In re Application of Duke Energy Ohio, Inc. (Slip Opinion)

2017 Ohio 5536, 150 Ohio St. 3d 437
CourtOhio Supreme Court
DecidedJune 29, 2017
Docket2014-0328
StatusPublished
Cited by13 cases

This text of 2017 Ohio 5536 (In re Application of Duke Energy Ohio, Inc. (Slip Opinion)) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Application of Duke Energy Ohio, Inc. (Slip Opinion), 2017 Ohio 5536, 150 Ohio St. 3d 437 (Ohio 2017).

Opinions

French, J.

{¶ 1} Appellants, the Office of the Ohio Consumers’ Counsel, the Ohio Manufacturers’ Association, Ohio Partners for Affordable Energy, and the Kroger Company, appeal an order of the Public Utilities Commission that authorized intervening appellee Duke Energy Ohio, Inc., to recover costs associated with the environmental remediation of two manufactured-gas-plant (“MGP”) sites near downtown Cincinnati.

{¶ 2} Appellants raise five propositions of law, but we have already resolved proposition Nos. 4 and 5. Of the three that remain, none warrants reversal. Therefore, we affirm the commission’s order.

Facts and procedural background

{¶ 3} MGPs were common in the United States from the middle of the 19th century until the middle of the 20th century. By burning coal, oil, and other fossil fuels, MGPs produced gas that consumers used for lighting, heating, and cooking. The process of manufacturing gas created residual byproducts, including coal tar, sulfur, and ammonia. These residuals often became waste products that were buried at the plant sites, an accepted industry practice at the time. By 1970, nearly all MGPs had become obsolete for various reasons, including the prevalence of natural gas. But the disposal of waste products at the sites of [438]*438former MGPs has caused a number of environmental problems, most notably soil and groundwater contamination.

{¶ 4} Duke’s predecessor companies operated one or both of two MGPs near downtown Cincinnati for over a century. Manufactured-gas operations ceased at these plants in 1928 and 1963. The two sites—now known as the East End and West End sites—contain waste products and contaminants that federal law defines as hazardous substances. As the current owner or operator of facilities from which there is a release or threatened release of hazardous material, Duke is liable for remediation of the MGP sites under the Comprehensive Environmental Response, Compensation, and Liability Act (“CERCLA”), 42 U.S.C. 9601 et seq. Courts have interpreted liability under CERCLA as strict. Westfarm Assocs. Ltd. Partnership v. Washington Suburban Sanitary Comm., 66 F.3d 669, 677 (4th Cir.1995).

{¶ 5} The East End and West End sites have undergone changes in operations and equipment since the two MGPs closed. They currently contain certain infrastructure and facilities that Duke uses to provide utility service to customers. Duke has been aware of its environmental obligations at the MGP sites since 1988, but the sites were considered low priorities because (1) public access to the properties was limited, (2) the groundwater is not used as a source of drinking water, and (3) the hazardous materials were capped with asphalt, concrete, and soil. The risk of exposure changed, however, in 2006 and again in 2009, when two new construction projects were planned on land adjacent to the MGP sites. In 2006, a real-estate developer purchased land adjacent to the East End site and announced plans to construct a residential development on the newly acquired property. And in 2009, Ohio and Kentucky finalized plans for a new bridge spanning the Ohio River that directly crosses the West End site.

{¶ 6} As a result, Duke initiated remediation of both MGP sites. Duke is remediating the sites through the Voluntary Action Program developed by the Ohio Environmental Protection Agency. See generally R.C. Chapter 3746.

{¶ 7} Once the environmental investigation began, Duke applied to the commission for authority to defer its future remediation costs. See R.C. 4905.13 (authorizing the commission to establish a system of accounts to be kept by public utilities and to prescribe the manner in which those accounts shall be kept). The commission granted the application but stated that it would not determine whether Duke could recover its deferred costs until Duke filed an application for cost recovery. In re Application of Duke Energy, Inc., Pub. Util. Comm. No. 09-712-GA-AAM, 2009 WL 4005137 (Nov. 12, 2009); In re Application of Duke Energy, Inc., Pub. Util. Comm. No. 09-712-GA-AAM, 2010 WL 148935 (Jan. 7, 2010).

