City of Cincinnati v. Public Utilities Commission

67 Ohio St. 3d 523
CourtOhio Supreme Court
DecidedNovember 3, 1993
DocketNo. 92-2101
StatusPublished
Cited by7 cases

This text of 67 Ohio St. 3d 523 (City of Cincinnati v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Cincinnati v. Public Utilities Commission, 67 Ohio St. 3d 523 (Ohio 1993).

Opinion

Per Curiam.

The city argues that the commission erred: (1) in determining Zimmer’s reasonable original cost, including failing to make a prudence adjustment to CG&E’s Zimmer rate base; and (2) in using a twelve-month average stock price to estimate CG&E’s cost of common equity. For the reasons which follow, we reject these arguments and affirm the commission’s order.

I. REASONABLE ORIGINAL COST

A. Equivalent Plant Standard

R.C. 4909.15 and 4909.051 require the commission to ascertain the reasonable original cost of a utility’s used and useful property for ratemaking purposes. In [526]*526doing so in this case for the converted Zimmer facility, the commission separated the cost of the plant, in accordance with the 1985 stipulation, into four distinct parts and included in rate base: (1) the sunk costs remaining as of January 31, 1984, which were stipulated to be used and useful in the converted coal-fired plant; (2) the AFUDC properly accrued on the sunk costs; (3) the portion of the post-cancellation conversion costs (ie., the “going forward costs”) determined to be used and useful in this proceeding; and (4) the AFUDC on those costs. While the city concedes that the commission properly determined the reasonableness of the used and useful conversion costs and associated AFUDC in this proceeding, it contends that the commission erred by not considering the reasonableness of the otherwise allowable sunk costs. The commission and CG&E generally contend that such a reasonableness analysis of the remaining sunk costs is prohibited by the 1985 stipulation. We agree.

The stipulation was crafted to provide for a dollar disallowance for “nuclear” Zimmer, rather than a consideration of specific plant items, in order to accommodate settlement and to avoid the need for an arduous “brick by brick” audit of specific plant items. Accordingly, the stipulation does not distinguish between the specific plant items deemed used and useful in a converted Zimmer facility, and those which were included in the $861 million disallowance. There being no means to identify or challenge the pre-January 31, 1984 plant stipulated to be used and useful in a converted Zimmer, it necessarily follows that the stipulation prohibits inquiry into the “reasonableness” of these otherwise allowable sunk costs. Indeed, in its 1985 order approving the stipulation, the commission recognized that only the reasonableness of the “going forward costs to complete the converted [Zimmer] facility” were left open to challenge in the instant proceeding. The city did not appeal that order and is now bound by it.

Recognizing that the specific plant items represented by the sunk costs are beyond review in this proceeding, the city based its alternative Zimmer valuation (including the remaining sunk costs and the conversion costs) upon the present value of the allegedly comparable Rockport Power Plant in Indiana.2 The [527]*527commission rejected the city’s proposal as being contrary to the original cost rate-base valuation required by R.C. 4909.05.

We have recognized that a utility’s rate base under the original-cost standard is based upon the actual investment in the assets of the utility. Babbit v. Pub. Util. Comm. (1979), 59 Ohio St.2d 81, 89-90, 13 O.O.3d 67, 72, 391 N.E.2d 1376, 1381; Franklin Cty. Welfare Rights Org. v. Pub. Util. Comm. (1978), 55 Ohio St.2d 1, 11, 9 O.O.3d 1, 6, 377 N.E.2d 990, 997. Clearly, the city’s proposed Zimmer rate-base valuation, based upon the cost of an allegedly comparable plant adjusted to price levels at the time of valuation, violates the statutory original cost standard and is unlawful under R.C. 4909.05(E).3

• The city also argues that the AFUDC accrued on the remaining sunk costs is not a “reasonable” cost of Zimmer and should be excluded in its entirety from rate base. As set forth more fully in the companion cases of Columbus S. Power, supra, and Cincinnati Gas & Elec. Co., supra, the 1985 stipulation explicitly provided for the allowance of such AFUDC in this proceeding, subject only to its “proper accrual” under established accounting conventions. Having determined in those cases that the commission’s allowance of AFUDC on these sunk costs from March 1986 until completion of the Zimmer facility was neither unreasonable nor unlawful, we reject this argument.

Accordingly, we conclude that the commission properly rejected the city’s equivalent-plant standard for valuing rate base and that it properly determined Zimmer’s valuation within the constraints imposed by the 1985 stipulation.

B. Prudence

While the 1985 stipulation prevented inquiry into the reasonableness of the remaining sunk costs, it expressly left open to challenge in this proceeding whether the owner-utilities’ decision to convert Zimmer to a coal-fired facility was prudent. We adopt the commission’s definition of a prudent decision, which [528]*528is in accord with that used in other jurisdictions,4 as “one which reflects what a reasonable person would have done in light of conditions and circumstances which were known or reasonably should have been known at the time the decision was made.” In the Matter of the Investigation into the Perry Nuclear Power Station (Jan. 12, 1988), PUCO No. 85-521-EL-COI, at 10-11. The standard contemplates a retrospective, factual inquiry, without the use of hindsight judgment, into the decisionmaking process of the utility’s management. See Re Syracuse Home Util. Co. (Dec. 30, 1986), PUCO No. 86-12-GA-GCR; Re Toledo Edison Co. (July 16, 1987), PUCO No. 86-05-EL-EFC.

The issue central to the prudence inquiry below was whether CG&E, in 1984, could have written off its entire Zimmer investment and still have had sufficient access to the capital markets to enable it to construct an arguably less costly generating facility in time to meet its customers’ forecasted energy needs in 1991. The construction options under consideration included, inter alia, building a coal-fired plant at a new (“greenfield”) site or adding an additional coal-fired generating unit at an existing facility, owned by CG&E and DP&L, at East Bend, Kentucky.

Although the commission found that CG&E’s decisionmaking process was “less than adequate,” and made a corresponding downward adjustment to the company’s rate of return, it refused to make a prudence adjustment to CG&E’s Zimmer rate base. Specifically, the commission found that an adjustment was not warranted because the rate-base exclusions related to AFUDC, nuclear fuel, and nuclear wind-down costs (nearly $230 million in this case), as well as the $861 million disallowance required by the 1985 stipulation (approximately $400 million in this case), reduced Zimmer’s valuation to the range of costs to construct an alternative plant at a greenfield site.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
67 Ohio St. 3d 523, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-cincinnati-v-public-utilities-commission-ohio-1993.