In re Application of Harvey Solar I, L.L.C.

2025 Ohio 1503
CourtOhio Supreme Court
DecidedApril 30, 2025
Docket2023-0793
StatusPublished
Cited by1 cases

This text of 2025 Ohio 1503 (In re Application of Harvey Solar I, L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Application of Harvey Solar I, L.L.C., 2025 Ohio 1503 (Ohio 2025).

Opinion

[Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as In re Application of Harvey Solar I, L.L.C., Slip Opinion No. 2025-Ohio-1503.]

NOTICE This slip opinion is subject to formal revision before it is published in an advance sheet of the Ohio Official Reports. Readers are requested to promptly notify the Reporter of Decisions, Supreme Court of Ohio, 65 South Front Street, Columbus, Ohio 43215, of any typographical or other formal errors in the opinion, in order that corrections may be made before the opinion is published.

SLIP OPINION NO. 2025-OHIO-1503 IN RE APPLICATION OF HARVEY SOLAR I, L.L.C., FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED TO CONSTRUCT A SOLAR- POWERED ELECTRIC-GENERATION FACILITY IN LICKING COUNTY, OHIO; SAVE HARTFORD TWP., L.L.C., ET AL., APPELLANTS; POWER SITING BOARD, APPELLEE; HARVEY SOLAR I, L.L.C., INTERVENING APPELLEE. [Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as In re Application of Harvey Solar I, L.L.C., Slip Opinion No. 2025-Ohio-1503.] Power Siting Board—R.C. 4906.10(A)—Solar-powered electric-generation facilities—Applications for certificates of environmental compatibility and public need—Board did not act unreasonably in making the determinations required by R.C. 4906.10(A)—Power Siting Board’s order granting certificate affirmed. (No. 2023-0793—Submitted January 7, 2025—Decided April 30, 2025.) APPEAL from the Power Siting Board, No. 21-164-EL-BGN. __________________ SUPREME COURT OF OHIO

DEWINE, J., authored the opinion of the court, which FISCHER, BRUNNER, DETERS, HAWKINS, and SHANAHAN, JJ., joined. KENNEDY, C.J., concurred in judgment only, with an opinion.

DEWINE, J. {¶ 1} The Ohio Power Siting Board authorized Harvey Solar I, L.L.C., to build a solar farm in Licking County. Save Hartford Twp., L.L.C., a citizens group, and 11 nearby residents1 appeal the board’s order to this court. (This opinion will refer to all appellants as “the residents.”) {¶ 2} Large-scale commercial solar farms have proved controversial in this State. Some tout their benefits in reducing dependence on fossil fuels and creating new jobs and development. Others argue that solar farms constitute an eyesore for affected communities, unnecessarily remove farmland from productive agricultural usages, and are costly and inefficient producers of energy. These competing viewpoints undergird this case. The residents assert that “the project’s masses of unsightly towering solar panels and substation will convert the community’s scenic country landscape into industrial blight” and that “[t]he solar project will remove 2,610 acres from food production.” Harvey Solar touts the benefits of its project in meeting Ohio’s “growing need for power generation,” creating construction jobs, and providing additional tax revenues for local communities. {¶ 3} Overarching public-policy questions about the general societal value of commercial solar farms are the province of the General Assembly, not this court. See State v. Parker, 2019-Ohio-3848, ¶ 37 (“It is the role of the legislature to weigh . . . competing policy concerns and make the public policy of this state. . . .”). The General Assembly has authorized commercial solar farms in Ohio. See R.C. Ch.

1. The nearby residents are Janeen Baldridge, Edward Bauman, Mary Bauman, Julie Bernard, Richard Bernard, Anthony Caito, John Johnson, Daniel Adam Lanthorn, Nancy Martin, Paul Martin, and Gary O’Neil.

2 January Term, 2025

4906. It has conditioned the construction of such facilities on approval of the Power Siting Board and provided the board with statutory guidelines that it must follow in making its determination about whether to approve a solar farm. See R.C. 4906.10. {¶ 4} Our task is to determine whether the Power Siting Board complied with the statutory criteria when it authorized construction of Harvey Solar’s solar farm. Under the standard for our review prescribed by the General Assembly, we may reverse the board’s order approving the solar farm if the residents establish that the order was unlawful or unreasonable. See R.C. 4903.13; R.C. 4906.12. Because we conclude that they have not done so, we affirm the board’s order. I. The Power Siting Board Approves the Harvey Solar Project {¶ 5} Before construction begins on a facility that will generate at least 50 megawatts of power, the Power Siting Board must issue a “certificate of environmental compatibility and public need,” R.C. 4906.01. R.C. 4906.04. In August 2021, Harvey Solar applied to build a solar farm in Hartford and Bennington Townships in Licking County that would generate up to 350 megawatts. {¶ 6} Multiple parties intervened in the matter, including the Village of Hartford, the Ohio Farm Bureau Federation, the Licking County Engineer, the Licking County Soil and Water Conservation District, the Hartford Township Board of Trustees, the Bennington Township Board of Trustees, and the residents. {¶ 7} The board staff investigated the potential impact of the project and submitted a report. Subsequently, Harvey Solar, the board staff, and most of the other intervening parties—except the residents—entered into a stipulation

3 SUPREME COURT OF OHIO

recommending that the board issue a construction certificate subject to 39 conditions.2 {¶ 8} The board held an evidentiary hearing and ultimately issued a decision and order amending and approving the stipulation and granting a certificate of construction for Harvey Solar’s facility. The facility will consist of rows of large solar panels mounted on metal racks, inverters and transformers, above- and below- ground collection cables, a substation, a network of access roads, and an operations and maintenance building. It will be constructed within a 2,630-acre area of land that Harvey Solar leases from private landowners. {¶ 9} After unsuccessfully seeking rehearing before the board, the residents appealed to this court. Harvey Solar intervened, see 2023-Ohio-2766, urging us to affirm the board’s order. II. The Residents Have Not Demonstrated that the Board’s Order Was Unreasonable or Unlawful {¶ 10} The General Assembly has set standards for the construction of major utility facilities in Ohio and delegated to the Power Siting Board the authority to implement those standards. Before the board may approve construction of a new major utility facility, it must make eight substantive determinations, which are set forth in R.C. 4906.10(A). Four of them are at issue in this appeal. The residents contend that the board failed to meet its obligations to find and determine the following under R.C. 4906.10(A):

(2) The nature of the probable environmental impact;

2. The Village of Hartford signed the stipulation but took no position on whether a certificate should be issued and instead requested that the conditions be included in any certificate that was issued. The Hartford Township Board of Trustees later modified its position to take no position on the stipulation.

4 January Term, 2025

(3) That the facility represents the minimum adverse environmental impact, considering the state of available technology and the nature and economics of the various alternatives, and other pertinent considerations; ... (5) That the facility will comply with [the water pollution requirements of] Chapter[] . . . 6111. of the Revised Code . . . ; [and] (6) That the facility will serve the public interest, convenience, and necessity[.]

{¶ 11} The General Assembly also has established the standard of review that we are to apply in reviewing the board’s determinations. We may only reverse, modify, or vacate a board order when, after considering the record, we conclude that the order “was unlawful or unreasonable.” R.C. 4903.13. Challengers to a board order bear the burden of establishing that the order is unlawful or unreasonable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Application of S. Branch Solar, L.L.C.
2025 Ohio 5679 (Ohio Supreme Court, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2025 Ohio 1503, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-harvey-solar-i-llc-ohio-2025.