Ohio Power Co. v. Burns

2024 Ohio 3364, 251 N.E.3d 822
Ohio Court of Appeals·Decided August 28, 2024·No. 23CA23, 23CA24, 23CA25, 23CA26·Published·Cited by 1 cases

Opinion

IN THE COURT OF APPEALS OF OHIO FOURTH APPELLATE DISTRICT WASHINGTON COUNTY

Ohio Power Company, : Case Nos. 23CA23, 23CA24, 23CA25, 23CA26

Plaintiff-Appellee, :

v. DECISION AND : JUDGMENT ENTRY

Michael Burns, et al., :

Defendants-Appellants. RELEASED 8/28/2024 :

APPEARANCES:

Joseph R. Miller, Thomas Fusonie, John M. Kuhl, Kara M. Mundy, Vorys, Sater, Seymour and Pease LLP, Columbus, Ohio for Defendants-Appellants.

Ryan P. Sherman, Christopher J. Baronzzi, Jason T. Gerken, Syed Ahmadul Huda, Porter Wright Morris & Arthur LLP, Columbus, Ohio for Plaintiff-Appellee.

Hess, J.

{¶1} Defendants-Appellants Michael and Misty Burns, Ronald and Barbara

Bohlen, Jeffrey and Holly Dexter, and Ryan and Denay May (“Landowners”) own property over which Plaintiff-Appellee Ohio Power Company seeks to take easements by eminent domain. Following the trial court’s necessity hearing, the Landowners appealed and we determined, among other things, that Ohio Power was entitled to neither a rebuttable nor an irrebuttable presumption of the necessity of the appropriation under R.C. 163.09(B)(1)(a) or (c) and that the trial court conducted an inadequate review of the evidence and erred in finding that the extent of the take was a factual question for the jury. We also found that the Landowners were entitled to certain attorney fees. However, we found that the applicable attorney fee provision was R.C. 163.21(B), rather than R.C.

Washington App. Nos. 23CA23, 23CA24, 23CA25, 23CA26 2

163.21(A), because the trial court ordered Ohio Power to remove the distribution line easement term after Ohio Power admitted it was not necessary, not because Ohio Power had abandoned the appropriation proceedings. Ohio Power Company v. Burns, 2021- Ohio-2714 (4th Dist.).

{¶2} Ohio Power appealed to the Supreme Court of Ohio, which in large part affirmed our decision, except that it reversed our determination that the Landowners were entitled to attorney fees under R.C. 163.21(B) on procedural grounds, not substantive grounds, because the Court found that the Landowners had waived that argument in its appeal. The Court also determined that the trial court errors occurred after the necessity hearing, therefore on remand rather than requiring a second necessity hearing,1 the Court remanded it “to the trial court for it to analyze whether each appropriation (i.e., each proposed easement term) is necessary” based upon the evidence that Ohio Power had previously presented. Ohio Power Company v. Burns, 2022-Ohio-4713, ¶ 42.

{¶3} Upon remand, the trial court issued a post-remand order in which it reviewed the transcript of the necessity hearing and found that Ohio Power had presented evidence that all the challenged easement terms were necessary, except the distribution lines term, which it found to be a moot issue. The Landowners appealed.

{¶4} The Landowners collectively raise two assignments of error for our review.

They contend that the trial court erred (1) by failing to conduct a property-specific review of each of the challenged easements and (2) by finding that Ohio Power met its burden of proof to show necessity for six of the various proposed easement terms.

1 A second hearing would have afforded Ohio Power an opportunity to submit additional evidence of the

necessity of each of the proposed easement terms for the individual Landowners. Ohio Power’s erroneous belief that (1) “appropriation” meant the “project” and not the individual easement terms and (2) it was entitled to an irrebuttable presumption appeared to have influenced its presentation of evidence.

Washington App. Nos. 23CA23, 23CA24, 23CA25, 23CA26 3

{¶5} We find that the trial court was required to and did in fact conduct a property-

specific review of each of the challenged easements therefore we overrule Landowners first assignment of error. We find that the trial court’s findings that the right to construct term, the access route term, and the Tree Protection Zone term were necessary were supported by some competent and credible evidence. We overrule Landowners’ second assignment of error as it concerns those three terms. However, we find that the trial court’s findings that the herbicide vegetation control term was necessary was not supported by competent and credible evidence and the anti-abandonment term and the distribution lines term findings were erroneous as a matter of law. We sustain Landowners’ second assignment of error as it concerns those three terms.

{¶6} We affirm, in part, and reverse, in part, the trial court’s judgment and remand the cause for further proceedings consistent with the decision herein. Specifically, for the trial court to enter findings on the herbicide term, the anti-abandonment term, and the distribution lines term consistent with this decision.

I. FACTS AND PROCEDURAL BACKGROUND2

{¶7} In 2017, the Ohio Power Board of Directors gave initial approval for a project in Marietta, Ohio to enhance the reliability of the electric transmission network. The Board of Directors determined that the existing 23kV network was not strong enough to support the load, was obsolete, and should be replaced with a 138kV network. The project, known as “The Bell Ridge-Devola 138kV Transmission Line Project,” (the “Project”) included approximately 10 miles of new 138kV transmission lines and required siting, rights of way, and property purchases. In August 2018, the Ohio Power Siting Board (“Siting Board”)

2 The facts and procedural background are abbreviated and taken from a more detailed recitation in Ohio Power Company v. Burns, 2021-Ohio-2714 (4th Dist.).

issued a certificate of environmental compatibility and public need for the Project. The Ohio Power Board of Directors issued a December 2019 resolution approving the Project.

{¶8} Ohio Power filed petitions for appropriation against Landowners in 2020 to take easements on their property after efforts to negotiate easements failed. Landowners filed answers in which they denied that the easements were necessary and denied that the Siting Board’s August 2018 certificate declared the appropriation a necessity.

{¶9} The trial court held a consolidated hearing under R.C. 163.09 to determine any matters relating to: (1) the right to make the appropriation of the easement rights, (2) the inability of the parties to agree, or (3) the necessity for the appropriation of the easement rights. Following the hearing, the trial court determined that it was not required to review the terms of the easements; that the Siting Board’s certification of the necessity of the Project established an irrebuttable presumption that the appropriation of the easement rights was necessary under R.C. 163.09(B)(1)(c); that Ohio Power presented testimony that the appropriations were necessary, which established a rebuttable presumption that the appropriations were necessary under R.C. 163.09(B)(1)(b); and the Ohio Power Board’s December 2019 resolution created a rebuttable presumption that the appropriations were necessary under R.C. 163.09(B)(1)(a). The trial court determined that even if the Siting Board’s certificate did not create an irrebuttable presumption, the appropriations were necessary: “The public utility is in the best position to determine what is necessary to construct, operate and maintain an electric transmission line now and for many decades into the future” and Ohio Power testified that the easements do not go beyond what is necessary.

Washington App. Nos. 23CA23, 23CA24, 23CA25, 23CA26 5

Free access — add to your briefcase to read the full text and ask questions with AI

Ohio Power Co. v. Burns, 2024 Ohio 3364, 251 N.E.3d 822 (Ohio Ct. App. 2024).

2024 Ohio 3364 (Ohio Power Co. v. Burns) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Cincinnati Enquirer v. Butler Cty. Sheriff's Office
2025 Ohio 4621 (Ohio Court of Appeals, 2025)