Hand v. RORICK CONSTRUCTION COMPANY

206 N.W.2d 835, 190 Neb. 191, 1973 Neb. LEXIS 661
CourtNebraska Supreme Court
DecidedMay 4, 1973
Docket38701
StatusPublished
Cited by8 cases

This text of 206 N.W.2d 835 (Hand v. RORICK CONSTRUCTION COMPANY) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hand v. RORICK CONSTRUCTION COMPANY, 206 N.W.2d 835, 190 Neb. 191, 1973 Neb. LEXIS 661 (Neb. 1973).

Opinion

Clinton, J.

This is an action in negligence against a general contractor by an employee of a masonry subcontractor for injuries sustained in a fall from a scaffold at the site of remodeling and construction of a school in Omaha, Nebraska. At the close of plaintiff’s case-in-chief before a jury, the amended petition of plaintiff was dismissed and this appeal was taken.

On October 25, 1965, plaintiff was on a scaffold 20 feet above the ground, laying block and brick. The scaffold planking gave way and plaintiff fell, receiving *193 bodily injuries. The scaffold platform had been constructed by resting two 2 x 10 planks side by side and placing them across arm brackets, part of the metal scaffold which supported both the brackets and the materials platform. The evidence showed that safe construction practice as well as safety codes adopted by the Department of Labor of the State of Nebraska pursuant to statutory authority required that the planks be kept in place by cleats and bars which are braces nailed or fastened across the planks on the underside at each end to prevent the planks from slipping off the arm brackets or separating. There were no cleats, or bars on the planks that fell.

The scaffold had been erected by employees of plaintiff’s employer which owned the scaffold, but plaintiff had not been one of those employees.

The contract between the owner and the general contractor provided: “The Contractor shall take all necessary precautions for the safety of employees on the work, and shall comply with all applicable provisions of Federal, State, and Municipal safety laws and building codes to prevent accidents or injury to persons on, about or adjacent to the premises where the work is being performed.”

Although its superintendent was at the site, the general contractor had never inspected the scaffolding.

Plaintiff, a bricklayer for 17 years, was. thoroughly familiar with scaffolds. He had experienced difficulty with scaffolding earlier at the same site, and someone had corrected the condition without anyone notifying the general contractor.

The plaintiff appears to recognize the rule that a general contractor is' not liable to an employee of a subcontractor for the acts and omissions of the employer-subcontractor. Munson v. Vane-Stecker Co., 347 Mich. 377, 79 N. W. 2d 855; Miller v. Weinberg, 56 Del. 87, 190 A. 2d 27; Johnson v. Cal-West Constr. Co., 204 Cal. App. 2d 610, 22 Cal. Rptr. 492; Davis v. Caristo Constr. *194 Corp., 13 App. Div. 2d 382, 216 N. Y. S. 2d 765; Gambella v. John A. Johnson & Sons, Inc., 285 App. Div. 580, 140 N. Y. S. 2d 208; Chesin Constr. Co., Inc. v. Epstein, 8 Ariz. App. 312, 446 P. 2d 11. However, he takes the position the contractual provision we have earlier quoted enlarges both the common law duty of the contractor and its obligation under pertinent statutes pertaining to scaffolding and gives rise to' a cause ■of action on the theory of a third party beneficiary. This position clearly appears to be the import of the amended petition on which the case was tried.

It appears to be conceded that the plaintiff’s employer was, under the terms of the contract with the defendant, required to furnish all the material, tools, and equipment required for performance of the subcontract, but it is the plaintiff’s theory that the contractual provision in this case imposed on the defendant the duty to furnish safe scaffolds, nonetheless. We do not agree.

