Ohio Power Co. v. Bauer

573 N.E.2d 780, 60 Ohio App. 3d 57, 1989 Ohio App. LEXIS 3488
CourtOhio Court of Appeals
DecidedSeptember 6, 1989
DocketCA-382
StatusPublished
Cited by16 cases

This text of 573 N.E.2d 780 (Ohio Power Co. v. Bauer) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio Power Co. v. Bauer, 573 N.E.2d 780, 60 Ohio App. 3d 57, 1989 Ohio App. LEXIS 3488 (Ohio Ct. App. 1989).

Opinion

Milligan, J.

On November 14, 1951, appellees granted an easement to the Ohio Power Company, appellant, “to construct, erect, operate and maintain a line of towers and wires for the purpose of transmitting electric or other power, in, on, along, over, through or across” their farm property-

Towers were constructed and three 345-kilovolt wires were hung across the property. This “Central Muskingum Line” carries approximately 950,000 kilowatts of power and serves approximately 150,000 customers in western and central Ohio.

The conflict between the parties has boiled intermittently since 1975 when the power company ran a second circuit of three 345-kilovolt wires upon the previously constructed towers.

The record is peppered with instances of confrontation and denial of access by Wayne W. Bauer, appellee, including threats, obscenities, and repeated orders to stay off his property. Damage settlements, pursuant to the easement, were executed over the past fourteen years.

Appellee, in his own words, acknowledged that he has asked the power company to leave his property numerous times:

“I have a standard answer. They’ve been here so many times. Pay your damage and you can go. Bring your check. * * * We should settle old problems, the old damages, then talk about new ones. I never objected to them crossing the farm — don’t yet — if they get their damages paid.”

Ohio Power Company (“Ohio Power”) invoked the equitable jurisdiction of the Perry County Court of Common Pleas, seeking both a preliminary and permanent injunction to enjoin defendants (appellees) from interfering with its use and enjoyment of the easement and access.

On February 3, 1988, the trial court found that the defendants “have interfered with the rights granted the plaintiff by said easement,” and “[t]hat said refusal of the defendants *58 to grant access to said property by plaintiff during this litigation may produce or cause irreparable injury to plaintiff and, in consequence, a temporary injunction should be granted.”

Defendants were ordered to refrain from denying access to Ohio Power and the power company was specifically granted access to the premises of defendants “at a point designated by the defendants”; further, Ohio Power was ordered to “traverse the premises of the defendants as closely adjacent to said line as is feasible.”

On July 29,1988, following a hearing, the court found Wayne W. Bauer in contempt of the restraining order and imposed a ten-day jail sentence, suspended on condition of permitting access.

At a hearing on October 17, 1988, Wayne W. Bauer, in open court, volunteered to allow access to his property at designated points and to install necessary gates. The court ordered that Ohio Power install “the necessary culverts, said size to be mutually agreed upon.”

On March 27, 1989, the Perry County Court of Common Pleas issued a permanent injunction against defendants and their agents, restraining them from denying access to Ohio Power in the exercise of its rights of patrolling and maintaining the power lines.

The court further fixed the access determination mechanism and the mutual responsibilities of the parties relative to points of access:

“It is further ORDERED that Plaintiff [Ohio Power] shall gain access to the premises of the Defendants at a point designated by the Defendants and shall traverse the premises of the Defendants as closely adjacent to said transmission line as is feasible.
“It is further ORDERED that Defendants shall install all gates needed for Plaintiff to gain access to the real estate referred to herein and traverse the premises of the Defendants as closely adjacent to the transmission line as possible; that Plaintiff shall install all necessary culverts at a size mutually agreed upon by the parties; and that in the event of any damage done to the fences, drains, ditches, crops, stock or trees of the Defendants, said damages shall forthwith be compensated.
“It is further ORDERED that Defendants, Wayne W. Bauer and Helen H. Bauer, pay the costs of this action.”

