In re Application of Black Fork Wind Energy, L.L.C.

2013 Ohio 5478, 138 Ohio St. 3d 43
CourtOhio Supreme Court
DecidedDecember 18, 2013
Docket2012-0900
StatusPublished
Cited by60 cases

This text of 2013 Ohio 5478 (In re Application of Black Fork Wind Energy, L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Application of Black Fork Wind Energy, L.L.C., 2013 Ohio 5478, 138 Ohio St. 3d 43 (Ohio 2013).

Opinion

Kennedy, J.

{¶ 1} Appellants, Gary J. Biglin, Brett A. Heffner, Alan Price, Catherine Price, and John Warrington, appeal from an order of the Power Siting Board issuing a certificate to Black Fork Wind Energy, L.L.C., to construct a proposed wind-powered electric-generation facility, or wind farm, in portions of Richland and Crawford Counties. In their only remaining proposition of law, appellants argue that the board violated their “right to procedural due process by disallowing the appellants from conducting cross-examination on staff members” and “prohibiting the presentation of evidence” at the evidentiary hearing on Black Fork’s application to site the project. After review, we hold that the board did not prevent appellants from cross-examining any witness or presenting evidence, and therefore, appellants have not established that the board violated their due-process rights. Because appellants have not established that the board’s order is unlawful or unreasonable, the board’s order is affirmed.

I. Facts and Procedural History

A. The proposed project

{¶ 2} The Power Siting Board has exclusive authority to issue certificates of environmental compatibility and public need for construction, operation, and maintenance of “major utility facilities,” such as the proposed wind farm at issue here. In re Application of Buckeye Wind, L.L.C., 131 Ohio St.3d 449, 2012-Ohio-878, 966 N.E.2d 869, ¶ 2; R.C. 4906.01, 4906.03, and 4906.13. In March 2011, Black Fork filed an application to construct a wind farm consisting of up to 91 turbines in portions of Crawford and Richland Counties. In addition to the turbines, Black Fork’s project includes access roads, electrical collection lines, a *44 construction-staging area, a concrete-batch plant, a substation, and an operation and maintenance facility. The project area covers approximately 24,000 acres of land, and the facilities will be located on approximately 14,800 acres of leased private land with 150 participating landowners. According to Black Pork’s application, voluntary agreements have been signed by the participating property owners within the project area. Black Fork claims that the facility will provide up to 200 megawatts of renewable energy “with effectively zero air emissions and waste generation.”

B. Proceedings before the board

{¶ 3} Upon receipt of Black Fork’s application, the board’s staff conducted an investigation into the environmental and other impacts of the proposed wind farm, and on August 31, 2011, the staff filed a report recommending that 71 conditions become a part of any certificate issued for the proposed facility. By that time, intervening-party status had been granted to the following entities and individuals: the boards of commissioners of Crawford and Richland Counties; the Richland County engineer; the boards of trustees of Plymouth, Sharon, and Sandusky Townships; the Ohio Farm Bureau Federation; appellants, who claimed to live near the leased land or within the boundaries of the project area; and ten other local residents.

{¶ 4} Because appellants, as well as certain other parties, were acting pro se, the board’s administrative law judge (“ALJ”) believed that it was “important to provide some clarification of the procedures” prior to the evidentiary hearing. Accordingly, in an August 31, 2011 order, the ALJ explained that the purpose of the upcoming evidentiary hearing was “to allow the parties to the case the opportunity to present sworn testimony subject to cross-examination that will form the evidentiary record that the board will weigh and consider in arriving at its formal decision on the merits of the application.” The ALJ explained that the parties would

not only be allowed to present testimony at the evidentiary hearing (on their own behalf or through the testimony of witnesses that they bring to the hearing, so long as such testimony is timely filed by September 15, 2011), but [would] also have the right to cross-examine all other parties’ witnesses who appear and testify at the evidentiary hearing.

{¶ 5} Black Fork thereafter prefiled the direct testimony of ten witnesses that it planned to call at the evidentiary hearing, and the board’s staff prefiled the testimony of eight witnesses. Of the board’s staff witnesses, seven authored sections of the staffs report, and the eighth, Jon Pawley, managed the staffs *45 investigation and compiled the final report. Appellants prefiled their own written testimony, but they did not prefile the testimony of other witnesses.

