In re Application of Ohio Edison Co. (Slip Opinion)

2016 Ohio 3021, 54 N.E.3d 1218, 146 Ohio St. 3d 222
CourtOhio Supreme Court
DecidedMay 18, 2016
Docket2013-0513
StatusPublished

This text of 2016 Ohio 3021 (In re Application of Ohio Edison Co. (Slip Opinion)) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Application of Ohio Edison Co. (Slip Opinion), 2016 Ohio 3021, 54 N.E.3d 1218, 146 Ohio St. 3d 222 (Ohio 2016).

Opinion

O’Connor, C.J.

{¶ 1} Appellants, Northeast Ohio Public Energy Council (“NOPEC”) and the Environmental Law and Policy Center (“ELPC”), appeal the decision of the Public Utilities Commission of Ohio (“PUCO”) approving an electric-security plan proposed by intervening appellees, the FirstEnergy Companies (Ohio Edison Company, Cleveland Electric Illuminating Company, and Toledo Edison Compa *223 ny (collectively, “FirstEnergy”)). For the reasons explained below, we affirm the commission’s order.

Background

{¶ 2} An electric-distribution utility is required to provide a “standard service offer” to all consumers in its certified territory. R.C. 4928.141(A). The utility may, at its discretion, base the standard service offer on either a market-rate offer (“MRO”) or an electric-security plan (“ESP”). Id.

{¶ 3} An MRO must be determined through a competitive-bidding process,' open to all generation suppliers. R.C. 4928.142(A)(1). A utility has considerably more flexibility to fashion a rate plan as an ESP. In re Application of Columbus S. Power Co., 134 Ohio St.3d 392, 2012-Ohio-5690, 983 N.E.2d 276, ¶ 4 (Ohio law “does not provide a detailed mechanism for establishing rates under an ESP”). The only substantive requirement is that the plan must be “more favorable in the aggregate as compared to the expected results” of an MRO. R.C. 4928.143(C)(1).

FirstEnergy’s first two applications

{¶ 4} On October 20, 2009, FirstEnergy filed an application for a standard service offer based on an MRO (“the MRO case”). After reviewing the MRO application, the commission staff recommended that FirstEnergy instead pursue an ESP.

{¶ 5} On March 23, 2010, in response to the staffs suggestion, FirstEnergy submitted an application for an ESP (“ESP 2”). The proposed plan would govern the purchase and supply of power for the period between June 1, 2011, and May 31, 2014.

{¶ 6} In its application, FirstEnergy proposed to establish a competitive bid process for electric power. The key feature of the bid process was that suppliers would not have to purchase all the power needed for the life of the plan in a single auction. Instead, at the outset, bidders could purchase energy to be supplied over variable time increments. And the plan called for a total of four auctions, two in 2010, a third in July 2011, and a final auction in July 2012. By offering multiple auctions and multiple options for the length of the contracts, the companies claimed that they could mitigate market fluctuations and stabilize prices over the life of the plan.

{¶ 7} The application proposed a number of riders by which the suppliers could recover various costs from consumers. One was the Delivery Capital Recovery Rider, which would permit recovery of certain costs, including the investment costs for improving delivery systems. The plan also proposed a rider allowing suppliers to meet their renewable-energy-resource requirements and recover the associated costs incurred that year.

*224 {¶ 8} In addition, FirstEnergy agreed not to seek recovery of a number of charges. Of particular significance, the companies agreed to forego recovery of regional-transmission-expansion-planning costs, at an estimated cost of $360 million.

{¶ 9} On April 25, 2010, the commission approved FirstEnergy’s ESP 2 application, and FirstEnergy began implementing the terms of the ESP 2.

FirstEnergy’s third application

{¶ 10} On April 13, 2012, with two years left on the ESP 2 plan, FirstEnergy filed an application to extend the plan through May 31, 2016 (“ESP 3”). The ESP 3 application consisted of supporting materials including a five-page summary, a partial stipulation signed by some but not all parties in the case agreeing on certain matters related to the application, and the prefiled testimony of William R. Ridmann, a company witness.

