In re Application of Ohio Power Co. (Slip Opinion)

2014 Ohio 4271, 20 N.E.3d 699, 140 Ohio St. 3d 509
CourtOhio Supreme Court
DecidedOctober 7, 2014
Docket2013-0154
StatusPublished
Cited by13 cases

This text of 2014 Ohio 4271 (In re Application of Ohio Power Co. (Slip Opinion)) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Application of Ohio Power Co. (Slip Opinion), 2014 Ohio 4271, 20 N.E.3d 699, 140 Ohio St. 3d 509 (Ohio 2014).

Opinion

Kennedy, J.

Summary

{¶ 1} In the case below, the Public Utilities Commission authorized the Ohio Power Company to recover costs associated with providing transmission service to its standard-service-offer customers (those who take generation service from the incumbent distribution utility instead of buying it on the market). The cost of transmission service is set by the Federal Energy Regulatory Commission (“FERC”). Under Ohio law, electric-distribution utilities are allowed to recover from their retail customers all transmission-related costs imposed on the utility *510 by FERC or by an organization approved by FERC. R.C. 4928.05(A)(2). Ohio Power recovers these costs through a reconciling rate mechanism called the Transmission Cost Recovery Rider (“TCRR”). Ohio Adm.Code 4901:l-36-03(A). The commission annually reviews and adjusts the TCRR to ensure that the utility is recovering only its actual costs of providing the service. Ohio Adm.Code 4901:l-36-03(B). By commission rule, shopping customers — those who shop for electric service from a competitive supplier — bypass the TCRR and thus avoid having to pay the rider. Ohio Adm.Code 4901:l-36-04(B).

2} During the period under review in this case, Ohio Power reported that it had underrecovered $36 million in transmission costs. The commission’s order determined that Ohio Power could collect the underrecovered costs from both shopping and nonshopping customers. The commission found that a large percentage of shopping customers who were receiving transmission service from Ohio Power at the time the underrecovery was created had since decided to take service from an alternative generation provider. Although these shopping customers would normally be able to avoid paying the TCRR, the commission reasoned that it would be unfair to require nonshopping customers to shoulder the entire burden of paying for the underrecovery, since the underrecovery was caused in part by these shopping customers.

{¶ 3} Industrial Energy Users-Ohio (“IEU”) challenges the commission’s decision to allow the company to recover the underrecovered transmission costs from shopping customers. For the reasons discussed in detail below, we affirm the commission.

Facts and Procedural Background

{¶ 4} Since competition began in the provision of electric-generation service, the law has required incumbent electric-distribution utilities to transfer control of their transmission assets to “one or more qualifying transmission entities.” R.C. 4928.12(A). On October 1, 2004, Ohio Power transferred control of its transmission assets to PJM Interconnection, L.L.C., one of six regional power grids regulated by FERC. 1 PJM, a qualifying entity under R.C. 4928.12(B)(1), now coordinates and directs the operation of Ohio Power’s transmission network.

{¶ 5} Ohio Power, as a member of PJM, is charged for securing transmission service through the organization. Currently, PJM bills Ohio Power based on rates set by FERC for transmission service associated with serving the company’s customer load. In turn, Ohio law permits Ohio Power (and all other electric- *511 distribution utilities) to recover from the utility’s retail customers the FERCapproved transmission charges billed by PJM. R.C. 4928.05(A)(2) (allowing electric distribution utilities to recover “all transmission and transmission-related costs * * * imposed on or charged to the utility by * * * a regional transmission organization * * * approved by” FERC). This provision authorizes the commission to provide for recovery through a “reconcilable rider” added to the electric utility’s distribution rates. Id.

{¶ 6} Consistent with this statutory provision, Ohio Power asked the commission to approve the TCRR to recover such costs as part of the company’s first Electric Security Plan (“ESP”). The commission approved the TCRR as proposed by the company. See In re Application of Columbus S. Power Co. for Approval of Elec. Sec. Plan, Pub. Util. Comm. Nos. 08-917-EL-SSO and 08-918-EL-SSO, 49-50 (Mar. 18, 2009). The TCRR was then carried over as part of Ohio Power’s second and current ESP, covering 2012 through 2014. See Pub. Util. Comm. Nos. 11-346-EL-SSO, 5, 63-64 (Aug. 8, 2012).

{¶ 7} The TCRR is structured as a pass-through mechanism, meaning that it is designed so that Ohio Power can recover the same amount in transmission costs from its customers as the amount billed by PJM. Once a year Ohio Power projects the amount of transmission costs it expects to be billed by PJM, and those costs are used as a revenue requirement to calculate the TCRR rate over the next 12-month period. Because the costs included in the TCRR are based on projections that will vary from actual costs, the TCRR contains a true-up mechanism to reconcile any over- or underrecovered charges from the preceding 12-month period.

{¶ 8} Pursuant to Ohio Adm.Code 4901:l-36-03(B), Ohio Power files an application each year with the commission to update the rates charged under the TCRR and to reconcile any over- or underrecoveries stemming from the prior period. R.C. 4928.05(A)(2) and Ohio Adm.Code 4901:l-36-03(B). This case began when Ohio Power filed an application with the commission to update the TCRR rates for the period from September 2012 through August 2013. The application reflected that Ohio Power’s TCRR had failed to recover enough revenue to recoup the costs that Ohio Power incurred to provide transmission service during the period of July 2011 through June 2012.

{¶ 9} The amount of underrecovered transmission costs was approximately $36 million. According to Ohio Power, these underrecovered costs were caused primarily by (1) the difference between the costs projected in the company’s most recent TCRR update ease and the actual costs incurred to provide transmission service over that period (i.e., transmission charges billed to Ohio Power by PJM from July 2011 through June 2012) and (2) a substantial increase (from less than *512 10 percent to nearly 40 percent) in the number of customers in Ohio Power’s service territory shopping for generation service.

{¶ 10} Ohio Power would normally recoup any underrecovered amounts through the TCRR over the next 12-month period. But to mitigate the impact of the rate increase on customers, Ohio Power proposed to collect the underrecovery balance with carrying charges over a three-year period. By commission rule, the TCRR is imposed on Ohio Power’s standard-service-offer customers since these customers are the ones who were provided the transmission service. Ohio Adm.Code 4901:1-36~04(B). Therefore, customers can avoid paying the TCRR by choosing to shop for generation service from a competitive supplier. 2 Ohio Power proposed that the rate impact could be further mitigated by collecting the underrecovered costs from all customers (shopping and nonshopping) pursuant to R.C. 4928.144.

{¶ 11} As an initial matter, the commission determined that it was not necessary to hold an evidentiary hearing in the case. In re Application of Ohio Power Co. to Update the Co.’s Transmission Cost Recovery Rider, Pub. Util. Comm. No. 12-1046-EL-RDR, 6 (Oct. 24, 2012) (the “TCRR Order”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ohio 4271, 20 N.E.3d 699, 140 Ohio St. 3d 509, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-ohio-power-co-slip-opinion-ohio-2014.