Office of Consumers' Counsel v. Public Utilities Commission

423 N.E.2d 820, 67 Ohio St. 2d 153, 21 Ohio Op. 3d 96, 1981 Ohio LEXIS 563
Ohio Supreme Court·Decided July 15, 1981·No. Nos. 80-1480, 80-1528 & 80-1547·Published·Cited by 58 cases

Opinions

Sweeney, J.

The scope of this court’s review of cornmis[156] sion orders is set forth in R. C. 4903.13, which states in pertinent part:

“A final order made by the public utilities commission shall be reversed, vacated, or modified by the supreme court on appeal, if, upon consideration of the record, such court is of the opinion that such order was unlawful or unreasonable.”

“Under the ‘unlawful or unreasonable’ standard specified in R. C. 4903.13, this court will not reverse or modify an opinion and order of the Public Utilities Commission where the record contains sufficient probative evidence to show that the commission’s determination is not manifestly against the weight of the evidence and is not so clearly unsupported by the record as to show misapprehension, mistake or willful disregard of duty,” Columbus v. Pub. Util. Comm. (1979), 58 Ohio St. 2d 103, 104. See, also, Consumers’ Counsel v. Pub. Util. Comm. (1979), 58 Ohio St. 2d 108, 110; Ohio Utilities Co. v. Pub. Util. Comm. (1979), 58 Ohio St. 2d 153, 164; Duffy. Pub. Util. Comm. (1978), 56 Ohio St. 2d 367, 370; General Motors Corp. v. Pub. Util. Comm. (1976), 47 Ohio St. 2d 58, paragraph two of the syllabus; Cleveland Electric Illuminating Co. v. Pub. Util. Comm. (1975), 42 Ohio St. 2d 403, paragraph eight of the syllabus. We assess the appellants’ objections with this standard of review in mind.

I A.

In its order the commission allowed approximately $91 million to be included in the rate base for construction work in progress (CWIP) pursuant to R. C. 4909.15(A)(1) and 4909.15(E). R. C. 4909.15(A)(1) states in relevant part:

“***The commission may, in its discretion, permit a reasonable allowance for construction work in progress but, in no event, may any allowance for construction work in progress be made by the commission until it has determined, after a physical inspection, that the particular construction project is at least seventy-five per cent complete.”

R. C. 4909.15(E) imposes the following limitation on allowable CWIP:

“In no event shall an allowance for construction work in progress under division (A)(1) of this section exceed twenty per cent of the total valuation as stated in such division, not including such allowance.”

[157] Some $90 million of the CWIP allowance was directly attributable to the Bruce Mansfield coal-fired generating station, which came on line several months after the new rates became effective. It is unquestioned that Bruce Mansfield met the 75 percent completion criterion for rate base eligibility pursuant to R. C. 4909.15(A)(1). Moreover, it is uncontroverted that inclusion of the Bruce Mansfield-related CWIP did not exceed the 20 percent of total valuation limitation imposed by R. C. 4909.15(E).

I A(i).

Appellants Senior Citizens Coalition et al. (hereinafter “SCC”), in case No. 80-1528, challenge the commission’s allowance for CWIP in this case on the basis that the CWIP provisions contained in R. C. 4909.15(A)(1) represent an unconstitutional delegation of legislative power. Specifically, SCC contends that the statute “***establishes no definite policy nor provides any standard for the exercise of PUCO discretion in permitting an allowance for construction work in progress and***therefore the PUCO should be prohibited from granting any such allowance.***”

We find no merit in SCO’s constitutional challenge to the CWIP provisions because the commission’s discretion is sufficiently circumscribed by the specific eligibility criteria enumerated in the statute. As we stated in Consumers’ Counsel v. Pub. Util. Comm., supra (58 Ohio St. 2d 108), at page 113:

“ * * * We believe these limitations adequately confine commission discretion. Further restriction would conceivably hinder the flexibility necessary to enable the commission to carry out legislative will. For these reasons, this court holds that the discretion granted the commission under R. C. 4909.15 to authorize a reasonable allowance for construction work in progress in a utility’s rate base constitutes a lawful delegation of the state’s police power by the General Assembly.”

We expressed the same view of the CWIP provisions of R. C. 4909.15(A)(1) in Cleveland v. Pub. Util. Comm. (1980), 63 Ohio St. 2d 62, 68. In the case at bar we decline to strike down the CWIP statute as an unconstitutional delegation of legislative authority.

