In re Application of Am. Transm. Sys., Inc.

2010 Ohio 1841, 125 Ohio St. 3d 333
CourtOhio Supreme Court
DecidedMay 4, 2010
Docket2009-0481
StatusPublished
Cited by23 cases

This text of 2010 Ohio 1841 (In re Application of Am. Transm. Sys., Inc.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Application of Am. Transm. Sys., Inc., 2010 Ohio 1841, 125 Ohio St. 3d 333 (Ohio 2010).

Opinions

O’Donnell, J.

[334]*334Introduction

{¶ 1} Citizens Advocating Responsible Energy (“CARE”), a group of landowners in and around Geauga County, appeal as of right from an order of the Ohio Power Siting Board that authorized construction of an electric transmission line across their properties.

{¶ 2} CARE contends that two procedural errors invalidate the order: first, that the board delegated its decision-making authority to an administrative law judge (“ALJ”) in violation of R.C. 4906.02(C) and, second, that the board improperly sealed parts of the record, unreasonably granted only a two-week continuance when CARE had requested a four-week continuance, and ultimately denied CARE a fair opportunity to prepare for the hearing.

{¶ 3} In response, the Power Siting Board asserts that it — not the ALJ — made the decision to approve the new line, and it maintains that it correctly sealed some of the information in the record and that it gave CARE sufficient time to prepare for the hearing. The applicants, American Transmission Systems, Inc., and the Cleveland Electric Illuminating Company (collectively, “American Transmission”), have intervened as appellees and defend the board’s order on similar grounds.

{¶ 4} CARE’s arguments are not well taken. The order on its face demonstrates that the board issued it, and the record does not show that the board denied CARE a fair opportunity to prepare for the hearing. Accordingly, we affirm the order of the Power Siting Board.

Background

{¶ 5} In order to meet Geauga County’s growing demand for electricity, American Transmission planned to build a new substation. A substation is a point on the power grid where electricity, having been stepped up in voltage for more efficient, long-distance transmission, is stepped down for distribution on smaller lines. The needed substation would require a new transmission line, which in turn required a new right-of-way.

{¶ 6} To find a new right-of-way, American Transmission commissioned URS Corporation to perform a route-selection study. URS identified hundreds of possible routes, documented dozens of characteristics on each route, and assigned scores to each characteristic — the more onerous or expensive the condition, the more points assigned. URS then examined more closely the routes with the lowest and thus best scores.

{¶ 7} Using this study, American Transmission settled on two potential routes. One traveled primarily along a rural road and had a greater “land use” impact, which would have required taking several homes within the right-of-way. The other route (ultimately preferred by the company and approved by the board) [335]*335traveled primarily across open country. It did not require the taking of any homes but had greater ecological impact.

{¶ 8} In February 2007, American Transmission filed a notice with the board of its proposal to construct a new line to serve the new substation, as well as a public notice explaining the two routes under consideration. It then held a public informational meeting on March 5, where affected landowners voiced their concerns regarding each route.

{¶ 9} On September 28, 2007, American Transmission filed its 1,300-page application proposing the cross-country route as the preferred route and the rural-road route as the alternate. In September and November, before any other parties had intervened, the company sought protective, trade-secret status for certain information, including a study that described power flows across its network.

{¶ 10} On January 15, 2008, CARE filed its motion to intervene.

{¶ 11} An ALJ conducted proceedings on behalf of the Power Siting Board. On March 3, 2008, the ALJ granted CARE’s motion to intervene and American Transmission’s motion for a protective order. CARE did not challenge the decision to seal parts of the record at that time.

{¶ 12} Discovery proceeded, and CARE eventually sought information subject to the protective order. American Transmission declined to provide the information until it reached a protective agreement with CARE, which took almost 14 weeks. Due to this delay, on August 7, 2008, CARE filed a motion to continue the September 2 hearing for at least four weeks, arguing that “it [was] not logistically possible * * * to be ready for the adjudicatory hearing by September 2, 2008.”

{¶ 13} One week later, on August 14, the ALJ continued the hearing until September 16 — that is, for two weeks and not the four weeks requested by CARE. CARE did not object to this ruling before the hearing. Though it could have, it did not seek reconsideration, ask for interlocutory review by the board, or file another motion for continuance.

