In re Application of Buckeye Wind, L.L.C.

2012 Ohio 878, 131 Ohio St. 3d 449
CourtOhio Supreme Court
DecidedMarch 6, 2012
Docket2010-1554
StatusPublished
Cited by15 cases

This text of 2012 Ohio 878 (In re Application of Buckeye Wind, L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Application of Buckeye Wind, L.L.C., 2012 Ohio 878, 131 Ohio St. 3d 449 (Ohio 2012).

Opinions

Lanzinger, J.

{¶ 1} This is the first time that we have reviewed an order involving the grant of authority to construct a proposed wind-powered electric generation facility. After full review of the record and consideration of the parties’ arguments, we hold that the order of the Power Siting Board should be affirmed because the board acted in accordance with all pertinent statutes and regulations.

I. Background

{¶2} The General Assembly enacted legislation, 2007 Am.Sub.S.B. No. 221, effective July 31, 2008, to require utilities to provide a portion of their electricity supply from alternative energy sources by 2025. See R.C. 4928.64 and 4928.65. The term “alternative energy resource” includes a “renewable energy resource.” R.C. 4928.64(A)(1). Wind energy is listed within the definition of “renewable energy resource.” R.C. 4928.01(A)(35). Under R.C. 4906.03, the board has been granted exclusive authority to issue certificates for construction, operation, and maintenance of major utility facilities.

{¶ 3} A private developer, Buckeye Wind, L.L.C. (“Buckeye”), developed a plan to build 70 wind turbines over approximately 9,000 acres in Champaign County, Ohio, where Buckeye perceived a favorable blend of wind, open land, and access to the electric power grid. This project is one of the first wind farms in Ohio. The wind farm’s expected generation capacity exceeded 126 megawatts, qualifying it under R.C. 4906.01(B)(1) as a “major utility facility” that required the approval of the board. R.C. 4906.03.

[450]*450{¶ 4} In April 2009, Buckeye filed with the board a 1,500-page application for a certificate of environmental compatibility and public need. See R.C. 4906.04. A group of neighboring landowners, Union Neighbors United (“UNU”), Robert and Diane McConnell, and Julia Johnson (collectively, “the neighbors”), opposed the application. Several other entities, including Champaign County and several local townships (collectively, “the county”), also intervened.

{¶ 5} The neighbors were concerned about noise and the turbines’ proposed setbacks of 914 feet from homes and 541 feet from property lines. Wind turbines such as those proposed by Buckeye can stand as tall as 328 feet, with a blade at the highest point being 492 feet high. The neighbors also raised issues of “shadow flicker,” a potentially annoying phenomenon caused by the swinging of turbine blades between the ground and the sun, and the possibility of blade detachment. Unlike landowner-lessors who host turbines, the neighbors received no compensation from Buckeye, and they also noted the effect the proposed' facility could have on property values. The board rejected most of the neighbors’ requests and approved construction of most of the proposed turbines.

{¶ 6} The county did not oppose the siting of the turbines but sought financial protection through bond requirements that would ensure that adequate money was available to (1) repair any roads damaged by the project and (2) remove (or “decommission”) the turbines if and when they became inoperable. The board agreed to require a $5,000 bond for the first year of operation. The county was dissatisfied with the bond amount as well as the fact that the Champaign County Engineer did not have final say on the amount.

{¶ 7} The county appealed, as did the neighbors. Buckeye intervened on behalf of the board. The county raised three propositions of law, the neighbors raised ten propositions of law, and the Ohio Farm Bureau filed an amicus brief urging affirmance.

II. Legal Analysis

A. The Board Conducted Appropriate Public Hearings

{¶ 8} In their ninth proposition of law, the neighbors argue that the board deprived the neighbors of “the statutory right to call and examine witnesses at the hearing.” Although the neighbors argue that the board has violated R.C. 4906.07(A) by failing to hold a full hearing and considering testimony from the opponents before acting on Buckeye’s application to construct wind turbines in Champaign County, the record belies this conclusion.

