In re Application of Suburban Natural Gas Co. (Slip Opinion)

2021 Ohio 3224, 184 N.E.3d 44, 166 Ohio St. 3d 176
CourtOhio Supreme Court
DecidedSeptember 21, 2021
Docket2020-0781
StatusPublished
Cited by3 cases

This text of 2021 Ohio 3224 (In re Application of Suburban Natural Gas Co. (Slip Opinion)) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Application of Suburban Natural Gas Co. (Slip Opinion), 2021 Ohio 3224, 184 N.E.3d 44, 166 Ohio St. 3d 176 (Ohio 2021).

Opinion

[Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as In re Application of Suburban Natural Gas Co., Slip Opinion No. 2021-Ohio-3224.]

NOTICE This slip opinion is subject to formal revision before it is published in an advance sheet of the Ohio Official Reports. Readers are requested to promptly notify the Reporter of Decisions, Supreme Court of Ohio, 65 South Front Street, Columbus, Ohio 43215, of any typographical or other formal errors in the opinion, in order that corrections may be made before the opinion is published.

SLIP OPINION NO. 2021-OHIO-3224 IN RE APPLICATION OF SUBURBAN NATURAL GAS COMPANY FOR AN INCREASE IN GAS DISTRIBUTION RATES, FOR TARIFF APPROVAL, AND FOR APPROVAL OF

CERTAIN ACCOUNTING AUTHORITY; OFFICE OF OHIO CONSUMERS’ COUNSEL, APPELLANT; PUBLIC UTILITIES COMMISSION, APPELLEE; SUBURBAN NATURAL GAS COMPANY, INTERVENING APPELLEE. [Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as In re Application of Suburban Natural Gas Co., Slip Opinion No. 2021-Ohio-3224.] Public utilities—R.C. 4909.15(A)(1)—Gas pipeline—When fixing rates for service, Public Utilities Commission must determine the valuation of the property of the public utility that is used and useful in rendering the public-utility service as of the date certain—To be useful, the property must be beneficial in rendering service for the convenience of the public as of the date certain—Public Utilities Commission applies an incorrect formula when it considers whether the utility’s investment is prudent. (No. 2020-0781—Submitted March 3, 2021—Decided September 21, 2021.) SUPREME COURT OF OHIO

APPEAL from the Public Utilities Commission of Ohio, Nos. 18-1205-GA-AIR, 18-1206-GA-ATA, and 18-1207-GA-AAM. _______________________ DEWINE, J. {¶ 1} This is an appeal from a decision of the Public Utilities Commission of Ohio (“PUCO”) allowing a gas company to charge its customers higher rates. At issue is whether the gas company’s customers must pay for a 4.9-mile extension of the gas company’s pipeline. To decide this point, the PUCO was required by statute to determine whether the pipeline extension was “used and useful” as of a specified date. R.C. 4909.15(A)(1). The PUCO determined that the extension met this “used-and-useful” test and approved the rate increase. {¶ 2} The Office of the Ohio Consumers’ Counsel opposed the rate increase before the PUCO and maintains its challenge on appeal. In its view, only two miles of the extension were used and useful and thus the PUCO erred by approving a rate increase based upon the entire 4.9-mile extension. We conclude that the PUCO did err: in evaluating the rate increase, the PUCO looked beyond whether the entire extension was used and useful on the applicable date and considered whether it was a prudent investment because it might prove useful in the future. As a consequence, we reverse the PUCO’s decision and remand the case for a proper application of the used-and-useful test. I. Suburban builds a 4.9-mile pipeline extension {¶ 3} The Suburban Natural Gas Company provides natural gas distribution services to residential customers in Delaware and Marion Counties, an area that has been experiencing significant population growth. On one extremely cold day in the winter of 2015, pressure in part of Suburban’s pipeline dropped below 100 pounds per square inch gauge (“psig”). This was concerning—we are told 100 psig is considered the minimum pressure necessary for that part of the pipeline to maintain

