Ohio Edison Co. v. Pub. Util. Comm.

1997 Ohio 196, 78 Ohio St. 3d 466
Ohio Supreme Court·Decided May 21, 1997·No. 1995-2575·Published·Cited by 8 cases

Opinion

[This opinion has been published in Ohio Official Reports at 78 Ohio St.3d 466.]

OHIO EDISON COMPANY, APPELLANT, v. PUBLIC UTILITIES COMMISSION OF OHIO ET AL., APPELLEES.

[Cite as Ohio Edison Co. v. Pub. Util. Comm., 1997-Ohio-196.]

Public utilities—Public utility’s authority to grant reduced-rate service to a political subdivision not subject to R.C. 4905.33 prohibition against furnishing below-cost service for the purpose of detroying competition.

Pursuant to R.C. 4905.34, a public utility’s authority to grant reduced-rate utility service to a political subdivision is not subject to the R.C. 4905.33 prohibition against furnishing below-cost utility service for the purpose of destroying competition. (No. 95-2575—Submitted January 7, 1997—Decided May 21, 1997.)

APPEAL from the Public Utilities Commission of Ohio, No. 93-1408-EL-CSS.

{¶ 1} This appeal involves an order by the Public Utilities Commission of Ohio (“commission”) resolving a complaint brought by Youngstown Thermal, Limited Partnership (“Thermal”) against Ohio Edison Company (“Ohio Edison”) for selling electricity below cost in violation of R.C. 4905.33.

{¶ 2} Thermal is a limited partnership that owns and operates a district heating system that provides steam-heating service to approximately fifty buildings in downtown Youngstown, Ohio. Thermal’s general partner is primarily engaged in acquiring, expanding, and operating district heating and cooling systems in several cities, including Pittsburgh. Pursuant to the Certified Territory Act, Ohio Edison is the monopoly electric provider for the city of Youngstown and vicinity. Thermal and Ohio Edison presently compete for the heating load in Youngstown.

{¶ 3} In the 1980s, Mahoning County proposed construction of a 198,000 square foot jail facility in downtown Youngstown. The jail was to be built across

SUPREME COURT OF OHIO

the street from Thermal’s existing steam plant. A county building commission was created to determine various aspects of the construction and equipment to be used in the jail facility. Architectural and engineering firms were hired to prepare plans and specifications for the facility.

{¶ 4} Ohio Edison, being the monopoly electric provider for the Youngstown area, had no competitors for the general electric load at the jail and agreed to provide the general electric load service to the jail at Ohio Edison’s standard commercial rate. Ohio Edison also sought to provide the cooling load at that same commercial rate. However, Thermal wanted to use the jail as the anchor for a district cooling system in Youngstown. Ohio Edison viewed the jail project as critical to protecting its existing downtown cooling-load customer base. Thus, Thermal and Ohio Edison began competing for the jail’s cooling load.

{¶ 5} Thermal submitted a bid for the cooling-load to the building commission. Ohio Edison responded by offering cooling-load service at a reduced rate, a cash incentive to purchase the chillers, and a high efficiency lighting allowance of $30,000-$50,000. Each party then offered several progressively lower bids, including multiple-tiered, usage-based, fixed or capped rates and sizable cash incentives, in an effort to obtain the cooling-load bid at the jail facility.

{¶ 6} On September 22, 1993, the building commission met and publicly voted five to two to negotiate exclusively with Thermal for thirty days to finalize a contract. Ohio Edison continued to contact and discuss the project with the building commission members. Ohio Edison also sent a letter to the chairman of the building commission reaffirming that its offer remained on the table.

{¶ 7} On October 22, 1993, the building commission members learned that Thermal had negotiated a contract with the county representatives. Apparently, the building commission then deferred a vote on the Thermal contract until later in October, citing a need to review the contract terms. The commission disapproved the contract by a vote of four to three at its October 26 meeting. Ohio Edison next

January Term, 1997

offered to include an interest-free loan with its bid. On December 22, 1993, the Mahoning County Commissioners awarded the final contract (“service agreement”), including the cooling load, to Ohio Edison.

{¶ 8} On August 23, 1993, Thermal brought an R.C. 4905.26 complaint before the commission against Ohio Edison alleging that Ohio Edison was proposing to provide a cooling service without authority and that Ohio Edison had priced the cooling service below Ohio Edison’s actual cost for the purpose of destroying competition in violation of R.C. 4905.33. Ohio Edison sought to dismiss the complaint because the proposed service agreement did not provide cooling services and was not subject to commission review under R.C. 4905.34. Ohio Edison’s motion to dismiss was denied.

{¶ 9} At a prehearing conference, the parties agreed to narrow the issues for hearing and to submit briefs on one legal issue:

“[I]s the authority granted a utility by [R.C.] Section 4905.34, * * * to offer free or reduced rate service limited by [R.C.] Section 4905.33, * * * which prohibits a utility from furnishing free service or service for less than actual cost for the purpose of destroying competition[?]”

{¶ 10} The commission issued an entry finding that although these sections were not in conflict, the grant of authority in R.C. 4905.34 was limited by the statement in R.C. 4905.33 that a utility cannot provide reduced-rate service for the purpose of destroying competition. The commission stated that this entry was not final or appealable. Ohio Edison sought but was denied rehearing.

{¶ 11} The commission then conducted an evidentiary hearing on the issue of Ohio Edison’s actual cost to provide the power for the cooling load at the jail project. Thermal presented two witnesses who testified that Ohio Edison was providing electrical energy below its actual cost for the cooling load to the jail project. Ohio Edison presented four witnesses who testified that the estimated total jail revenues would exceed the cost to serve the facility.

SUPREME COURT OF OHIO

{¶ 12} The commission reviewed the conflicting evidence and held that Ohio Edison had violated R.C. 4905.33 by agreeing to provide the cooling-load power to the jail at a rate below Ohio Edison’s actual cost for the purpose of destroying competition by Thermal. However, the commission assessed no civil forfeiture against Ohio Edison on the basis that this was the first time that the commission had been presented with the question at hand.

{¶ 13} Ohio Edison sought rehearing. Thermal did not seek rehearing, but it opposed Ohio Edison’s application for rehearing. The commission denied Ohio Edison’s application for rehearing.

{¶ 14} The cause is now before this court upon an appeal as of right.

James W. Burk, Michael R. Beiting and Anthony J. Alexander; Roetzel & Andress Co., L.P.A., and George W. Rooney, Jr., for appellant.

Betty D. Montgomery, Attorney General, Duane W. Luckey, William L.

Wright, Thomas W. McNamee and Paul A. Colbert, Assistant Attorneys General, for appellee, Public Utilities Commission of Ohio.

Vorys, Sater, Seymour & Pease and John Winship Read, for intervening appellee, Youngstown Thermal, Limited Partnership.

Kaufman & Cumberland and Frank J. Cumberland, urging affirmance for amicus curiae, AT&T Communications of Ohio, Inc.

Chester, Willcox & Saxbe, John W. Bentine and Jeffrey L. Small, urging affirmance for amicus curiae, American Municipal Power-Ohio, Inc.

January Term, 1997

LUNDBERG STRATTON, J.

Free access — add to your briefcase to read the full text and ask questions with AI

Ohio Edison Co. v. Pub. Util. Comm., 1997 Ohio 196, 78 Ohio St. 3d 466 (Ohio 1997).

1997 Ohio 196 (Ohio Edison Co. v. Pub. Util. Comm.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related