Such contractual provisions are frequently held not to create a third party beneficiary relationship unless it clearly appears it was so intended. Rausch v. Julius B. Nelson & Sons, Inc., 276 Minn. 12, 149 N. W. 2d 1; Davis v. Nelson-Deppe, Inc., 91 Idaho 463, 424 P. 2d 733; Walker v. Wittenberg, Delony & Davidson, Inc., 242 Ark. 97, 412 S. W. 2d 621. In the first-cited case, the negligence was that of the general contractor. The contractual provision in the contract was similar to that involved here and was held to be admissible merely as evidence of the duty.

The plaintiff relies upon, among other cases, our holding in Simon v. Omaha P. P. Dist., 189 Neb. 183, 202 N. W. 2d 157, which was decided after the trial of this case. Our holding there is clearly distinguishable. In that case the instrumentality which caused the injury was a condition of the premises and the failure of the owner, who was its own general contractor and was in absolute control of the premises through its retained engineer (to whom it had entrusted implementation *195 of safety measures), to cover or barricade an opening as required by the safety code. The condition had existed for many months. The owner and its agent, who had complete control of all safety on the premises, had the right, opportunity, and duty to cover or barricade the opening. This was not the subcontractor’s obligation. In the present case the instrumentality which caused the injury was not the premises, but equipment owned, controlled, and erected by the plaintiff’s employer, the subcontractor. The evidence does not establish that the general contractor had any right to control the instrumentalities used by the subcontractor. It is not clear that the contractual provision gives it that right and nothing in Simon supports such a conclusion. It is clear it did not undertake to exercise control over the machines and equipment of the subcontractor. In Simon we held a general contractor, in control of the premises where work performance under a contract with the owner is to be carried out, owes a duty to persons rightfully on the premises to keep the premisesi in a reasonably safe condition while the contract is in the course of performance. The reach of that holding does not cover the situation we have here.

Plaintiff cites a number of other cases. We believe they are all clearly distinguishable. In Blount Brothers Constr. Co. v. Rose, 274 Ala. 429, 149 S. 2d 821, the general contractor did, in fact, erect and furnish the scaffolding which was found to be inadequate and which caused the injury. In Presser v. Siesel Constr. Co., 19 Wis. 2d 54, 119 N. W. 2d 405, the situation was similar to that in Simon. The general contractor failed to erect a barricade in front of an opening in the structure which was under the control of the general contractor.

In McDonnell v. Wasenmiller, 74 F. 2d 320, the court upheld a jury verdict against the engineer in charge of and who directly supervised the installation of an expansion joint in the steam line which failed because it was not installed in conformity with the contract. *196 The faulty joint was the instrumentality which caused the injury.

In Dinschel v. United States Gypsum Co., 83 Ill. App. 2d 466, 228 N. E. 2d 106, the basis of liability was the Scaffold Act of Illinois which the court interpreted to be applicable to the person “in charge of” the work and held that under the provisions of the contract in question the general contractor was “in charge of” the work within the meaning of the contract and the statute.

The Nebraska statutes pertaining to scaffold safety, sections 48-425 and 48-428, R. R. S. 1943, have been applied by this court to persons who erect, construct, or supply the scaffold.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eastlick v. Lueder Construction Co.
741 N.W.2d 628 (Nebraska Supreme Court, 2007)
Dellinger v. Omaha Public Power District
611 N.W.2d 132 (Nebraska Court of Appeals, 2000)
Whalen v. U S West Communications, Inc.
570 N.W.2d 531 (Nebraska Supreme Court, 1997)
Parrish v. Omaha Public Power District
496 N.W.2d 902 (Nebraska Supreme Court, 1993)
Oddo v. Speedway Scaffold Co.
443 N.W.2d 596 (Nebraska Supreme Court, 1989)
McKinstry v. County of Cass
424 N.W.2d 322 (Nebraska Supreme Court, 1988)
Sullivan v. Geo. A. Hormel and Co.
303 N.W.2d 476 (Nebraska Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
206 N.W.2d 835, 190 Neb. 191, 1973 Neb. LEXIS 661, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hand-v-rorick-construction-company-neb-1973.