{¶ 11} Ridmann’s testimony summarized the provisions of the proposed ESP 3 and identified the changes it would make to the existing plan. However, Ridmann’s testimony did not explain or support numerous aspects of the proposed ESP 3. Responding to some parties’ concerns, and in anticipation of a hearing, FirstEnergy made supplemental submissions of evidence, including prefiling the testimony of commission staff witness Robert B. Fortney.

{¶ 12} The matter eventually went to hearing on June 4, 2012. The original ESP 3 application had “requested] that the Commission take administrative notice of the evidentiary record established in” the ESP 2 proceedings. On the first day of the hearing, FirstEnergy verbally renewed its request-for administrative notice of the record from the ESP 2. The attorney examiner declined to admit the entire record wholesale but invited FirstEnergy to make a document-by-document request.

{¶ 13} Two days later, on June 6, 2012, FirstEnergy submitted a more specific request. FirstEnergy requested that the commission take administrative notice of ten exhibits from the ESP 2 case, including the stipulation filed in that case and transcripts of testimony by several witnesses. FirstEnergy also asked the attorney examiner to take administrative notice of seven exhibits and two transcript pages from the MRO case. The examiner granted the requests over objections.

Approval of the ESP 3

{¶ 14} On July 18, 2012, the commission issued an opinion and order approving FirstEnergy’s ESP 3 application. The commission expressly found that the ESP 3 was “more favorable in the aggregate” than an MRO.

{¶ 15} On August 17, 2012, ELPC filed a petition for rehearing. NOPEC filed a separate application for rehearing on the same date. ELPC argued that *225 FirstEnergy’s ESP 3 application was incomplete when submitted and that the commission erred by permitting the examiner to take administrative notice of materials from the MRO and ESP 2 cases. NOPEC’s rehearing application listed 11 alleged errors and included a challenge to the commission’s determination that the ESP 3 was more favorable in the aggregate than an MRO.

{¶ 16} On September 12, 2012, the commission granted the applications “for further consideration of the matters specified.” Ultimately, however, the commission issued a second entry on rehearing in which it denied the rehearing applications and affirmed its approval of FirstEnergy’s ESP 3. The commission found that FirstEnergy’s application met the minimum filing requirements of the Ohio Administrative Code. And with respect to the question of administrative notice, the commission concluded that it had fully addressed this issue in its earlier opinion and order and that the rehearing applications had raised no new issues.

{¶ 17} ELPC and NOPEC filed notices of appeal to this court.

Analysis

Standard of review

{¶ 18} An order of the commission shall be reversed, vacated, or modified only when, upon consideration of the record, this court finds the order to be unlawful or unreasonable. R.C. 4903.13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monongahela Power Co. v. Public Utilities Commission
2004 Ohio 6896 (Ohio Supreme Court, 2004)
In re Application of Columbus S. Power Co.
2012 Ohio 5690 (Ohio Supreme Court, 2012)
In re Application of Columbus S. Power Co.
2011 Ohio 958 (Ohio Supreme Court, 2011)
Allen v. Public Utilities Commission
532 N.E.2d 1307 (Ohio Supreme Court, 1988)
Office of Consumers' Counsel v. Public Utilities Commission
64 Ohio St. 3d 123 (Ohio Supreme Court, 1992)
Canton Storage & Transfer Co. v. Public Utilities Commission
72 Ohio St. 3d 1 (Ohio Supreme Court, 1995)
Time Warner AxS v. Public Utilities Commission
75 Ohio St. 3d 229 (Ohio Supreme Court, 1996)
AK Steel Corp. v. Public Utilities Commission
95 Ohio St. 3d 81 (Ohio Supreme Court, 2002)
Constellation NewEnergy, Inc. v. Public Utilities Commission
104 Ohio St. 3d 530 (Ohio Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
2016 Ohio 3021, 54 N.E.3d 1218, 146 Ohio St. 3d 222, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-ohio-edison-co-slip-opinion-ohio-2016.