In re Application of Oak Run Solar Project, L.L.C.

CourtOhio Supreme Court
DecidedMay 26, 2026
Docket2024-1477
StatusPublished

This text of In re Application of Oak Run Solar Project, L.L.C. (In re Application of Oak Run Solar Project, L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Application of Oak Run Solar Project, L.L.C., (Ohio 2026).

Opinion

[Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as In re Application of Oak Run Solar Project, L.L.C., Slip Opinion No. 2026-Ohio-1849.]

NOTICE This slip opinion is subject to formal revision before it is published in an advance sheet of the Ohio Official Reports. Readers are requested to promptly notify the Reporter of Decisions, Supreme Court of Ohio, 65 South Front Street, Columbus, Ohio 43215, of any typographical or other formal errors in the opinion, in order that corrections may be made before the opinion is published.

SLIP OPINION NO. 2026-OHIO-1849 IN RE APPLICATION OF OAK RUN SOLAR PROJECT, L.L.C., FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED TO CONSTRUCT A

SOLAR-POWERED ELECTRIC-GENERATION FACILITY IN MADISON COUNTY, OHIO; MADISON COUNTY BOARD OF COMMISSIONERS ET AL., APPELLANTS; POWER SITING BOARD, APPELLEE; OAK RUN SOLAR PROJECT, L.L.C., INTERVENING APPELLEE. [Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as In re Application of Oak Run Solar Project, L.L.C., Slip Opinion No. 2026-Ohio-1849.] Public utilities—Certificate of construction for solar farm—R.C. 4906.10(A)— Adm.Code 4906-4-08(D)(4)(e)—Ohio Power Siting Board did not obtain from applicant seeking certificate to construct solar farm photographic simulations or artist’s pictorial sketches of substations for the proposed project, which the board needed to adequately assess the proposed project from public vantage points under Adm.Code 4906-4-08(D)(4)(e) and to make the substantive statutory determinations regarding the visual impacts SUPREME COURT OF OHIO

of the proposed project under R.C. 4906.10(A)—Orders affirmed in part and reversed in part and matter remanded. (No. 2024-1477—Submitted October 28, 2025—Decided May 26, 2026.) APPEAL from the Power Siting Board, Nos. 22-549-EL-BGN and 22-550-EL-BTX. __________________ FISCHER, J., authored the opinion announcing the judgment of the court, which DEWINE and DETERS, JJ., joined. KENNEDY, C.J., concurred in part and dissented in part, with an opinion. BRUNNER, J., concurred in part and dissented in part, with an opinion. HAWKINS, J., concurred in part and dissented in part, with an opinion joined by KENNEDY, C.J., and SHANAHAN, J.

FISCHER, J. {¶ 1} Appellee, the Ohio Power Siting Board, authorized intervening appellee, Oak Run Solar Project, L.L.C., to construct a solar farm in Madison County. The project’s opponents and appellants here, the Board of Trustees for Somerford Township, the Board of Trustees for Deercreek Township, the Board for Trustees for Monroe Township, and the Madison County Board of Commissioners (collectively, “the local governments”)—have appealed the board’s opinion and order granting that authorization, as well as the board’s order denying their application for rehearing. {¶ 2} The crux of their argument is that the board failed to obtain the information necessary to engage in reasoned decision-making about whether to approve various aspects of the project. The local governments are right in one respect: the board did not obtain adequate visual simulations or sketches of the proposed facility. The local governments’ remaining arguments fail either on the merits or because they do not show prejudice from the board’s orders.

2 January Term, 2026

{¶ 3} We accordingly affirm in part and reverse in part the board’s orders, and we remand this matter to the board with instructions to more thoroughly address the project’s visual impacts. I. BACKGROUND A. Legal background {¶ 4} The General Assembly has vested the board with the authority to approve the construction of a “major utility facility.” R.C. 4906.10(A); see also R.C. 4906.01(B)(1) (defining “major utility facility”); R.C. 4906.04 (“No person shall commence to construct a major utility facility in this state without first having obtained a certificate for the facility.”). There is no dispute that, as the board found, Oak Run’s proposed solar farm in Madison County qualifies as a major utility facility. {¶ 5} Before the board can approve the construction of a major utility facility, however, “it must make eight substantive determinations,” In re Application of Harvey Solar I, L.L.C., 2025-Ohio-1503, ¶ 10, as set forth in R.C. 4906.10(A). At issue here is whether the board’s findings support its order with regard to the following four substantive determinations under R.C. 4906.10(A):

(2) The nature of the probable environmental impact; (3) That the facility represents the minimum adverse environmental impact, considering the state of available technology and the nature and economics of the various alternatives, and other pertinent considerations; ... (5) That the facility will comply with [R.C. Ch. 3704, 3734, and 6111] and all rules and standards adopted under those chapters . . . ; [and]

3 SUPREME COURT OF OHIO

(6) That the facility will serve the public interest, convenience, and necessity; . . . .

