Monongahela Power Co. v. Public Utilities Commission

2004 Ohio 6896, 104 Ohio St. 3d 571
CourtOhio Supreme Court
DecidedDecember 30, 2004
Docket2004-0305
StatusPublished
Cited by62 cases

This text of 2004 Ohio 6896 (Monongahela Power Co. v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Monongahela Power Co. v. Public Utilities Commission, 2004 Ohio 6896, 104 Ohio St. 3d 571 (Ohio 2004).

Opinions

Lundberg Stratton, J.

Background

{¶ 1} This is an appeal as of right by Monongahela Power Company (“Mon Power”) from decisions of the Public Utilities Commission of Ohio in In the Matter of the Application of the Monongahela Power Co. for Approval of a Market-Based Standard Serv. Offer & Competitive Bidding Process (Oct. 22, 2003) case No. 03-1104-EL-ATA, 2003 WL 22472140 (the “MBSSO case”). Mon Power was the applicant, and Industrial Energy Users-Ohio (“IEU”) was an intervening party in the MBSSO case. IEU has also intervened as an appellee in this appeal.

{¶ 2} The legal backdrop for this appeal is Am.Sub.S.B. No. 3, 148 Ohio Laws, Part IV, 7962, 7992 (“S.B. 3”), codified primarily at R.C. 4928.01 et seq., which restructures Ohio’s electric-utility industry so as to achieve retail competition in the generation component of electric-utility service. Under S.B. 3, utilities supplying electric service in Ohio were required to file transition plans for approval by the commission. R.C. 4928.31. Key to these transition plans were the unbundling of the three main components of electric service — generation, transmission, and distribution — and developing a “rate unbundling plan.” R.C. 4928.31(A)(1). The unbundled retail rates, including rates for generation service, were capped and frozen for a limited transition period known as the “market development period” (“MDP”). After that period, a utility is entitled to charge market-based retail-generation rates that permit it to recover its cost of purchasing power at wholesale for resale to its customers. R.C. 4928.14.

{¶ 3} On June 22, 2000, in its restructuring case, Mon Power entered into a settlement agreement, styled a “Stipulation and Recommendation” (“the Stipulation”), with the commission’s staff and with representatives of Mon Power’s Ohio retail customers. The Stipulation purported to resolve all issues pertinent to Mon Power’s statutorily required transition plan. The commission approved the Stipulation in its October 5, 2000 opinion and order in its case No. 00-02-EL-ETP, 2000 WL 1873291 (the “ETP1 Order”).

[573]*573{¶ 4} On April 24, 2003, Mon Power filed an application in the MBSSO case, seeking commission approval of a market-based standard service offer and a competitive bidding process to follow the MDP, which Mon Power asserts ended December 31, 2003. On July 24, 2003, the commission issued an order allowing Mon Power to solicit bids for power to serve its large commercial, industrial, and street-lighting customers. Mon Power then conducted the bidding process. Only two qualifying bids were received, the lower of which was from an affiliate of Mon Power.

{¶ 5} On October 22, 2003, the commission issued an order in the MBSSO case (“the MBSSO Order”) denying approval of the winning bid and requiring Mon Power to continue its MDP to December 31, 2005, based on a finding that neither of the controlling statutory conditions for early ending of the MDP had been satisfied. Mon Power then filed an application for rehearing, which was denied on December 17, 2003. This appeal ensued.

MDP and its Early Ending

{¶ 6} While the subject of this appeal is the MBSSO Order issued on October 22, 2003, we must consider the ETP Order and the Stipulation that the commission approved in the ETP Order. In addition, we must focus on the meanings of the Stipulation’s provisions.

{¶ 7} Central to this appeal is whether the Stipulation approved by the commission in the ETP Order shortened Mon Power’s MDP with respect to its large commercial and industrial customers. The MDP is a statutorily defined term: “ ‘Market development period’ for an electric utility means the period of time beginning on the starting date of competitive retail electric service and ending on the applicable date for that utility as specified in section 4928.40 of the Revised Code, irrespective of whether the utility applies to receive transition revenues under this chapter.” R.C. 4928.01(A)(17). The starting date of competitive retail electric service was January 1, 2001. R.C. 4928.01(A)(29). Thus, Mon Power’s MDP began on that date.