[158] I A (ii).

Both SCC and appellant city of Cleveland, in case No. 80-1547, contend that the inclusion of a CWIP allowance in this case constituted an abuse of commission discretion. As previously noted, the Bruce Mansfield generating station, which accounted for virtually all of the CWIP at issue, met the 75 percent completion criterion and came on line several months after the new rates went into effect. Under these circumstances we cannot say that the commission’s decision was either manifestly against the weight of the evidence or unsupported by the record. Columbus v. Pub. Util. Comm., supra. Therefore, we refuse to disturb the commission’s findings on the propriety of including a CWIP allowance in CEI’s rate base. Accordingly, we reject appellants’ assertions that the commission abused its discretion in granting the CWIP allowance.

II.

SCC alleges that the commission did not adequately investigate CEI’s generating capacity to determine whether the utility had excess capacity. The commission staff investigated CEI’s generating capacity and determined that the reserve capacity was adequate but not excessive.4 Staff and CEI witnesses testified to the same effect at the hearings before the commission wherein they explained the methodology by which they reached their conclusions.

We have in a previous case acknowledged the difficulties the commission and utilities face on the excess capacity issue.

“* * * Since utilities must anticipate load growth years in advance to maintain adequate capacity to ensure reliable service, it is unrealistic to expect a utility to have only the precise amount of capacity needed at a given time.” Cleveland v. Pub. Util. Comm., supra, at 65. To paraphrase what we stated in Consumers’ Counsel v. Pub. Util. Comm. (1980), 64 Ohio St. 2d 71, 79: Limited judicial review of an excess capacity determination is sound for the reason that while excess capacity analyses have an aura of precision about them, they are fraught with judgments and assumptions. Given the inherent [159] problems of accurately projecting load growth, we are satisfied that the commission’s excess capacity methodology is reasonable and that the factual findings are supported by the record. SCO’s challenge on the question of excess capacity is, therefore, without merit.

Ill A.

Free access — add to your briefcase to read the full text and ask questions with AI

Office of Consumers' Counsel v. Public Utilities Commission, 423 N.E.2d 820, 67 Ohio St. 2d 153, 21 Ohio Op. 3d 96, 1981 Ohio LEXIS 563 (Ohio 1981).

423 N.E.2d 820 (Office of Consumers' Counsel v. Public Utilities Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In re Application of Suburban Natural Gas Co. (Slip Opinion)
2021 Ohio 3224 (Ohio Supreme Court, 2021)
Biglin v. S (In re Black Fork Wind Energy, L. L.C.)
124 N.E.3d 787 (Ohio Supreme Court, 2018)
In re Application of Duke Energy Ohio, Inc. (Slip Opinion)
2017 Ohio 5536 (Ohio Supreme Court, 2017)
Vah v. Mahan, Unpublished Decision (6-30-2006)
2006 Ohio 3476 (Ohio Court of Appeals, 2006)
Cincinnati Gas & Elec. Co. v. Pub. Util. Comm.
1999 Ohio 81 (Ohio Supreme Court, 1999)
Cincinnati Gas & Electric Co. v. Public Utilities Commission
86 Ohio St. 3d 53 (Ohio Supreme Court, 1999)
Tongren v. Public Utilities Commission
706 N.E.2d 1255 (Ohio Supreme Court, 1999)
Columbus Southern Power Co. v. Pub. Util. Comm.
1993 Ohio 67 (Ohio Supreme Court, 1993)
Columbus Southern Power Co. v. Public Utilities Commission
620 N.E.2d 835 (Ohio Supreme Court, 1993)
Consolidated Rail Corp. v. Public Utilities Commission
547 N.E.2d 1176 (Ohio Supreme Court, 1989)
State ex rel. Utilities Commission v. Thornburg
385 S.E.2d 451 (Supreme Court of North Carolina, 1989)
STATE EX REL. UTIL. COM'N v. Thornburg
385 S.E.2d 451 (Supreme Court of North Carolina, 1989)
State ex rel. Union Electric Co. v. Public Service Commission
765 S.W.2d 618 (Missouri Court of Appeals, 1988)
In re G & B Anderson, Inc.
526 N.E.2d 792 (Ohio Supreme Court, 1988)
Barasch v. Pennsylvania Public Utility Commission
532 A.2d 325 (Supreme Court of Pennsylvania, 1987)
Power v. Utilities & Transp. Comm'n
711 P.2d 319 (Washington Supreme Court, 1985)