Columbia Gas of Ohio, Inc. v. Holloway

2023 Ohio 4257
Ohio Court of Appeals·Decided November 27, 2023·No. 14-23-18, 14-23-19, 14-23-20, 14-23-21, 14-23-22, 14-23-23, 14-23-24, 14-23-25·Published·Cited by 3 cases

Opinion

IN THE COURT OF APPEALS OF OHIO THIRD APPELLATE DISTRICT

UNION COUNTY

COLUMBIA GAS OF OHIO, INC., CASE NO. 14-23-18

PETITIONER-APPELLEE,

v.

JOHN L. HOLLOWAY, JR., OPINION RESPONDENT-APPELLANT.

COLUMBIA GAS OF OHIO, INC., CASE NO. 14-23-19

PETITIONER-APPELLEE,

v.

JEREMY W. TILLER, ET AL., OPINION RESPONDENTS-APPELLANTS.

COLUMBIA GAS OF OHIO, INC., CASE NO. 14-23-20

PEITIONER-APPELLEE,

v.

TERESA PERRY, ET AL., OPINION RESPONDENT-APPELLANTS.

14-23-22, 14-23-23, 14-23-24, 14-23-25

COLUMBIA GAS OF OHIO, INC.

CASE NO. 14-23-21

PETITIONER-APPELLEE v. SCHRADER 10944, LLC, OPINION RESONDENT-APPELLANT.

COLUMBIA GAS OF OHIO, INC., CASE NO. 14-23-22

PETITIONER-APPELLEE,

v. OLIVE K. FLEMING, OPINION RESPONDENT-APPELLANT.

COLUMBIA GAS OF OHIO, INC., CASE NO. 14-23-23

PETITIONER-APPELLEE,

v. JOHN H. PUGH, ET AL., OPINION RESPONDENTS-APPELLANTS.

14-23-22, 14-23-23, 14-23-24, 14-23-25

COLUMBIA GAS OF OHIO, INC., CASE NO. 14-23-24

PETITIONER-APPELLEE,

v. GB FAMILY LIMITED PARTNERSHIP, OPINION RESPONDENT-APPELLANT.

COLUMBIA GAS OF OHIO, INC., CASE NO. 14-23-25

PETITIONER-APPELLEE,

v. RONALD E. KUHN, ET AL., OPINION RESPONDENTS-APPELLANTS.

Appeals from Union County Common Pleas Court Trial Court Nos. 2022-CV-0135, 2022-CV-0138, 2022-CV-0134, 2022-CV-

0140, 2022-CV-0131, 2022-CV-0142, 2022-CV-0129 and 2022-CV-0139

Judgments Affirmed

Date of Decision: November 27, 2023

APPEARANCES:

Thomas H. Fusonie for Appellants Adam C. Smith for Appellee

14-23-22, 14-23-23, 14-23-24, 14-23-25

Ryan P. Sherman Counsel for Amici Curiae Ohio Power Company and AEP Ohio Transmission Company, INC in support of Appellee Columbia Gas of Ohio, Inc.

WALDICK, J.

{¶1} Respondents-appellants, GB Limited Partnership, Olive K. Fleming, Teresa Perry, et al., John L. Holloway, Jr., Jeremy W. Tiller, et al., Ronald E. Kuhn, et al., Schrader 10944, LLC, John Pugh, et al., (collectively, “respondents”), bring these appeals from the April 19, 2023, judgments of the Union County Common Pleas Court determining that petitioner-appellee, Columbia Gas of Ohio, Inc., (“Columbia Gas”), established the necessity of easement appropriations for a natural gas pipeline. On appeal, respondents argue that the trial court erred by determining that Columbia Gas established the necessity of the appropriations and that the trial court failed to make required, specific findings concerning the necessity of the individually challenged easement terms. For the reasons that follow, we affirm the judgments of the trial court.

Background

{¶2} Columbia Gas is a natural gas distribution company that operates a public utility subject to regulation by the State of Ohio. This case concerns Columbia Gas appropriating easement rights on respondents’ properties in order to

14-23-22, 14-23-23, 14-23-24, 14-23-25

construct and operate a subsurface natural gas pipeline.1 The specific pipeline constitutes “Phase VII” of the “Northern Columbus Loop,” and will supply natural gas to Union, Delaware, and Franklin Counties to meet rising energy demands.2 The pipeline was approved by the Ohio Power Siting Board (“OPSB”) after various parties, including the Union County Commissioners, recommended the project’s approval.3