From this judgment Ohio Power appeals assigning a single error:

Assignment of Error

“The trial court erred in imposing upon plaintiff-appellant restrictions and conditions upon its beneficial use and enjoyment of an unambiguous express easement when the restrictions and conditions imposed by the trial court are not contained in the express terms of the unambiguous easement and limit the rights expressly granted to plaintiff-appellant in the easement.”

The power company’s claim is that the judgment, imposing restrictions upon access to the one-hundred-foot right-of-way underlying the power lines and poles, is contrary to law. It argues:

“The plaintiff-appellant is entitled, under the terms of the easement, at its discretion, to use any of the lands of defendants-appellees to gain access to the towers and power lines located on defendants-appellees’ lands and to maintain its easement as it desires and the defendants-appellees may not restrict or limit that right in any way.” (Emphasis added.)

The access provisions of the 1951 easement provide, inter alia:

“TOGETHER with the right to said party of the second part [Ohio Power Co.], its successors and assigns, to place, erect, maintain, inspect, add *59 to the number of, and relocate at will, towers, crossarms, or fixtures, and string wires and cables, adding thereto from time to time, across, through or over the above described premises, to cut and, at its option, remove from said premises or the premises of the parties of the first part adjoining the same on either side, any trees, overhanging branches or other obstructions which may endanger the safety or interfere with the use of said towers or fixtures or wires attached thereto or any structure on said premises, and the right of ingress and egress to and over said above described primeses [sic], and any of the adjoining lands of the parties of the first part, at any and all times, for the purpose of patrolling the line, of repairing, renewing or adding to the number of said towers, structures, fixtures and wires, and for doing anything necessary or useful or convenient for the enjoyment of the easement herein granted; also the privilege of removing at any time any or all of said improvements erected upon, over, or on said land, together with the rights, easements, privileges and appurtenances in or to said lands which may be required for the full enjoyment of the rights herein granted; provided however, the said THE OHIO POWER COMPANY, its successors or assigns, shall further pay to us or our heirs or assigns the sum of Fifty Dollars ($50.00) for each tower erected on said lands, hereinbefore described, from time to time, whenever and as soon as any towers are erected thereon. Grantee will immediately repair or replace all fences, gates, drains and ditches damaged or destroyed by it on said premises or pay Grantor all damages done to the fences, drains, ditches, crops and stock on the premises herein described, caused by the construction, operation and maintenance of said lines.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dar Jen Farms, Inc. v. Ohio Power Co.
2023 Ohio 4612 (Ohio Court of Appeals, 2023)
Berry v. Bowling
2019 Ohio 898 (Ohio Court of Appeals, 2019)
Beatty v. Urbania
2019 Ohio 245 (Ohio Court of Appeals, 2019)
Watson v. Caldwell Hotel, LLC
91 N.E.3d 179 (Court of Appeals of Ohio, Seventh District, Noble County, 2017)
Gulas v. Tirone
919 N.E.2d 833 (Ohio Court of Appeals, 2009)
Stefanich v. Am. Elec. Power, 07 Ca 0045 (11-5-2007)
2007 Ohio 6108 (Ohio Court of Appeals, 2007)
Village of Walbridge v. Carroll
875 N.E.2d 144 (Ohio Court of Appeals, 2007)
Bayes v. Toledo Edison Co., Unpublished Decision (10-29-2004)
2004 Ohio 5752 (Ohio Court of Appeals, 2004)
Crane Hollow, Inc. v. Marathon Ashland Pipe Line, LLC
740 N.E.2d 328 (Ohio Court of Appeals, 2000)
Murray v. Lyon
642 N.E.2d 41 (Ohio Court of Appeals, 1994)
Ohio Edison Co. v. Dessecker
623 N.E.2d 1251 (Ohio Court of Appeals, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
573 N.E.2d 780, 60 Ohio App. 3d 57, 1989 Ohio App. LEXIS 3488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-power-co-v-bauer-ohioctapp-1989.