Crane Hollow, Inc. v. Marathon Ashland Pipe Line, LLC

740 N.E.2d 328, 138 Ohio App. 3d 57, 2000 Ohio App. LEXIS 2548
CourtOhio Court of Appeals
DecidedJune 6, 2000
DocketCase Nos. 99CA16, 99CA17, 99CA18.
StatusPublished
Cited by73 cases

This text of 740 N.E.2d 328 (Crane Hollow, Inc. v. Marathon Ashland Pipe Line, LLC) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crane Hollow, Inc. v. Marathon Ashland Pipe Line, LLC, 740 N.E.2d 328, 138 Ohio App. 3d 57, 2000 Ohio App. LEXIS 2548 (Ohio Ct. App. 2000).

Opinions

Kline, Presiding Judge.

Crane Hollow, Inc., the Metropolitan Park District of Columbus (“Metro Parks”), and a group of Hocking County landowners appeal the Hocking County Court of Common Pleas’ decision and judgment entry in favor of Marathon Ashland Pipe Line, LLC and Ohio River Pipe Line, LLC (collectively “Marathon”). Crane Hollow, Metro Parks and the other landowners assert that the trial court’s judgment regarding the width of the Marathon’s easement is against the manifest weight of the evidence and that its finding that the easement was not abandoned is against the manifest weight of the evidence. We disagree, because the record contains some competent, credible evidence supporting these findings. Crane Hollow, Metro Parks and the other landowners also assert that *64 the trial court abused its discretion by expanding the width of the easement in some areas. We disagree, because the trial court acted pursuant to its equitable jurisdiction and did not act arbitrarily, unreasonably, or unconscionably. Finally, Crane Hollow, Metro Parks, and the landowners assert that the trial court erred in determining that the Cooperative Agreement between Marathon and Metro Parks did not apply to the easement. We disagree, because the contract is ambiguous as a matter of law and because the trial court’s factual determination that the parties did not intend to include the easement in the Cooperative Agreement is supported by some competent, credible evidence.

Accordingly, we overrule each of Crane Hollow, Metro Parks, and the other landowners’ assignments of error and we affirm the judgment of the trial court.

I

Marathon recently acquired an existing easement, originally granted to the Ohio Fuel Supply Company, that crosses the properties of Crane Hollow, Metro Parks, Big Brothers/Big Sisters Association of Greater Columbus, Michael Daniels, Kirk and Debra Pierce, Larry Menchhofer, Barbara Holt, Julie Guda, Dennis Savage, Barbara Andreas, and Thomas and Teresa Amerine (collectively, “the landowners”). The grant provides the easement owner with “the right to lay a pipeline, and maintain, operate, repair, replace, and remove the same * * * [and] change the size of its pipes * * *.” The grant requires the easement owner to pay for any damages to crops or fences arising from its exercise of this right. The grant further provides the easement owner with “the right at any time to lay, maintain, operate, repair, replace and remove a second line of pipe along side of the first line, upon the payment of a like consideration, and subject to the same conditions * * *.” The granting document does not describe the easement’s width. The Ohio Fuel Supply Company acquired the easement in approximately 1916 and installed the buried pipeline known as the FR-25.

The FR-25 was used for the transportation of natural gas from 1916 until 1986, when its owner and Marathon’s direct predecessor in interest, Columbia Gas Transmission Corporation, capped off portions of the FR-25 due to deterioration. When Marathon acquired the FR-25 easement from Columbia, it notified the landowners of its intent to replace the FR-25 with a modern pipeline capable of carrying liquid petroleum. Marathon further notified the landowners that it would remove all trees within seventy-five feet of the FR-25 in order to replace it, and that it would maintain a fifty-foot clearing for maintenance purposes.

The ensuing dispute prompted the parties to file three separate lawsuits in the trial court, each seeking injunctions or declaratory relief. The trial court consolidated the three actions and conducted a bench trial.

*65 At trial, the landowners presented evidence of numerous large trees growing within seventy-five feet of the FR-25. They also presented evidence that portions of the FR-25 had not been used since 1986, and that it had rust holes in it. Additionally, they presented evidence that Columbia executed an agreement with Metro Parks (the “Cooperative Agreement”) that altered and limited the rights associated with the FR-25 on a few properties.

Marathon submitted historical evidence that large trees were used as forms for putting fire bends in pipes and as leverage anchors for moving heavy sections of pipe when the FR-25 was constructed. Large groups of men assisted by teams of oxen and horses constructed the FR-25. The construction process required a great deal of space to accommodate the men, animals, materials, and equipment.

