Columbia Gas v. Bailey

2023 Ohio 1245
CourtOhio Court of Appeals
DecidedApril 17, 2023
Docket1-18-35
StatusPublished
Cited by4 cases

This text of 2023 Ohio 1245 (Columbia Gas v. Bailey) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbia Gas v. Bailey, 2023 Ohio 1245 (Ohio Ct. App. 2023).

Opinion

[Cite as Columbia Gas v. Bailey, 2023-Ohio-1245.]

IN THE COURT OF APPEALS OF OHIO THIRD APPELLATE DISTRICT UNION COUNTY

COLUMBIA GAS OF OHIO, INC.,

PETITIONER-APPELLANT/ CASE NO. 14-22-13 CROSS-APPELLEE,

v.

PATRICK E. BAILEY, ET AL., OPINION

RESPONDENTS-APPELLEES/ CROSS-APPELLANTS.

PETITIONER-APPELLANT/ CASE NO. 14-22-14 CROSS-APPELLEE,

DON BAILEY, JR., SUCCESSOR TRUSTEE OF THE ARNO RENNER TRUST DATED APRIL 24, 1997, ET AL., OPINION

Appeals from Union County Common Pleas Court Trial Court Nos. 21-CV-0112 and 21-CV-0113

Judgments Affirmed in Part, Reversed in Part and Cause Remanded

Date of Decision: April 17, 2023 Case No. 14-22-13 and 14-22-14

APPEARANCES:

Adam C. Smith for Appellant/Petitioner Columbia Gas of Ohio, Inc.

David Watkins for Appellees/Cross-Appellants/Respondents

Ryan P. Sherman for Amici Curiae, Ohio Power Company and AEP Ohio Transmission Co., Inc.

ZIMMERMAN, J.

{¶1} Petitioner-appellant/cross-appellee, Columbia Gas of Ohio, Inc.

(“Columbia Gas”), appeals the April 26, 2022 judgment of the Union County Court

of Common Pleas denying its petitions for the appropriation of easement rights.

Respondents-appellees/cross-appellants, Don Bailey, Jr., Successor Trustee of the

Arno Renner Trust dated April 24, 1997 (“Don”), Charles Peter Renner (“Renner”),

Patrick E. Bailey (“Patrick”), and Whitney Bailey (“Whitney”) (collectively,

“respondents”), appeal the trial court’s determination that an agricultural easement

does not prevent Columbia Gas’s petitions. For the reasons that follow, affirm in

part and reverse in part.

{¶2} Much like our previous and similar case, this case involves a dispute

involving Columbia Gas over the necessity of easement rights it sought through

eminent domain for the construction, operation, and maintenance of a natural-gas

pipeline. See Columbia Gas of Ohio, Inc. v. Phelps Preferred Investments, LLC, 3d

-2- Case No. 14-22-13 and 14-22-14

Dist. Union No. 14-22-07, 2022-Ohio-2540. However, the main issues in this case

is whether Columbia Gas is entitled to a necessity presumption under R.C.

163.09(B)(1) and whether respondents’ agricultural easement precludes an

appropriation of easement rights.

Background

{¶3} The Arno Renner farm originally comprised 231.25 acres of farmland

in Marysville, Ohio (the “protected property”). However, the protected property is

encumbered by an agricultural easement (as defined under R.C. 5301.67(C)) granted

in favor of the Ohio Department of Agriculture (“ODA”). The easement was filed

on August 21, 2003, recorded in Volume 509 of the Official Records at Page 369,

in the Union County, Ohio Recorder’s Office. Later, the protected property was

devised and divided. As a result, Don and Renner became the successive owners of

121 acres of the protected property, while and Patrick and Whitney became the

successive owners of 110.25 acres of the protected property.

