Automated Solutions Corp. v. Paragon Data Systems, Inc.

856 N.E.2d 1008, 167 Ohio App. 3d 685, 2006 Ohio 3492
CourtOhio Court of Appeals
DecidedJuly 6, 2006
DocketNo. 86067.
StatusPublished
Cited by33 cases

This text of 856 N.E.2d 1008 (Automated Solutions Corp. v. Paragon Data Systems, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Automated Solutions Corp. v. Paragon Data Systems, Inc., 856 N.E.2d 1008, 167 Ohio App. 3d 685, 2006 Ohio 3492 (Ohio Ct. App. 2006).

Opinions

*688 Karpinski, Judge.

{¶ 1} Defendant, Paragon Data Systems, Inc. (“the hardware company”), appeals the trial court’s ruling on a declaratory judgment action interpreting its contract with plaintiff, Automated Solutions Corp. (“the software company”). Paragon manufactures computer hardware, and Automated writes software to run on computer hardware. 1

{¶ 2} The hardware company discussed with the Chicago Tribune a project that would provide the Tribune with a hand-held computerized inventory device for its newspapers. Because the hardware company provided only the physical components, it needed a software developer to write the software for the system. The hardware company, therefore, contacted a software company with which the hardware company had done projects in the past. Both companies entered into a contract to work together on the Tribune’s project and share the copyright and profits, including profits from any modified software sold to other periodical publishers (“the building contract”). The software company, in turn, entered into a contract with the Tribune to write the software for it (“the licensing agreement”). Wanting to keep a close eye on the costs of the project, the Tribune requested that all invoices be processed through one entity. The parties agreed that the hardware company would handle the invoices and reimburse the software company.

{¶ 3} Development of the software took longer than expected because the Tribune required numerous changes to the system. At a meeting with the Tribune in 2002, an officer of the software company stated that it was experiencing severe financial difficulties and that if requests for changes continued, it would “have to close its doors in three weeks.” This comment caused concern to the Tribune, which contacted the hardware company for reassurance that the project would not fail. The hardware company assured the Tribune that because of the way the hardware company’s contract with the software company was written, in the event the software company failed, the hardware company would assume all the software company’s rights to the software and also would ensure that the project would be completed.

{¶4} Meanwhile, the relationship between the hardware company and the software company deteriorated significantly during 2002, the year the project was to have been completed. The software company discovered that the hardware company had been altering its billings to the Tribune and had not been paying *689 the software company its share of the payments. Specifically, contrary to their agreement to split the profits, the hardware company was underpaying the software company its share of profits from the sale of hardware.

{¶ 5} Because of the delay in completing the software contract and the growing distrust between the companies, the hardware company executed an agreement memorialized in a letter signed by both companies and copied to the Tribune (“the September 2002 letter”). This letter acknowledged various financial transactions that had occurred between the companies and, more importantly, provided that the Tribune would pay the software company’s invoices directly, rather than channel payments through to the hardware company, as it had in the past.

{¶ 6} Additionally, the amended agreement required the software company to provide unencrypted source code no later that 120 days from September 20, 2003 (January 18th, 2003) or once the “go-live milestone” has been reached, whichever comes first. In consideration for this unlocked code, [the hardware company] has agreed to pay [the software company] $3,000.00 of its final milestone payments, as part of a compromise. Encrypted code updates will occur approximately twice per month starting no later than the first week of November, 2002.

Letter of September 20, 2002.

{¶ 7} The software company admitted that it was several weeks late in delivering the unencrypted source code, but it claims that it did provide the code as soon as the code was in a form that could be delivered. The hardware company, on the other hand, claimed that because the software company’s comments were stripped from the code, it was not usable. 2 The hardware *690 company took no action, however, against the software company concerning the code at that time.