{¶ 6} At the request of the board’s staff, an ALJ issued an entry prior to the scheduled September 19, 2011 evidentiary hearing, converting the first day of the hearing into a settlement conference. The ALJ also directed the staff and intervenors to bring to that settlement conference “a list of the witnesses they [would] be calling to testify at the evidentiary hearing, along with the dates that they [would] be available to testify.” Upon commencement of the settlement conference, one of the two ALJs present requested that the parties first discuss “the order of witnesses that might be scheduled.” After that off-the-record discussion, an ALJ summarized the schedule of witnesses as follows: Black Fork’s witnesses would testify on September 21, 22, and 23; the witnesses for the county commissioners and the township trustees would testify on the afternoon of September 23; the staff witnesses would testify on September 26 and 27; and the remaining intervenors would testify on September 28 and 30, if necessary.

{¶ 7} Settlement negotiations proved fruitful, and the date for the start of the evidentiary hearing was continued. Black Fork, the board’s staff, and the Ohio Farm Bureau Federation eventually entered into a joint stipulation recommending that the board approve the project subject to 71 conditions. The same ■ parties later filed an amendment to the stipulation that added nine conditions and included the approval of the Crawford County Board of Commissioners. None of the appellants signed the stipulation.

{¶ 8} The evidentiary hearing commenced on October 11, 2011. Each appellant participated in the hearing by cross-examining witnesses, including those from Black Fork, the board’s staff, and the county commissioners, and each appellant testified. Even though the staff had prefiled the testimony of eight witnesses, the only staff member who testified was Pawley, the project manager who had overseen the compilation of the staff report. Four appellants cross-examined Pawley; appellant Alan Price had no questions for him. No appellant objected to the introduction of Pawley’s testimony, to the staffs decision to present only Pawley, or to the fact that other board staff members were not present. And while appellant Warrington requested that Pawley’s testimony— and the hearing — be suspended so that a noise standard could be completed and reviewed by experts, the transcript does not indicate that Warrington, or any other appellant, requested that the hearing be suspended or continued so that they could subpoena additional staff witnesses or otherwise compel the attendance of more staff witnesses.

C. Appellants’ appeal

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Application of S. Branch Solar, L.L.C.
2025 Ohio 5679 (Ohio Supreme Court, 2025)
Lucas Cty. Children's Servs. v. Kujawski
2025 Ohio 5605 (Ohio Court of Appeals, 2025)
N. Star Med. Research, L.L.C. v. Kozlovich
2025 Ohio 5410 (Ohio Court of Appeals, 2025)
Richmond Hts. v. Turner
2025 Ohio 5347 (Ohio Court of Appeals, 2025)
Davis v. JLW Constr. Group, L.L.C.
2025 Ohio 5049 (Ohio Court of Appeals, 2025)
State v. Craig
2025 Ohio 4571 (Ohio Court of Appeals, 2025)
Am. Express Natl. Bank v. Reynolds
2025 Ohio 4470 (Ohio Court of Appeals, 2025)
Bykova v. Cleveland
2025 Ohio 3285 (Ohio Court of Appeals, 2025)
U.S. Bank Natl. Assn. v. Butts
2025 Ohio 3154 (Ohio Court of Appeals, 2025)
T.C. v. M.C.
2025 Ohio 2995 (Ohio Court of Appeals, 2025)
K&D Mgt., L.L.C. v. Marshall
2025 Ohio 1736 (Ohio Court of Appeals, 2025)
Bykova v. Cleveland Div. of Water
2025 Ohio 552 (Ohio Court of Appeals, 2025)
Gilles v. Castelli
2025 Ohio 460 (Ohio Court of Appeals, 2025)
Gadson v. Scott
2025 Ohio 7 (Ohio Court of Appeals, 2025)
Grace v. Geico Ins. Corporate Office
2024 Ohio 5815 (Ohio Court of Appeals, 2024)
Maleky v. Ohio State Univ., Office of Compliance & Integrity
2024 Ohio 5825 (Ohio Court of Appeals, 2024)
State v. Christian
2024 Ohio 4493 (Ohio Court of Appeals, 2024)
Habtemariam-Brown v. Christensen
2024 Ohio 4464 (Ohio Court of Appeals, 2024)
T.K. v. D.R.
2024 Ohio 3402 (Ohio Court of Appeals, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
2013 Ohio 5478, 138 Ohio St. 3d 43, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-black-fork-wind-energy-llc-ohio-2013.