{¶4} Before filing its verified petitions in the trial court, Columbia Gas—a

public utility—filed a letter-of-notification application under R.C. 4906.06 with the

Ohio Power Siting Board (“OPSB”) on December 20, 2019. Importantly, Columbia

Gas sought approval from the OPSB under R.C. 4906.03(F)(3) since it intended to

construct a new natural-gas pipeline which would be greater than one-mile length

but not greater than five miles in length. Specifically, Columbia Gas sought the

-3- Case No. 14-22-13 and 14-22-14

OPSB’s approval to construct a natural-gas pipeline that is approximately 4.78 miles

in length, consisting of a 12-inch diameter “coated steel pipe with a wall thickness

of 0.375 inches,” and “a Maximum Allowable Operating Pressure (“MAOP”) of

190 pounds per square inch gauge * * * .” (Petitioner’s Ex. 1).

{¶5} In its application, Columbia Gas generally represented to the OPSB that

it had “not obtained any easements along the right-of-way” under the section of its

application discussing the “list of properties for which the applicant ha[d] obtained

easements * * * necessary to construct and operate the facility and a list of the

additional properties for which such agreements have not been obtained.” (Id.).

Nevertheless, Columbia Gas indicated that it was “working to obtain easements

from the individuals and entities” identified in the appendix and that it would “not

begin construction until all easements [were] secured.” (Id.). Significantly,

Columbia Gas’s application did not include any further information regarding the

specific easements it sought from the landowners in that section or in the

corresponding appendix.

{¶6} However, in the general information portion of the application,

Columbia Gas informed the OPSB that “[t]he majority of the 12-inch natural gas

main will be constructed within permanent private pipeline easements * * * as

depicted in the construction plans in Appendix B.” (Id.). Further, Columbia Gas

indicated to the OPSB that “the proposed pipeline route will only include a 75-foot

-4- Case No. 14-22-13 and 14-22-14

wide (50-foot permanent easement and 25-foot temporary easement) construction

footprint” in the section of its application discussing the impact to wetlands. (Id.).

{¶7} In its July 9, 2020 staff report of investigation, the OPSB documented

that the pipeline project “crosses a parcel protected by an agricultural easement with

the [ODA].” (Doc. No. 1, Ex. 3). However, the report reflects the findings that

“[t]he easement held by ODA states that it does not preclude installation over or

under the protected property for the purpose of providing gas” and that “[f]arming

activities would be able to resume within the pipeline easement following

completion of construction.” (Id.).

{¶8} Ultimately, on August 27, 2020, the OPSB concluded that Columbia

Gas’s letter-of-notification application satisfied the requirements enumerated under

R.C. 4906.10. Notably, the OPSB concluded that “Columbia [Gas] has

demonstrated the basis of need for the Project” since “the Marysville area requires

additional demand for natural gas and that the proposed Project, especially when

connected to Columbia’s Columbus Northern Loop system, will provide an

additional supply of natural gas.” (Case No. 21CV0112, Doc. No. 1, Ex. 17); (Case

No. 21CV0113, Doc. No. 1, Ex. 17).

{¶9} Furthermore, the OPSB concluded (based on the findings contained

within its staff report of investigation) that “[l]and use throughout the Project area

consists primarily of agricultural uses” and that “[t]he Project also crosses an

-5- Case No. 14-22-13 and 14-22-14

agricultural easement held by the [ODA]; however, the easement does not preclude

installation over or under the property for purposes of providing gas. Farming

activities can resume within the Project easement following completion of

construction.” (Id.); (Id.).

{¶10} As a result, the OPSB (conditionally) issued a certificate under R.C.

Chapter 4906 to Columbia Gas. Following the conditional approval of its

certificate, Columbia Gas sought to appropriate the necessary easement rights from

the respondents.

{¶11} However, when negotiations with the respondents failed, Columbia

Gas, filed a verified petition for the appropriation of easement rights in real property

on July 22, 2021 in the Union County Court of Common Pleas against Patrick,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hoover v. Pfeifer
2025 Ohio 4909 (Ohio Court of Appeals, 2025)
Adams v. DiSabato
2025 Ohio 1219 (Ohio Court of Appeals, 2025)
Luckey v. T&S Agriventures, L.L.C.
2025 Ohio 871 (Ohio Court of Appeals, 2025)
Columbia Gas of Ohio, Inc. v. Holloway
2023 Ohio 4257 (Ohio Court of Appeals, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2023 Ohio 1245, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbia-gas-v-bailey-ohioctapp-2023.