In re Application of Icebreaker Windpower, Inc.

2022 Ohio 2742, 207 N.E.3d 651, 169 Ohio St. 3d 617
CourtOhio Supreme Court
DecidedAugust 10, 2022
Docket2021-0153
StatusPublished
Cited by6 cases

This text of 2022 Ohio 2742 (In re Application of Icebreaker Windpower, Inc.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Application of Icebreaker Windpower, Inc., 2022 Ohio 2742, 207 N.E.3d 651, 169 Ohio St. 3d 617 (Ohio 2022).

Opinion

[Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as In re Application of Icebreaker Windpower, Inc., Slip Opinion No. 2022-Ohio-2742.]

NOTICE This slip opinion is subject to formal revision before it is published in an advance sheet of the Ohio Official Reports. Readers are requested to promptly notify the Reporter of Decisions, Supreme Court of Ohio, 65 South Front Street, Columbus, Ohio 43215, of any typographical or other formal errors in the opinion, in order that corrections may be made before the opinion is published.

SLIP OPINION NO. 2022-OHIO-2742 IN RE APPLICATION OF ICEBREAKER WINDPOWER, INC., FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED FOR AN ELECTRIC GENERATING FACILITY IN CUYAHOGA COUNTY, OHIO; DEMPSEY ET AL., APPELLANTS; POWER SITING BOARD, APPELLEE; ICEBREAKER WINDPOWER, INC., INTERVENING APPELLEE. [Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as In re Application of Icebreaker Windpower, Inc., Slip Opinion No. 2022-Ohio-2742.] Power Siting Board—Offshore wind-powered electric-generation facility— Application for certificate of environmental compatibility and public need— R.C. 4906.10(A)—Power Siting Board’s order granting certificate subject to conditions affirmed—Board’s authority under R.C. 4906.10(A)(6) does not extend to the power to make public-trust determinations. (No. 2021-0153—Submitted December 7, 2021—Decided August 10, 2022.) APPEAL from the Power Siting Board, No. 16-1871-EL-BGN. __________________ SUPREME COURT OF OHIO

BRUNNER, J. {¶ 1} Appellee, the Ohio Power Siting Board (“the board”), approved the application of intervening appellee, Icebreaker Windpower, Inc. (“Icebreaker”), for a certificate of environmental compatibility and public need to build a six-turbine wind-powered electric-generation facility in Lake Erie. Appellants, W. Susan Dempsey and Robert M. Maloney (hereafter, “the residents”), who are residents of the village of Bratenahl on the southern shore of Lake Erie, have appealed the board’s decision granting the certificate, raising two propositions of law. First, they argue that there was insufficient evidence before the board for it to determine (1) the nature of the probable environmental impact of the project under R.C. 4906.10(A)(2) and (2) whether the project represents the minimum adverse environmental impact under R.C. 4906.10(A)(3). Second, they argue that the board’s decision to issue the certificate violated the public-trust doctrine and thus the project does not serve the public interest, convenience, and necessity under R.C. 4906.10(A)(6). {¶ 2} For the reasons discussed below, we affirm the board’s decision. I. FACTS AND PROCEDURAL BACKGROUND {¶ 3} On February 1, 2017, Icebreaker filed an application with the board for a certificate to build a six-turbine wind-powered electric-generation facility on approximately 4.2 acres of submerged land in Lake Erie located between eight and ten miles off the shore of Cleveland. The project would be the first freshwater offshore wind-powered electric-generation facility in North America. It has been described as a small-scale demonstration project that will provide valuable information as to how offshore wind facilities interact with the environment and that will test the viability of large-scale wind facilities on Lake Erie and the other Great Lakes. See Power Siting Bd. No. 16-1871-EL-BGN, ¶ 2 (May 21, 2020).

