Cincinnati Gas & Elec. Co. v. Pub. Util. Comm.

1999 Ohio 81, 86 Ohio St. 3d 53
CourtOhio Supreme Court
DecidedJuly 7, 1999
Docket1997-0738
StatusPublished
Cited by2 cases

This text of 1999 Ohio 81 (Cincinnati Gas & Elec. Co. v. Pub. Util. Comm.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cincinnati Gas & Elec. Co. v. Pub. Util. Comm., 1999 Ohio 81, 86 Ohio St. 3d 53 (Ohio 1999).

Opinion

[This opinion has been published in Ohio Official Reports at 86 Ohio St.3d 53.]

THE CINCINNATI GAS AND ELECTRIC COMPANY, APPELLANT, v. PUBLIC UTILITIES COMMISSION OF OHIO, APPELLEE. [Cite as Cincinnati Gas & Elec. Co. v. Pub. Util. Comm., 1999-Ohio-81.] Public Utilities Commission—Application to increase rates for natural gas service—Commission did not abuse its discretion in excluding a portion of the development costs of natural gas company’s customer service system from its rate base—Commission acted unlawfully in imputing revenue levels for ratemaking purposes that differ significantly from the actual revenue collected from customers during the test period pursuant to contracts previously approved by the commission. (Nos. 97-738 and 97-2199—Submitted September 29, 1998—Decided July 7, 1999.) APPEALS from the Public Utilties Commission of Ohio, No. 95-656-GA-AIR. __________________ {¶ 1} The Cincinnati Gas and Electric Company (“CG&E”) is a public utility and a natural gas company as defined in R.C. 4905.02 and 4905.03(A)(6). As such, it is subject to the jurisdiction of the Public Utilities Commission of Ohio. On January 8, 1996, pursuant to R.C. 4909.18, CG&E filed with the commission an application to increase its rates for gas service. The commission’s staff investigated the application and filed its report on July 12, 1996. CG&E and a number of intervenors, including the Office of Consumers’ Counsel (“OCC”), filed objections to the staff report. {¶ 2} In summer 1996, the commission conducted hearings, and on December 12, 1996, it issued its opinion and order in the rate case. The commission allowed an increase in gas rates, but not to the level CG&E had sought. CG&E filed an application for rehearing, which the commission denied on February 12, SUPREME COURT OF OHIO

1997. On April 14, 1997, CG&E filed its notice of appeal in this court in case No. 97-738. {¶ 3} On July 2, 1997, the commission issued a supplemental opinion and order in the rate case. CG&E also appealed after that order, initiating case No. 97- 2199 in this court. Since the appeals in case Nos. 97-738 and 97-2199 are substantially identical, this court consolidated the two appeals. {¶ 4} CG&E’s appeal focuses on two issues, each affecting a different element in the ratemaking formula set forth in R.C. 4909.15. Briefly, a rate increase is determined as follows: {¶ 5} R.C. 4909.15(A) requires the commission to determine the following: the valuation of the utility’s property in service as of a date certain, i.e. its rate base; a fair and reasonable return on that investment; and the expenses incurred in providing service during the test year. Once these determinations are made, the commission, pursuant to R.C. 4909.15(B), computes the gross annual revenues to which the utility is entitled by adding the dollar return on the utility’s investment to the utility’s test-year expenses. Pursuant to R.C. 4909.15(C), the commission then determines the utility’s revenues during the test period. If the revenues received by the utility during the test year are less than the gross annual revenues to which the utility is entitled, the commission must set new rates that will raise the necessary revenue. R.C. 4909.15(D); Columbus S. Power Co. v. Pub. Util. Comm. (1993), 67 Ohio St.3d 535, 537-538, 620 N.E.2d 835, 838-839. To simplify: The value of used and useful property (rate base) (1) is multiplied by rate of return (2), yielding the dollar annual return to which the utility is entitled (3). That amount (3) is added to test-period expenses (4), yielding gross annual revenues to which utility is entitled (5). Subtracted from amount (5) is test period revenues (6), yielding the rate increase (7). {¶ 6} The two issues in CG&E’s appeal deal with the rate base, which CG&E argues was set too low, and test-period revenues, which the company argues