{¶ 14} On September 12 — less than a week before the hearing, more than six months after the ALJ granted the protective order, and after it had the sealed information — CARE, for the first time, challenged the decision to seal parts of the record. Significantly, its motion to unseal did not request more time to prepare.

{¶ 15} On September 16, the first day of the hearing, the ALJ denied CARE’s motion to unseal, as well as two unrelated motions to strike. The ALJ then asked, “Are there any other matters, procedural matters, before we start the testimony?” CARE’s counsel did not then object that the board had given [336]*336CARE an inadequate opportunity to prepare. Indeed, CARE’s counsel said nothing. During oral argument, counsel stated that CARE had objected to the two-week continuance “at the commencement of the hearing,” but the record contradicts this assertion.

{¶ 16} On November 24, 2008, the board issued its opinion and order authorizing the preferred, cross-country route (with 43 additional conditions proposed by the board’s staff). CARE timely applied for rehearing, which the board denied on January 26, 2009. The present appeal as of right ensued. R.C. 4903.13.

Standard of Review

{¶ 17} “Pursuant to R.C. 4906.12, this court must apply the same standard of review to Power Siting [Board] determinations as we apply to orders by the Public Utilities Commission.” Chester Twp. v. Power Siting Comm. (1977), 49 Ohio St.2d 231, 238, 3 O.O.3d 367, 361 N.E.2d 436. R.C. 4903.13 applies to board proceedings pursuant to R.C. 4906.12 and provides that an order “shall be reversed, vacated, or modified by this court only when, upon consideration of the record, the court finds the order to be unlawful or unreasonable.” Constellation NewEnergy, Inc. v. Pub. Util. Comm., 104 Ohio St.3d 530, 2004-Ohio-6767, 820 N.E.2d 885, ¶ 50. Regarding procedural matters, the board “has the discretion to decide how * * * it may best proceed to manage and expedite the orderly flow of its business, avoid undue delay and eliminate unnecessary duplication of effort.” Toledo Coalition for Safe Energy v. Pub. Util. Comm. (1982), 69 Ohio St.2d 559, 560, 23 O.O.3d 474, 433 N.E.2d 212; compare R.C. 4901.13 (authorizing the commission to adopt “rules to govern its proceedings”) with R.C. 4906.03(C) (authorizing the board to adopt “rules [that] are necessary and convenient to implement this chapter”).

The Delegation Issue

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Application of E. Ohio Gas Co.
2023 Ohio 3289 (Ohio Supreme Court, 2023)
In re Application of Duke Energy Ohio, Inc. (Slip Opinion)
2021 Ohio 3301 (Ohio Supreme Court, 2021)
Goree v. Northland Auto Ents. Inc.
2020 Ohio 3457 (Ohio Court of Appeals, 2020)
In re T.M.
2019 Ohio 4552 (Ohio Court of Appeals, 2019)
Corrigan v. Illum. Co. (Slip Opinion)
2017 Ohio 7555 (Ohio Supreme Court, 2017)
State v. Brice
2017 Ohio 974 (Ohio Court of Appeals, 2017)
Smith v. Ohio Edison Co.
2015 Ohio 4540 (Ohio Court of Appeals, 2015)
Brenneman Bros. v. Allen Cty. Commrs.
2015 Ohio 148 (Ohio Court of Appeals, 2015)
Fultz v. Fultz
2014 Ohio 3344 (Ohio Court of Appeals, 2014)
In re E. A.
2014 Ohio 280 (Ohio Court of Appeals, 2014)
In re Application of Black Fork Wind Energy, L.L.C.
2013 Ohio 5478 (Ohio Supreme Court, 2013)
In re Complaint of Smith v. Ohio Edison Co.
2013 Ohio 4070 (Ohio Supreme Court, 2013)
In re Application of Buckeye Wind, L.L.C.
2012 Ohio 878 (Ohio Supreme Court, 2012)
In re Application of Middletown Coke Co.
2010 Ohio 5725 (Ohio Supreme Court, 2010)
In re Application of Am. Transm. Sys., Inc.
2010 Ohio 1841 (Ohio Supreme Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
2010 Ohio 1841, 125 Ohio St. 3d 333, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-am-transm-sys-inc-ohio-2010.