ohio Court of Appeals, 2024)
Algoma Group, A Gen. Partnership v. Marchbanks
2024 Ohio 2342 (Ohio Court of Appeals, 2024)
Columbia Gas of Ohio, Inc. v. Holloway
2023 Ohio 4257 (Ohio Court of Appeals, 2023)
Wildcat Drilling, L.L.C. v. Discovery Oil & Gas, L.L.C.
2023 Ohio 3398 (Ohio Supreme Court, 2023)
Columbia Gas v. Bailey
2023 Ohio 1245 (Ohio Court of Appeals, 2023)
Weiler v. DLR Group
2023 Ohio 1221 (Ohio Court of Appeals, 2023)
Djurin v. Ginley
2023 Ohio 1041 (Ohio Court of Appeals, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2022 Ohio 4713, 215 N.E.3d 527, 171 Ohio St. 3d 84, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-power-co-v-burns-ohio-2022.