{¶ 8} The end of the MDP is also specified by statute. R.C. 4928.40(B)(2) provides:

{¶ 9} “For purposes of this chapter, the market development period shall not end earlier than December 31, 2005, unless, upon application by an electric utility, the commission issues an order authorizing such earlier date for one or more customer classes as is specified in the order, upon a demonstration by the utility and a finding by the commission of either of the following:

{¶ 10} “(a) There is a twenty per cent switching rate of the utility’s load by the customer class.

{¶ 11} “(b) Effective competition exists in the utility’s certified territory.”

[574]*574{¶ 12} Based on these statutory provisions, we conclude that Mon Power’s MDP could end no later than December 31, 2005, but that it could end earlier if pertinent criteria are met.

{¶ 13} Mon Power argues that the commission approved an early end of its MDP as to its large commercial and industrial customers when, in the ETP Order, the commission approved the Stipulation that provided in Section IV: “For customers on the Company’s Rate Schedule C with a demand greater than 300 kW, Rate Schedules CSH, D, K, P, and street lighting, the market development period shall be a three year period and end December 31, 2003.” (Emphasis added.) Mon Power further asserts: “Section IV of the Stipulation recognized that R.C. 4928.40(B)(2) provides that the market development period may not end earlier than December 31, 2005, unless, upon application by the electric utility, the Commission authorizes an earlier termination date for one or more customer classes based upon either a finding of a 20 percent switching rate of load by the customer class or that effective competition exists in the utility’s certified territory. Accordingly, in § IV of the Stipulation, Mon Power made an application to end the market development period early for its large commercial and industrial customers.”

{¶ 14} Mon Power argues that by adopting the Stipulation in its ETP Order, the commission approved the early ending of the MDP for large commercial and industrial customers with no contingency involving future proceedings or future findings by the commission. Mon Power bases its argument on the observation that Section IV of the Stipulation provides that the MDP for small (300kW and below) commercial customers was not shortened and that, in order to end the MDP for those customers early, Mon Power would have to make separate application in the future under R.C. 4928.40(B)(2): “For either Schedule B customers and/or Schedule C customers having demands of 300 kW and below, the market development period can be terminated at any time by the Company making a filing with the Commission showing a 20% switching rate or effective competition.” Mon Power argues that since the Stipulation contains a specific qualification of further commission approval to shorten the MDP for small commercial customers but does not impose such a qualification on Mon Power to shorten the MDP for its large commercial and industrial customers, no such qualification exists.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Application of Ohio Power Co.
2024 Ohio 2890 (Ohio Supreme Court, 2024)
In re Application of Alamo Solar I, L.L.C.
2023 Ohio 3778 (Ohio Supreme Court, 2023)
In re Establishing the Solar Generation Fund Rider
2022 Ohio 4348 (Ohio Supreme Court, 2022)
Corrigan v. Illum. Co. (Slip Opinion)
2017 Ohio 7555 (Ohio Supreme Court, 2017)
In re Application of Duke Energy Ohio, Inc. (Slip Opinion)
2017 Ohio 5536 (Ohio Supreme Court, 2017)
In re Application of Ohio Edison Co. (Slip Opinion)
2016 Ohio 3021 (Ohio Supreme Court, 2016)
In re Application of Columbus S. Power Co. (Slip Opinion)
2016 Ohio 1608 (Ohio Supreme Court, 2016)
In re Application of Champaign Wind, L.L.C. (Slip Opinion)
2016 Ohio 1513 (Ohio Supreme Court, 2016)
In re Complaint of Pilkington N. Am., Inc. (Slip Opinion)
2015 Ohio 4797 (Ohio Supreme Court, 2015)
In re Ohio Power Co.
40 N.E.3d 1060 (Ohio Supreme Court, 2015)
In re Application of Ohio Power Co. (Slip Opinion)
2014 Ohio 4271 (Ohio Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2004 Ohio 6896, 104 Ohio St. 3d 571, Counsel Stack Legal Research, https://law.counselstack.com/opinion/monongahela-power-co-v-public-utilities-commission-ohio-2004.