2 January Term, 2021

safe, reliable service. At lower pressure levels, there is a risk of the pipeline freezing over, causing an outage that could take weeks to repair. {¶ 4} Suburban hired an engineering firm to look at the problem. The engineers performed modeling work, examining Suburban’s system and taking into account projected growth in Suburban’s customer base. Ultimately, they determined that by 2018 on an extremely cold day (when the demand for gas was at its highest), pressure in the pipeline would dip to 104 psig, just above the 100- psig minimum operating pressure. By the end of 2019, the engineers projected, the pressure could drop below 78 psig. {¶ 5} Based on the results of this modeling, Suburban decided to build a 4.9-mile pipeline extension that would be completed in time for the 2018-2019 winter. Pipeline construction must be approved by the Ohio Power Siting Board. See R.C. 4906.04. But by keeping the extension below five miles, Suburban was able to take advantage of an expedited approval process before the Power Siting Board. See R.C. 4906.03(F)(3); Ohio Adm.Code 4906-6-10. The Power Siting Board approved the extension. The board’s staff report warned, however, that the extension might be longer than needed to serve current and future customers and that Suburban’s cost recovery hinged on being able to demonstrate in a future rate case that the extension was not overbuilt. After receiving the Power Siting Board’s signoff, Suburban built the extension and placed it into service on February 22, 2019. II. Proceedings before the PUCO {¶ 6} While construction was underway, Suburban filed an application with the PUCO for a rate increase to cover the costs of the pipeline extension. Its proposed rate increase was based on a projected value of $8.9 million for the 4.9- mile extension. {¶ 7} In weighing such requests, the PUCO is required to determine “[t]he valuation as of the date certain of the property of the public utility used and useful

3 SUPREME COURT OF OHIO

or * * * projected to be used and useful as of the date certain, in rendering the public utility service.” R.C. 4909.15(A)(1). In this case, the PUCO determined that date certain to be February 28, 2019. {¶ 8} The Consumers’ Counsel is the statewide legal representative for Ohio’s residential ratepayers. R.C. 4911.02(B). It intervened in the proceedings at the PUCO and argued that Suburban had admitted that at most only two miles of the pipeline were used and useful as of February 28, 2019. {¶ 9} After completing an investigation of Suburban’s application, the staff of the PUCO instituted settlement discussions. Ultimately, Suburban and the PUCO staff entered into a settlement agreement that did not include the Consumers’ Counsel. Under the settlement, the staff approved the rate increase based on the entire 4.9-mile extension and Suburban agreed to phase in the increase over a period of three years. {¶ 10} Settlement agreements of this type must be approved by the PUCO. See Ohio Adm.Code 4901-1-30. The Consumers’ Counsel filed objections to the agreement, arguing that the pipeline extension was not used and useful. {¶ 11} The PUCO overruled the objections and approved the settlement. In doing so, the PUCO credited testimony from the engineering firm hired by Suburban. Based on this testimony, the PUCO noted that by the 2018-2019 winter, “assuming a negative five-degree temperature, additional capacity” was required to ensure adequate pressure in the system. Pub. Util. Comm. Nos. 18-1205-GA-AIR, 18-1206-GA-ATA, and 18-1207-GA-AAM, ¶ 121 (Sept. 26, 2019). It further pointed out that according to Suburban, pressure in the system dropped to 105 psig on January 21, 2019—a month before the extension was placed into service. {¶ 12} The Consumers’ Counsel did not offer its own engineering expert. Rather, it sought to use testimony from Suburban’s expert to argue that the 4.9-mile extension was significantly longer than was required to meet Suburban’s needs in February 2019. This engineer said he believed he had done modeling for a two-

4 January Term, 2021

mile extension. He further indicated that a two-mile extension seemed to be enough for the 2018-2019 winter season.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re M.E.B.
2025 Ohio 4326 (Ohio Court of Appeals, 2025)
Steuer Revocable Trust v. Strauss
2022 Ohio 3484 (Ohio Court of Appeals, 2022)
Motorists Mut. Ins. Co. v. Ironics, Inc. (Slip Opinion)
2022 Ohio 841 (Ohio Supreme Court, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2021 Ohio 3224, 184 N.E.3d 44, 166 Ohio St. 3d 176, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-suburban-natural-gas-co-slip-opinion-ohio-2021.