[439]*439{¶ 8} The case giving rise to this appeal began when Duke filed an application with the commission to increase its natural-gas-distribution rates and to recover its deferred costs. Duke sought to recover environmental-remediation costs incurred through December 31, 2012. The parties entered into a comprehensive stipulation that resolved all issues except whether Duke could recover costs incurred to remediate the MGP sites.

{¶ 9} In November 2013, the commission issued an order adopting the stipulation and authorizing Duke to recover its remediation costs. The commission found that the costs of remediating the MGP sites were recoverable under R.C. 4909.15(A)(4), which allows utilities to recover “[t]he cost to the utility of rendering the public utility service for the test period.”1 According to the commission, Duke has shown on the record that the remediation expenses were a necessary and current cost of doing business as a public utility in response to CERCLA, the federal law that imposes strict liability on Duke for remediating the MGP sites. The commission rejected the argument that Duke could not recover remediation costs because the MGP sites were no longer “used and useful” in rendering utility service, as R.C. 4909.15(A)(1) requires.

{¶ 10} The commission set the amount of Duke’s prudent costs at approximately $55.5 million, which Duke could recover from customers over a five-year period—-approximately $925,000 a month. The parties had stipulated that if the commission allowed MGP costs, recovery would be through a rider and not base rates. The commission therefore ordered Duke to implement “Rider MGP” to recover costs from ratepayers on a per-bill basis. The commission required Duke to file annual updates of Rider MGP to reflect the costs Duke incurred for the preceding year.

{¶ 11} In addition, the commission found that Duke’s shareholders should bear some responsibility for the environmental-remediation costs. To that end, the commission denied the company’s request that ratepayers pay carrying costs on the deferred amounts. The commission also ordered Duke to continue efforts to recover costs from insurers and other third parties that may be liable for remediation costs and ordered that any proceeds recovered be returned to ratepayers, less the company’s costs to achieve the recovery (e.g., litigation costs).

{¶ 12} Appellants filed a joint appeal to this court, challenging the commission’s order. The commission and Duke have filed briefs in defense of the order.

[440]*440 Standard of review

{¶ 13} R.C. 4903.13 provides that this court may reverse, vacate or modify an order of the commission only when, upon considering the record, the court finds that the order is unlawful or unreasonable. Constellation NewEnergy, Inc. v. Pub. Util. Comm., 104 Ohio St.3d 530, 2004-Ohio-6767, 820 N.E.2d 885, ¶ 50. We will not reverse or modify a commission decision as to questions of fact when the record contains sufficient probative evidence to show that the decision is not manifestly against the weight of the evidence and is not so clearly unsupported by the record as to show misapprehension, mistake or willful disregard of duty. Monongahela Power Co. v. Pub. Util. Comm.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gales v. Ohio Lottery Comm.
2025 Ohio 5189 (Ohio Court of Claims, 2025)
In re Application of Dayton Power & Light Co.
2025 Ohio 2953 (Ohio Supreme Court, 2025)
Snodgrass v. Harris
2024 Ohio 3130 (Ohio Supreme Court, 2024)
Madyda v. Ohio Dept. of Pub. Safety
2023 Ohio 4889 (Ohio Court of Claims, 2023)
In re Establishing the Solar Generation Fund Rider
2022 Ohio 4348 (Ohio Supreme Court, 2022)
In re Application of Suburban Natural Gas Co. (Slip Opinion)
2021 Ohio 3224 (Ohio Supreme Court, 2021)
Norman v. Kellie Auto Sales, Inc.
2020 Ohio 4311 (Ohio Court of Appeals, 2020)
State v. Wilson
2020 Ohio 1584 (Ohio Court of Appeals, 2020)
Clark v. State Teachers Retirement Sys.
2018 Ohio 4680 (Ohio Court of Appeals, 2018)
In re Duke Energy Ohio, Inc.
2017 Ohio 7843 (Ohio Supreme Court, 2017)
In re Application of Duke Energy Ohio, Inc. (Slip Opinion)
2017 Ohio 5536 (Ohio Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2017 Ohio 5536, 150 Ohio St. 3d 437, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-duke-energy-ohio-inc-slip-opinion-ohio-2017.