Austin Cramer, a former Columbia employee who was in charge of maintaining the northern portion of the FR-25 from 1979 through 1995, testified that he cleared small trees and brush in a fifty-foot-wide strip surrounding the FR-25 on a regular basis. Cramer stated that he left large trees in place to avoid damaging the FR-25. Marathon submitted Cramer’s detailed daily logbooks in which he recorded his clearing activities. Cramer also testified about his coworker’s clearing activities that occurred on the southern portion of the FR-25.

Finally, Marathon presented evidence that the Cooperative Agreement applied only to pipelines that are part of the Crawford Storage Field and that the FR-25, while in the vicinity of the Crawford Storage Field, is not part of the Crawford Storage Field.

The trial court found that Marathon established, based upon its predecessor’s use and the landowners’ acquiescence, that the easement is fifty feet wide. The trial court further found that the width of the construction easement was established at seventy-five feet based upon use and acquiescence. The trial court also found that Columbia did not abandon the easement when it took the FR-25 out of service. Finally, the trial court found that the Cooperative Agreement did not apply to the FR-25 pipeline.

The landowners appeal, asserting the following assignments of error:

“I. The trial court’s decision that the width of the FR-25 easement was 50 feet based upon use and that the line was originally constructed in 1916 using 75 feet was against the manifest weight of the evidence.
“II. The trial court abused its discretion by expanding the width of the easement established by historical use and acquiescence.
“III. The trial court’s decision that the FR-25 easement was not abandoned on the property of appellants Daniels, Pierce and Metro Parks was against the manifest weight of the evidence.
*66 “IV. It was plain error for the trial court to conclude that the Cooperative Agreement between Columbus and Franklin County Metropolitan Park District and Columbia Gas did not prohibit or restrict the proposed replacement of the FR-25 line with Clear Creek Metro Park and that the Cooperative Agreement had been surrendered.”

II

In their first assignment of error, the landowners assert that the trial court’s determinations that Marathon’s predecessors (1) maintained the easement at a width of fifty feet and (2) used an area seventy-five feet in width to construct the FR-25 were against the manifest weight of the evidence.

A reviewing court will not reverse a judgment as being against the manifest weight of the evidence when the judgment is supported by some competent, credible evidence going to all the essential elements of the case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baber v. Mikolayczyk
2025 Ohio 2910 (Ohio Court of Appeals, 2025)
Worthy v. Hawthorne
2025 Ohio 1941 (Ohio Court of Appeals, 2025)
Corder v. Ohio Edison Co.
2024 Ohio 5432 (Ohio Supreme Court, 2024)
Garcia v. Ewais
2024 Ohio 3024 (Ohio Court of Appeals, 2024)
Prince v. Harper
2024 Ohio 521 (Ohio Court of Appeals, 2024)
Columbia Gas v. Bailey
2023 Ohio 1245 (Ohio Court of Appeals, 2023)
Johnson's Island Property Owners' Assn. v. Cianciola
2021 Ohio 1341 (Ohio Court of Appeals, 2021)
Hemmelgarn v. Huelskamp & Sons, Inc.
2019 Ohio 5298 (Ohio Court of Appeals, 2019)
Cliffs & Creeks, L.L.C. v. Swallie
128 N.E.3d 825 (Court of Appeals of Ohio, Seventh District, Belmont County, 2018)
Bond v. Halcon Energy Properties, Inc.
2017 Ohio 7754 (Ohio Court of Appeals, 2017)
Kilbane v. Polzner
2016 Ohio 8042 (Ohio Court of Appeals, 2016)
Brian Bash v. Textron Financial Corporation
834 F.3d 651 (Sixth Circuit, 2016)
Goralske v. Parsell
2016 Ohio 531 (Ohio Court of Appeals, 2016)
Savoy Hospitality, L.L.C. v. 5839 Monore St. Assocs., L.L.C.
2015 Ohio 4879 (Ohio Court of Appeals, 2015)
Mitiwanga Park Co. v. Sablack
2015 Ohio 3945 (Ohio Court of Appeals, 2015)
Dane Subdivision, Inc. v. Zimmer
2014 Ohio 4968 (Ohio Court of Appeals, 2014)
Am. Servicing Corp. v. Wannemacher
2014 Ohio 3984 (Ohio Court of Appeals, 2014)
Dunn v. Ransom
2013 Ohio 5116 (Ohio Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
740 N.E.2d 328, 138 Ohio App. 3d 57, 2000 Ohio App. LEXIS 2548, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crane-hollow-inc-v-marathon-ashland-pipe-line-llc-ohioctapp-2000.