{¶ 8} On September 9, 2003, nearly one year after the letter was written and six months after the code was due to the hardware company, the hardware company mailed another letter to the software company. In this letter, the hardware company noted that it had “worked with [the software company] to renegotiate the deadlines for [the software company’s] performance after it was made clear that the original deadlines would not be met.” This letter also complained of the software company’s failure to provide either the unencrypted or encrypted software according to the agreement in the September 2002 letter amending the original agreement. The hardware company then set a deadline of September 15, or five days later, for the software company to respond, preferably by providing the software (code) update.

{¶ 9} On September 16, the day after the deadline, the hardware company’s counsel terminated the contract in a letter, which stated:

This letter is to formally notify you that, effective immediately, the [original contract between the hardware company and the software company] and modified by letter agreement dated September 20, 2002 (“letter”) is hereby terminated by [the hardware company.]

Letter of September 16, 2003.

{¶ 10} As grounds for terminating the contract, the hardware company cited the software company’s “repeated material breaches of the Agreement,” including the delays in providing workable software and its refusal to provide the required software updates (codes)to the hardware company. The letter noted that the hardware company did not accept the software company’s claim that the hardware company was required to prepay $3,000 in exchange for the software code. Rather, the hardware company “unequivocally demandfed] that [the software company] immediately transfer all rights in and to the Software to [the hardware company], as mandated by the Agreement and to turn over the source code and all unencryption keys.” The software company responded by filing a complaint for a declaratory judgment interpreting the contract. That complaint is the subject of this appeal.

{¶ 11} Two days after sending the termination letter to the software company, the hardware company sent a letter instructing the Tribune to send all payments *691 for the software to the hardware company and not to the software company. The Tribune responded by writing that the licensing agreement was between the Tribune and the software company and that the hardware company was not a party to that contract. It also noted that the Tribune was not a party to the contract between the software company and the hardware company; rather, it was only a third-party beneficiary in that contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Platinum Restoration Contrs., Inc. v. Salti
2023 Ohio 4426 (Ohio Court of Appeals, 2023)
Platinum Restoration Contractors, Inc. v. Salti
2023 Ohio 3709 (Ohio Court of Appeals, 2023)
Erie Cty. Bd. of Commrs. v. Hintz
2023 Ohio 1595 (Ohio Court of Appeals, 2023)
USPG Portfolio Six, L.L.C. v. Dick's Sporting Goods, Inc.
2023 Ohio 550 (Ohio Court of Appeals, 2023)
Ohio Power Co. v. Burns
2021 Ohio 2714 (Ohio Court of Appeals, 2021)
Accurate Elec. Constr., Inc. v. Ohio State Univ.
2019 Ohio 4992 (Ohio Court of Appeals, 2019)
Cheng v. Haney
2019 Ohio 2144 (Ohio Court of Appeals, 2019)
King v. King
2019 Ohio 722 (Ohio Court of Appeals, 2019)
Patel v. Univ. of Toledo
2017 Ohio 7132 (Ohio Court of Appeals, 2017)
Third Fed. S. & L. Assn. of Cleveland v. Formanik
2016 Ohio 7478 (Ohio Court of Appeals, 2016)
3637 Green Rd. Co., Ltd. v. Specialized Component Sales Co., Inc.
2016 Ohio 5324 (Ohio Court of Appeals, 2016)
CosmetiCredit, L.L.C. v. World Fin. Network Natl. Bank
2014 Ohio 5301 (Ohio Court of Appeals, 2014)
PHH Mtge. Corp. v. Ramsey
2014 Ohio 3519 (Ohio Court of Appeals, 2014)
Chiquita Fresh North America, L.L.C. v. Greene Transport Co.
949 F. Supp. 2d 954 (N.D. California, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
856 N.E.2d 1008, 167 Ohio App. 3d 685, 2006 Ohio 3492, Counsel Stack Legal Research, https://law.counselstack.com/opinion/automated-solutions-corp-v-paragon-data-systems-inc-ohioctapp-2006.