Intermount Distribution, Inc. v. Public Service Co. of North Carolina, Inc.

563 S.E.2d 626, 150 N.C. App. 539, 2002 N.C. App. LEXIS 572
CourtCourt of Appeals of North Carolina
DecidedJune 4, 2002
DocketCOA01-238
StatusPublished
Cited by3 cases

This text of 563 S.E.2d 626 (Intermount Distribution, Inc. v. Public Service Co. of North Carolina, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Intermount Distribution, Inc. v. Public Service Co. of North Carolina, Inc., 563 S.E.2d 626, 150 N.C. App. 539, 2002 N.C. App. LEXIS 572 (N.C. Ct. App. 2002).

Opinion

TIMMONS-GOODSON, Judge.

Public Service Company of North Carolina, Inc. (“PSNC”) appeals from an order granting partial summary judgment in favor of Intermount Distribution, Inc. (“Intermount”). The relevant facts are as follows: Intermount acquired title to certain property located in Henderson County, North Carolina from Bessie Riddle (“Riddle”). The land was subject to an easement acquired by PSNC from Riddle pursuant to a right-of-way agreement dated 7 October 1955. The agreement granted PSNC and its successors and assigns, the right to maintain, construct, replace, change the size of, or lay one or more *540 pipelines across the property for the transportation of natural gas and other materials that may be transported through a pipeline. The agreement gave PSNC the right to select the route by laying the first pipeline. Shortly after obtaining the right-of-way across the property, PSNC laid an eight-inch diameter high pressure transmission pipeline (“T-l”) for the transportation of natural gas from Gastonia, North Carolina to Asheville, North Carolina.

In late 1997, PSNC began installing its second pipeline (“T-1B”) on the property. The second pipeline was twelve inches in diameter and parallel to T-l. The installation of T-1B was necessary to satisfy increasing demands on its pipeline system in Western North Carolina. In March of 1998, PSNC sent a letter to Intermount concerning the installation of its proposed pipeline.

Before installing T-1B, PSNC learned that Intermount planned to construct a building to the east of T-l. In accordance with industry and its own regulations, PSNC had maintained for many years that its easement was thirty-five (35) feet to the west and fifteen feet (15) to the east. However, in an effort to accommodate Intermount’s construction plans, PSNC relocated its easement and constructed T-1B to the west of T-l rather than to the east, which gave Intermount an additional twenty feet east of T-l to start construction. This accommodation would keep any building construction fifteen feet from T-l and would also provide sufficient space to maneuver and operate any specialized equipment required to install, maintain, and repair the pipelines.

Intermount subsequently began to design and construct its building within ten feet of T-l. PSNC continued to advise Intermount that a clearance of fifteen feet was necessary for safety reasons. When PSNC refused to acquiesce, Intermount filed this action.

On 14 April 2000, PSNC moved for summary judgment. The only issue before the court was the enforceable width of the easement or right-of-way claimed by PSNC. On 21 December 2000, the court granted partial summary judgment holding that PSNC’s pipeline easement was eight inches wide. The court then certified that its order affected a substantial right of the parties, particularly PSNC, therefore providing the basis for this appeal.

The dispositive issue on appeal is whether the trial court erred in entering partial summary judgment in favor of Intermount and deter *541 mining, as a matter of law, that the actual width of PSNC’s easement is eight inches.

At the outset, we note that the denial of a motion for summary judgment is not typically appealable. See Lamb v. Wedgewood South Corp., 308 N.C. 419, 424, 302 S.E.2d 868, 871 (1983). Likewise, “[a] grant of partial summary judgment, because it does not completely dispose of the case, is an interlocutory order from which there is ordinarily no right of appeal.” Liggett Group v. Sunas, 113 N.C. App. 19, 23, 437 S.E.2d 674, 677 (1993). The order appealed from in the instant case granted partial summary judgment in favor of plaintiff and therefore, it is an interlocutory order. “As a general rule, a party has no right to immediate appellate review of an interlocutory order.” See Tise v. Yates Construction Co., 122 N.C. App. 582, 584,471 S.E.2d 102, 105 (1996). However, appeal from an interlocutory order is permissible under two specific statutory exceptions. Town Center Assoc. v. Y & C Corp., 127 N.C. App. 381, 384, 489 S.E.2d 434, 436 (1997). “First, if the order or judgment is final as to some but not all of the claims or parties, and the trial court certifies the case for appeal pursuant to N.C. Gen. Stat. § 1A-1, Rule 54(b), an immediate appeal will lie.” N.C. Dept. of Transportation v. Page, 119 N.C. App. 730, 734, 460 S.E.2d 332, 334 (1995). The order appealed from in the instant case contained the trial court’s certification pursuant to Rule 54(b). We now allow the appeal and address the merits of the case.

Summary judgment is appropriate if the “pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that any party is entitled to a judgment as a matter of law.” N.C. Gen. Stat. § 1A-1, Rule 56(c) (2001). The party moving for summary judgment has the burden of showing that either an essential element of the plaintiffs claim does not exist or that plaintiff cannot produce evidence to support an essential element of the claim. Evans v. Appert, 91 N.C. App. 362, 365, 372 S.E.2d 94, 96, disc. review denied, 323 N.C. 623, 374 S.E.2d 584 (1988). The evidence presented is viewed in the light most favorable to the non-movant. BruceTerminex Co. v. Zurich Ins. Co., 130 N.C. App. 729, 733, 504 S.E.2d 574, 577 (1998).

The deed in the instant case was created in 1955 and granted PSNC an easement for the purpose of laying, constructing, maintaining, operating, repairing, altering, replacing and removing pipelines, *542 for the transportation of natural gas, and other substances. Although the right-of-way agreement did not distinctly specify the width of the easement, the agreement provided that PSNC shall have “all other rights and benefits necessary or convenient for the full enjoyment or use of the rights herein granted including the right from time to time, to lay, construct, maintain, alter, repair, remove, change the size of, and replace one or more additional lines of pipe approximately parallel with the first pipe line laid by” PSNC.

We begin by noting that an easement deed, such as the one disputed in the instant case, is a contract. See Cochran v. Keller, 84 N.C. App. 205, 211, 352 S.E.2d 458, 462 (1.987), disc. review denied, 322 N.C. 605, 370 S.E.2d 244 (1988). “In North Carolina, it is an established principle that the possessor of an easement has all rights that are necessary to the reasonable and proper enjoyment of that easement.” Keller v. Cochran,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

COUNTY OF MOORE v. ACRES
M.D. North Carolina, 2020
Woodring v. Swieter
637 S.E.2d 269 (Court of Appeals of North Carolina, 2006)
Keener v. Arnold
589 S.E.2d 731 (Court of Appeals of North Carolina, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
563 S.E.2d 626, 150 N.C. App. 539, 2002 N.C. App. LEXIS 572, Counsel Stack Legal Research, https://law.counselstack.com/opinion/intermount-distribution-inc-v-public-service-co-of-north-carolina-inc-ncctapp-2002.