2 January Term, 2022

{¶ 4} The proposed wind farm’s estimated electric-generation capacity is 20.7 megawatts, making it an “economically significant wind farm,” R.C. 4906.13(A) and Ohio Adm.Code 4906-1-01(R), the construction of which requires the board’s approval, R.C. 4906.10 and 4906.20(A). R.C. 4906.10(A) provides that the board shall not grant a certificate for the construction, operation, and maintenance of a major utility facility unless it first makes eight substantive findings, including “[t]he nature of the probable environmental impact” of the facility, R.C. 4906.10(A)(2), and that “[t]he facility represents the minimum adverse environmental impact,” R.C. 4906.10(A)(3). {¶ 5} Several parties, including the residents, intervened before the board. The residents do not want the facility to be built on Lake Erie, because they fear that the project could lead to additional wind farms being built on the lake. The most contentious issue before the board was whether Icebreaker had sufficiently demonstrated under R.C. 4906.10(A)(2) and (3) the proposed facility’s probable environmental impact on birds and bats. The residents argued that the board could not determine the facility’s probable impact on birds and bats based on the evidence that Icebreaker had submitted. The residents also claimed that the project violates the public-trust doctrine, which provides that the state holds title to Lake Erie in trust for the benefit of the people of Ohio, State ex rel. Squire v. Cleveland, 150 Ohio St. 303, 82 N.E.2d 709 (1948), paragraph two of the syllabus. {¶ 6} On September 4, 2018, Icebreaker entered a joint stipulation with several parties that purported to resolve most of the issues in the case. The residents and the board’s staff opposed the stipulation. Icebreaker filed a revised stipulation on May 15, 2019. The staff joined the revised stipulation, leaving only the residents opposing Icebreaker’s application. {¶ 7} On May 21, 2020, the board issued an order approving the revised stipulation with certain modifications, thereby granting a certificate to Icebreaker for the proposed project, subject to certain conditions. The board found, contrary

3 SUPREME COURT OF OHIO

to the residents’ arguments, that Icebreaker had submitted sufficient evidence for the board to determine the probable environmental impact of the project on birds and bats. However, the board found it necessary to impose a different risk- mitigation measure than that which the revised stipulation proposed. The board therefore modified the stipulation to require that the turbines be nonoperational from dusk to dawn for eight months of the year until otherwise ordered by the board. The board reasoned that it was necessary to shut down the turbines during the specified times due to the lack of data regarding the actual impact that the project would have on birds and bats at the project site and some uncertainty regarding Icebreaker’s postconstruction collision-monitoring technology. {¶ 8} As for the residents’ argument that the project violated the public-trust doctrine, the board determined that it lacked jurisdiction over the issue. The board, however, went on to reject the argument that the project violated the public-trust doctrine. {¶ 9} The residents and Icebreaker both sought rehearing of the board’s order. On October 8, 2020, the board issued an entry denying the residents’ rehearing application. The board, however, granted Icebreaker’s rehearing application in part and removed the turbine-shutdown requirement imposed in the May 21 order. The board determined that it was unnecessary to impose that requirement because the order had approved a process ensuring that Icebreaker would provide the board with the necessary information both before construction of the wind farm and during its operation. Power Siting Bd. No. 16-1871-EL-BGN, ¶ 30-32, 36 (Oct. 8, 2020). {¶ 10} On November 5, 2020, the residents filed a rehearing application challenging the board’s removal of the turbine-shutdown requirement. The board did not rule on the rehearing application within 30 days; thus, it was denied by operation of law. See R.C. 4903.10(B).

4 January Term, 2022

{¶ 11} The residents appealed the board’s determination to this court as of right. The board and Icebreaker filed merit briefs defending the order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Application of S. Branch Solar, L.L.C.
2025 Ohio 5679 (Ohio Supreme Court, 2025)
In re Application of Harvey Solar I, L.L.C.
2025 Ohio 1503 (Ohio Supreme Court, 2025)
In re Application of Alamo Solar I, L.L.C.
2023 Ohio 3778 (Ohio Supreme Court, 2023)
Vandercar, L.L.C. v. Port of Greater Cincinnati Dev. Auth.
2022 Ohio 3148 (Ohio Court of Appeals, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2022 Ohio 2742, 207 N.E.3d 651, 169 Ohio St. 3d 617, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-icebreaker-windpower-inc-ohio-2022.