{¶3} On August 5, 2022, Columbia Gas filed “Verified Petition[s] for Appropriation of Easement Rights” related to respondents’ properties. 4 The easements Columbia Gas seeks to acquire on respondents’ properties are essentially the same: “the right to lay, operate, maintain, repair, replace, alter, relocate, and remove a single natural gas pipeline, no greater than 24 inches in diameter, with a maximum allowable operating pressure of 720 psig, together with valves and appurtenances * * *, subsurface within a 50-foot-wide permanent easement[.]”5 In addition, Columbia Gas seeks to acquire a “50-foot-wide temporary easement * * *

1 Columbia Gas asserts that the pipeline runs 16 miles through 115 parcels of land and that respondents own 10 of the subject parcels. Columbia Gas asserts that respondents are the only landowners challenging the easements in Union County. 2 According to Columbia Gas, this is the final phase of the pipeline project. 3 This Court and the trial court have addressed prior cases involving Columbia Gas and pipeline projects. See Columbia Gas v. Bailey, 3d Dist. Union Nos. 14-22-13, 14-22-14, 2023-Ohio-1245 (specifically dealing with the Northern Columbus Loop Pipeline); Columbia Gas v. Phelps, 3d Dist. Union No. 14-22-07, 2022-Ohio- 2540 (dealing with the “Marysville Connector”). 4 In the petitions, Columbia Gas asserted that the route of the pipeline project was selected after “evaluating approximately 37,800 acres of land,” that the “route parallels property lines and existing utility easements as much as practicable,” that the route minimized tree clearing, and that the route avoided “six wetlands and four streams.” 5 The pipeline on one property will be smaller.

14-23-22, 14-23-23, 14-23-24, 14-23-25

for the purpose of initial construction of the Pipeline and restoration of the Property resulting from the construction of the Pipeline.”6 The rights would be transferable to Columbia Gas’s “successors and assigns.”

{¶4} In the appropriation petitions Columbia Gas asserted, inter alia, that it had provided respondents with Notices of Intent to Acquire and Written Good Faith Offers based on appraisals. Columbia Gas asserted that the easements were necessary and reasonably convenient for public use. Because Columbia Gas and respondents had been unable to agree on the easement rights and/or compensation, Columbia Gas asserted the appropriation action was necessary.

{¶5} Respondents filed “Verified Answer[s]” asserting, inter alia, that the appropriations were not necessary in that they sought easement rights in excess of those necessary for the project.7 Respondents specifically argued that the proposed easements would improperly provide “unfettered blanket assignability rights,” that the proposed easements would improperly provide Columbia Gas unnecessary rights to maintain its pipeline, that the proposed 36-month temporary easements for construction of the pipeline were too indefinite, and that the easements improperly allowed Columbia Gas to construct “unspecified ‘appurtenances and valves’” on respondents’ property. Respondents sought a hearing on the necessity of the easements and their terms.

6 The temporary easement for one property owner was smaller since the pipeline being installed was smaller.

7 Respondents are represented collectively by the same law firm.

14-23-22, 14-23-23, 14-23-24, 14-23-25

{¶6} On February 10, 2023, the trial court held a consolidated “necessity”

hearing and heard testimony from Columbia Gas employees attesting to the necessity of the easements. The parties filed written closing arguments containing proposed findings of fact and conclusions of law.

{¶7} On April 19, 2023 the trial court filed a judgment entry determining that Columbia Gas was entitled to a rebuttable presumption of necessity due to the evidence presented, that respondents did not rebut the presumption, that the appropriations were necessary, and that the appropriations were not excessive.8 The trial court thus set the matter to proceed to compensation hearings. Respondents now appeal the trial court’s judgments, asserting the following assignments of error for our review.

First Assignment of Error

The Trial Court erred when it found that Columbia Gas of Ohio, Inc. showed the necessity of the underlying appropriations, that the evidence at the necessity hearing did not rebut the presumption under R.C. 163.09(B)(1)(b), and that the proposed easements do not constitute an excessive taking.

Second Assignment of Error

The Trial Court erred when it failed to make specific findings concerning the necessity of the easements at issue pursuant to Ohio Power Co. v. Burns, Slip Opinion No. 2022-Ohio-4713.

8 The trial court filed a nunc pro tunc entry on May 3, 2023.

14-23-22, 14-23-23, 14-23-24, 14-23-25

First Assignment of Error

Free access — add to your briefcase to read the full text and ask questions with AI

Columbia Gas of Ohio, Inc. v. Holloway, 2023 Ohio 4257 (Ohio Ct. App. 2023).

2023 Ohio 4257 (Columbia Gas of Ohio, Inc. v. Holloway) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Osborne v. Parkview Fed. Sav. Bank
2026 Ohio 260 (Ohio Court of Appeals, 2026)
Algoma Group, A Gen. Partnership v. Marchbanks
2024 Ohio 2342 (Ohio Court of Appeals, 2024)