Ohio Power Co. v. Burns

2021 Ohio 2714, 176 N.E.3d 778
CourtOhio Court of Appeals
DecidedAugust 4, 2021
Docket20CA19, 20CA20, 20CA21, 20CA22
StatusPublished
Cited by3 cases

This text of 2021 Ohio 2714 (Ohio Power Co. v. Burns) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio Power Co. v. Burns, 2021 Ohio 2714, 176 N.E.3d 778 (Ohio Ct. App. 2021).

Opinion

[Cite as Ohio Power Co. v. Burns, 2021-Ohio-2714.]

IN THE COURT OF APPEALS OF OHIO FOURTH APPELLATE DISTRICT WASHINGTON COUNTY

Ohio Power Company, : Case Nos. 20CA19, 20CA20, : 20CA21, 20CA22 Plaintiff-Appellee, : : v. : DECISION AND : JUDGMENT ENTRY Michael Burns, et al., : : RELEASED 8/04/2021 Defendants-Appellants. :

APPEARANCES:

Joseph R. Miller, Thomas Fusonie, John M. Kuhl, Kara M. Mundy, Vorys, Sater, Seymour and Pease LLP, Columbus, Ohio for Defendants-Appellants.

Ryan P. Sherman, Christopher J. Baronzzi, Jason T. Gerken, Syed Ahmadul Huda, Porter Wright Morris & Arthur LLP, Columbus, Ohio for Plaintiff-Appellee.

Hess, J. {¶1} Defendants-Appellants Michael and Misty Burns, Ronald and Barbara

Bohlen, Jeffrey and Holly Dexter, and Ryan and Denay May (“Landowners”) own property

over which Plaintiff-Appellee Ohio Power Company seeks to take easements by eminent

domain. The trial court held a necessity hearing and determined that the easements

sought by Ohio Power, except the distribution line easements, were necessary, and that

Ohio Power’s admission during the hearing that an easement for distribution lines was

not necessary did not constitute an abandonment. The trial court also denied the Burnses’

and Bohlens’ motion for judgment on the pleadings based on Ohio Power’s invalid petition

verifications. The trial court found that their motion to dismiss was not timely, and that

even if it were to consider the motion’s merits, the invalid verification was inconsequential. Washington App. Nos. 20CA19, 20CA20, 20CA21, 20CA22 2

{¶2} Landowners collectively raise five assignments of error for our review. The

Burnses and the Bohlens challenge the trial court’s denial of their motion for judgment on

the pleadings, arguing that their motion was timely and that Ohio Power’s invalid petition

verification resulted in a void proceeding. We find that the trial court erred when it

determined that the motion was untimely. Under Civ.R. 12(C), a motion for judgment on

the pleadings may be made “within such time as not to delay the trial.” The “trial” for

purposes of R.C. 163.01, et seq. is the jury trial on compensation under R.C. 163.14;

Landowners’ motion was timely. However, we find that the error was harmless because

the trial court addressed the merits of the motion. Although we find the trial court erred

in finding “the verification was accurate,” we nevertheless confirm the trial court’s denial

of the motion on other grounds. We agree with Landowners that the verification was

invalid because the Ohio Board of Directors’ 2019 Board resolution (“2019 Board

resolution”) attached as an exhibit to the petition did not exist when the petition was

verified. However, at the necessity hearing Ohio Power employees testified about the

2019 Board resolution and authenticated it. Under R.C. 163.12(C), the trial court had

discretion to sua sponte “amend any defect or informality in the proceedings under

[R.C.]163.01 to [R.C.] 163.22” and deem any deficiency in the petition’s verification cured

by the hearing testimony. We overrule Landowners’ first assignment of error.