{¶ 9} First, appellants were active participants throughout the administrative process. The neighbors and the Ohio Farm Bureau Federation were allowed to intervene on July 31, shortly after Buckeye had filed its initial application on April 24, 2009. The townships of Goshen, Rush, Salem, Urbana, and Wayne, the [451]*451city of Urbana, the Urbana Country Club, the Board of Commissioners of Champaign County, the Champaign Telephone Company, and the Piqua Shawnee Tribe also were permitted to intervene in the proceedings before the board.

{¶ 10} Second, these intervening parties, as well as the general public, had an opportunity to be heard. A public informational hearing was held on June 10, 2008, shortly after Buckeye notified the board of its intention to apply for a construction certificate. After the application was filed and staff conducted its investigation, a local public hearing was held, in accordance with Ohio Adm.Code 4906-7-01(A), on October 28, 2009, in North Lewisburg, Ohio. The adjudicatory hearing began on October 27, was continued on November 9, and initial testimony concluded on November 20, 2009; rebuttal testimony was presented on December 1 and 2, 2009.

{¶ 11} Third, the intervenors conducted discovery before the hearing, participated in pretrial hearings, and filed motions to ensure the presentation of written testimony and of witnesses. Buckeye called 11 witnesses, the board staff called 8, and intervenors presented 17. Forty-six people testified at the local public hearing.

{¶ 12} Fourth, the board’s summary of the evidence, consideration of arguments for and against every point, and careful recitation of the requirements of R.C. 4906.10(A) are clearly presented in its opinion, order, and certificate, which was entered on March 22, 2009. The 101-page order is thorough and shows that the board considered all points of view, including the intervenors’ positions on every issue.

B. The Board Did Not Improperly Delegate Decisionmaking to Its Staff

{¶ 13} We stated in In re Application of Am. Transm. Sys., Inc., 125 Ohio St.3d 333, 2010-Ohio-1841, 928 N.E.2d 427, ¶ 20-21:

R.C. Chapter 4906, the board’s enabling statute, expressly allows the board to delegate many responsibilities to subordinates. * * * R.C. 4906.02(C) states, “The chairman of the public utilities commission may assign or transfer duties among the commission’s staff.” * * *
One responsibility, however, cannot be delegated: “the board’s authority to grant certificates under section 4906.10 of the Revised Code shall not be exercised by any officer, employee, or body other than the board itself.” R.C. 4906.02(C).

{¶ 14} Appellants argue that the board improperly delegated its decisionmaking authority because the order allows staff members to (1) approve new sites for three turbines, (2) review and accept plans regarding the design and siting of [452]*452electric-collection lines, transportation routing, tree clearing, emergency services, and complaint resolution, (3) resolve the maximum potential distance that a detached turbine blade could be thrown, and (4) determine the specific model of wind turbine to be used.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Application of S. Branch Solar, L.L.C.
2025 Ohio 5679 (Ohio Supreme Court, 2025)
In re Application of Harvey Solar I, L.L.C.
2025 Ohio 1503 (Ohio Supreme Court, 2025)
In re Application of Alamo Solar I, L.L.C.
2023 Ohio 3778 (Ohio Supreme Court, 2023)
In re Application of Icebreaker Windpower, Inc.
2022 Ohio 2742 (Ohio Supreme Court, 2022)
Biglin v. S (In re Black Fork Wind Energy, L. L.C.)
124 N.E.3d 787 (Ohio Supreme Court, 2018)
In re Application of Buckeye Wind, L.L.C. (Slip Opinion)
2016 Ohio 5664 (Ohio Supreme Court, 2016)
In re Application of Champaign Wind, L.L.C. (Slip Opinion)
2016 Ohio 1513 (Ohio Supreme Court, 2016)
In re Application of Black Fork Wind Energy, L.L.C.
2013 Ohio 5478 (Ohio Supreme Court, 2013)
In re Application of Buckeye Wind, L.L.C.
2012 Ohio 878 (Ohio Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
2012 Ohio 878, 131 Ohio St. 3d 449, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-buckeye-wind-llc-ohio-2012.