{¶ 6} The board has adopted “rules as are necessary and convenient to implement” R.C. Ch. 4906. R.C. 4906.03(C). The board’s rules that are at issue in this case are discussed below.1 B. Factual background {¶ 7} In September 2022, Oak Run applied to the board for approval to develop, construct, and operate a solar farm in Madison County. The board granted the local governments’ motions to intervene in the case, as well as the motions to intervene of several other parties, including Dr. John Boeckl and the Ohio Environmental Council (“OEC”), both of whom filed amicus briefs in this appeal. {¶ 8} The board’s staff submitted a report summarizing its investigation of the project, with findings and recommendations for the board’s consideration. Oak Run and some of the intervenors (including Dr. Boeckl and OEC) then filed a joint stipulation, recommending that the board approve the project, subject to 46 conditions. {¶ 9} The board held a hearing on the stipulation; it heard evidence supporting and opposing the project, after which it issued a decision amending the stipulation and approving the project, subject to the conditions in the amended stipulation. 2024 WL 1465954, *82 (Mar. 21, 2024). It determined that the project, as approved, satisfied the eight requirements of R.C. 4906.10(A). Id. at *81. {¶ 10} The facility will sit on about 4,400 acres of privately owned land within an approximate 6,050-acre project area. Oak Run procured the land by

1. Effective May 30, 2024, after it issued its opinion and order in this case, the board amended and renumbered some of its rules. There is no dispute that the pre-amendment versions of the rules govern here, and each rule citation in this opinion is to the pre-amendment version. The first citation to each rule identifies the effective date of the applied version. And each subsequent citation to the same rule is to that prior version.

4 January Term, 2026

executing agreements with the landowners. The facility will include an 800 megawatt (“MW”) solar-powered electric-generating facility, a 300 MW alternating-current battery-energy storage system (“BESS”) comprised of two 150 MW facilities, and two 3.45-mile-long transmission lines. {¶ 11} Rows of solar panels will be secured to the ground and “grouped in large clusters that will be fenced with gated entrances.” Oak Run will site the panels as part of an “agrivoltaics program,” whereby agricultural products will grow and livestock will graze between the rows of panels. The purpose of an agrivoltaics program is to harness the dual-use capabilities of land—that is, to preserve the agricultural productivity of the land while simultaneously using the land as a solar farm to generate renewable energy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Application of Buckeye Wind, L.L.C.
2012 Ohio 878 (Ohio Supreme Court, 2012)
In re Application of Ohio Power Co. (Slip Opinion)
2014 Ohio 4271 (Ohio Supreme Court, 2014)
In re Application of Champaign Wind, L.L.C. (Slip Opinion)
2016 Ohio 1513 (Ohio Supreme Court, 2016)
Stanton v. State Tax Commission
151 N.E. 760 (Ohio Supreme Court, 1926)
In re Application of Duke Energy Ohio, Inc. (Slip Opinion)
2021 Ohio 3301 (Ohio Supreme Court, 2021)
In re Application of Alamo Solar I, L.L.C.
2023 Ohio 3778 (Ohio Supreme Court, 2023)
State v. Beatty
2024 Ohio 5684 (Ohio Supreme Court, 2024)
In re Application of Harvey Solar I, L.L.C.
2025 Ohio 1503 (Ohio Supreme Court, 2025)
State ex rel. Martens v. Findlay Mun. Court
2024 Ohio 5667 (Ohio Supreme Court, 2024)
In re Application of Dayton Power & Light Co.
2025 Ohio 2953 (Ohio Supreme Court, 2025)
In re Application of S. Branch Solar, L.L.C.
2025 Ohio 5679 (Ohio Supreme Court, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
In re Application of Oak Run Solar Project, L.L.C., Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-oak-run-solar-project-llc-ohio-2026.