{¶3} All Landowners challenge the trial court’s finding that Ohio Power was

entitled to both a rebuttable and an irrebuttable presumption of the necessity for the

appropriation under R.C. 163.09(B)(1)(a)-(c). First, they contend that the regulatory

agency, the Ohio Power Siting Board (“Siting Board”), approved the necessity of the

project, not the necessity of the appropriation of the easement rights. They contend that Washington App. Nos. 20CA19, 20CA20, 20CA21, 20CA22 3

the Siting Board did not review the easements or their terms and, in fact, had no

jurisdiction to do so. As a result, the irrebuttable presumption created in R.C.

163.09(B)(1)(c) is inapplicable. Likewise, Landowners contend that because the Ohio

Power Board of Directors did not review the easements or their terms, its resolution did

not approve any specific easements or easement terms. Therefore, Ohio Power is not

entitled to the rebuttable presumption created in R.C. 163.09(B)(1)(a). For their fourth

assignment of error, Landowners argue that the trial court erred in finding that Ohio Power

met its burden of presenting evidence of the necessity for the appropriation under R.C.

163.09(B)(1)(b) because the trial court improperly deferred to Ohio Power, finding “[t]he

public utility is in the best position to determine what is necessary to * * * maintain an

electric transmission line now and for many decades into the future * * * .” We find that

neither the Ohio Power Siting Board nor the Ohio Power Board of Directors approved the

specific appropriations against the Landowners. Therefore, Ohio Power was not entitled

to the presumptions set forth in R.C. 163.09(B)(1)(a) and (c). The trial court erred in

applying these presumptions in favor of Ohio Power. Likewise, the trial court was

mistaken regarding the scope of review to be employed and erred in deferring to Ohio

Power on the issue of the necessity of the easements. The trial court also erred in

determining that the extent of the taking was a factual question for the jury to consider at

the compensation trial. We sustain Landowners’ second, third, and fourth assignments of

error.

{¶4} Finally, Landowners argue that the trial court erred in concluding that Ohio

Power’s decision not to pursue an easement for distribution lines was not an

abandonment under R.C. 163.21. We agree with the trial court’s finding that Ohio Power’s Washington App. Nos. 20CA19, 20CA20, 20CA21, 20CA22 4

concession was not an abandonment under R.C.163.21. However, we nevertheless find

that the trial court erred in how it addressed the distribution line rights issue. Ohio Power

lost the right to appropriate easement rights for distribution lines because the Landowners

raised a successful challenge in their answer and at the hearing. Under R.C. 163.21(B),

Ohio Power was “not entitled to appropriate [that] particular property” and the trial court

should have issued a judgment against Ohio Power for costs and determined a just

amount in favor of the Landowners for reasonable disbursements and expenses

associated with defending against the taking of distribution line rights. We sustain the

Landowners’ fifth assignment of error on other grounds.

{¶5} We affirm, in part, and reverse, in part, the trial court’s judgment and remand

the cause for further proceedings consistent with the decision herein.

I. FACTS AND PROCEDURAL BACKGROUND

{¶6} In 2017, the Ohio Power Board of Directors gave initial approval for a project

in Marietta, Ohio to enhance the reliability of the electric transmission network. The Board

of Directors determined that the existing 23kV network was not strong enough to support

the load, was obsolete, and should be replaced with a 138kV network. The project, known

as “The Bell Ridge-Devola 138kV Transmission Line Project,” (the “Project”) included

miles of new 138kV transmission lines and required siting, rights of way, and property

purchases. In August 2018, the Siting Board issued a certificate of environmental

compatibility and public need for the Project. The Ohio Power Board of Directors issued

a December 2019 resolution approving the Project.

{¶7} Ohio Power filed petitions for appropriation against Landowners in 2020 to

take easements on their property after efforts to negotiate easements failed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ohio Power Co. v. Burns
2024 Ohio 3364 (Ohio Court of Appeals, 2024)
Ohio Power Co. v. Burns
2022 Ohio 4713 (Ohio Supreme Court, 2022)
Columbia Gas v. Phelps Preferred Invests., L.L.C.
2022 Ohio 2540 (Ohio Court of Appeals, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2021 Ohio 2714, 176 N.E.3d 778, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-power-co-v-burns-ohioctapp-2021.