2 January Term, 1999

were set too high. We will set forth the facts relevant to each issue separately, below. Rate Base {¶ 7} The rate-base issue centers around the cost associated with CG&E’s development of a new customer service system (“CSS”). CG&E sought to have the bulk of the development costs of the CSS included in its rate base. The commission allowed substantially less than CG&E sought. {¶ 8} In June 1987, CG&E commenced development of a CSS to replace its existing customer billing and customer service order systems, which had been in use for approximately twenty years. CG&E targeted July 1990 as the implementation date, with the new CSS to handle customer service operations well into the future. {¶ 9} Because of the extraordinary development costs and expected long- term usefulness of the new CSS, CG&E chose to capitalize the bulk of development costs rather than treat them as ordinary operating expenses. To that end, CG&E in 1990 requested and received approval from the commission to capitalize CSS development expenses in commission case No. 90-277-GE-AAM. At that time, CG&E’s estimate of the cost of development of CSS was $24 million. {¶ 10} The CSS development efforts met trouble from the start. In late 1989, the proposed implementation date was revised from July 1990 to July 1991. The project experienced further delays, and by July 1991, the CSS was far from completion and the costs had far exceeded the $24 million estimate; by November 1991, the capitalized expenditures totaled $47.43 million. {¶ 11} In mid-1991, CG&E commissioned two outside consultants to evaluate the viability of completing the project and to provide advice as to completion procedures. Both Andersen Consulting and Computer Science Corporation (“CSC”) concluded that the CSS project was viable. In the fall of 1991, CG&E contracted with CSC to complete the project by July 1993 for a flat

3 SUPREME COURT OF OHIO

fee of $14.875 million. In its role of managing the project, CSC was given full authority with respect to staffing, cost, technical decisions, and schedules. CSC successfully completed and implemented the CSS by July 1993. At the project’s completion, the entire capitalized cost was $62.3 million, one hundred sixty percent above CG&E’s 1990 projection. {¶ 12} In the rate case, CG&E sought to recover the portion of CSS costs allocable to its Ohio gas operations by including such costs, capitalized and amortized, as an asset in its rate base. The commission’s staff investigated pursuant to R.C. 4909.19 and recommended a substantial disallowance of capitalized CSS development costs from the rate base proposed by CG&E. The staff’s recommendation was premised on its conclusion that CG&E had mismanaged the CSS development project in various respects, thereby causing its costs to be excessive. {¶ 13} The commission staff concluded that CG&E had mismanaged the CSS project by “unreasonably missing project deadlines and exceeding project costs, by failing to sign CSS contractors to contracts with identified deliverables with certain deadlines, by choosing to develop a customized DB2-based CSS system without adequate identification of software capabilities and resource availability, by investing in a system where the costs greatly exceeded benefits, and by failing to maintain an adequate audit trail of CSS system development and managerial decision-making with regard to costs and deadlines.” {¶ 14} Based on those conclusions, the staff recommended that the commission allow recovery based on the staff’s “best estimate of system costs had the project been expertly developed and managed.” The staff believed that “the CSS project was expertly managed from the point where CSC took over project responsibility” from CG&E, and found that the system was fifty percent complete at that point. Doubling CSC’s contract fee would yield a figure representing the total cost had the project been expertly managed from the get-go.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AK Steel Corp. v. Pub. Util. Comm.
2002 Ohio 1735 (Ohio Supreme Court, 2002)
Cincinnati Bell Tel. Co. v. Pub. Util. Comm.
2001 Ohio 134 (Ohio Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
1999 Ohio 81, 86 Ohio St. 3d 53, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cincinnati-gas-elec-co-v-pub-util-comm-ohio-1999.