Whalen v. U S West Communications, Inc.

570 N.W.2d 531, 253 Neb. 334, 1997 Neb. LEXIS 226
CourtNebraska Supreme Court
DecidedNovember 21, 1997
DocketS-95-1181
StatusPublished
Cited by62 cases

This text of 570 N.W.2d 531 (Whalen v. U S West Communications, Inc.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whalen v. U S West Communications, Inc., 570 N.W.2d 531, 253 Neb. 334, 1997 Neb. LEXIS 226 (Neb. 1997).

Opinion

Wright, J.

Michael Whalen appeals the district court’s summary judgment in favor of U S West Communications, Inc. (U S West). The court concluded that U S West neither owed nor breached a duty of due care to Whalen and ordered Whalen’s action against U S West dismissed with prejudice.

I. SCOPE OF REVIEW

In reviewing a summary judgment, an appellate court views the evidence in a light most favorable to the party against whom the judgment is granted and gives such party the benefit of all reasonable inferences deducible from the evidence. Kramer v. Kramer, 252 Neb. 526, 567 N.W.2d 100 (1997); Bowling Assocs. Ltd. v. Kerrey, 252 Neb. 458, 562 N.W.2d 714 (1997).

When reviewing a question of law, an appellate court reaches a conclusion independent of the lower court’s ruling. Heins v. Webster County, 250 Neb. 750, 552 N.W.2d 51 (1996).

II. FACTS

On May 24, 1990, while working as a laborer with Diamond Engineering (Diamond) on a U S West jobsite located near Schuyler, Nebraska, Whalen received serious injuries when a manhole cover fell on top of him. Gary Anderson, a Diamond employee, and Dale Krotz, also a Diamond employee, were working with Whalen unloading and placing manhole cover assemblies.

On the day in question, David Ross, the U S West contract inspector, delivered two manhole cover assemblies to the job-site so that Diamond employees would not have to make a special trip to the U S West storage facility to get them. Ross arrived at the jobsite with two manhole cover assemblies in the back of his truck, and Krotz and Ross both decided that the manhole cover assemblies would be unloaded. Krotz reasoned that it would be easier to move the manhole cover assemblies *337 directly from the truck to their places on the manhole vaults, rather than unloading them onto the ground and then moving them into place. Krotz testified that Ross had no part in making this decision and that Ross had stated only that he would like to have the manhole cover assemblies removed from his truck before he left later that day. Krotz said there was no time pressure on the crew to remove the manhole cover assemblies or to have them in place before the weekend began.

In order to lift the manhole cover assemblies out of Ross’ truck, the Diamond crew used a cable sling apparatus, which is attached to the bucket on the arm of a backhoe tractor. Typically, such a sling apparatus has four cables which have clips at one end that are attached to an item the crew wishes to move. For some reason, the cable sling apparatus used on May 24, 1990, had only three operable cables. Krotz indicated that although having four cables was optimal, the manhole cover assemblies could be safely unloaded and placed using only three cables.

Whalen, Anderson, and Krotz worked on unloading and placing the manhole cover assemblies. Krotz operated the backhoe, while Whalen and Anderson attached the cables to a manhole cover assembly and stabilized it as it was lowered into place.

The first manhole cover assembly was installed without incident. Then Krotz lowered the cable sling apparatus toward the second manhole cover assembly in Ross’ truck and waited for Whalen and Anderson to attach each cable to it. The facts do not indicate why, but Whalen and Anderson attached only two of the three cables to the manhole cover assembly. Krotz stated that he did not realize that Whalen and Anderson had attached only two of the three operable cables until the manhole cover assembly was high enough in the air that he could see it. Upon noticing that only two cables were attached, Krotz became concerned about the stability of the manhole cover assembly and told Whalen and Anderson that one of the men would have to hold onto one side of it in order to stabilize it. Whalen responded to Krotz’ direction and reached up to stabilize the manhole cover assembly. As he touched the manhole cover assembly, it tipped, and the steel manhole cover fell onto Whalen, severely injuring him.

*338 Whalen received workers’ compensation benefits from Diamond’s workers’ compensation carrier, St. Paul Insurance Company (St. Paul), for the injuries he sustained. Whalen then filed the instant action, alleging that his injuries were caused by the negligence of U S West.

In its answer and response to requests for admissions, U S West stated it was the owner and general contractor of the job-site when Whalen was injured. A motion for summary judgment filed by U S West was denied on the grounds that U S West had admitted that it was the owner and general contractor of the job-site on which Whalen was injured and that, therefore, a genuine issue of material fact remained as to U S West’s control and supervision of the jobsite and the employees. U S West moved to amend its answer and response to the request for admissions because these admissions were factually erroneous. The district court granted the amendments, and U S West filed an amended answer denying it was its own general contractor on the jobsite in question.

Following the commencement of this action, a liability coverage dispute arose between U S West and St. Paul. Subsequently, U S West and Whalen began settlement negotiations, and a document entitled “Consent to Entry of Judgment” was drafted. This document would have enabled Whalen to obtain a judgment in a specific amount in exchange for his agreement to execute the judgment only against the insurance policy issued by St. Paul or against Diamond. The above document required court approval before it would become effective. It also contained a signature line for St. Paul. The document was submitted to the court for approval, but was not signed by St. Paul. St. Paul filed an objection with the court, arguing, inter alia, that it had not consented to the agreement and that the court should not enforce it without consent of all parties. The court agreed and refused to enforce the agreement.

After the parties engaged in additional discovery, U S West filed a second motion for summary judgment, which the court sustained. Whalen timely appealed, and pursuant to our authority to regulate the dockets of the Nebraska Court of Appeals and this court, we removed the appeal to our docket.

*339 III. ASSIGNMENTS OF ERROR

Summarized and restated, Whalen assigns the following errors to the district court: (1) The district court erred as a matter of law by permitting St. Paul to assert its subrogation lien and object to the settlement agreement between U S West and Whalen, and (2) the district court erred in granting summary judgment because it failed to give Whalen all favorable inferences of fact, and genuine issues of material fact remain.

IV. ANALYSIS

1. Settlement Agreement

Whalen argues that the district court erred by permitting St. Paul to assert its subrogation lien and erred by permitting St.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Estate of Meyers
Nebraska Court of Appeals, 2025
Jaksha v. Jaksha
319 Neb. 308 (Nebraska Supreme Court, 2025)
Sundermann v. Hy-Vee
306 Neb. 749 (Nebraska Supreme Court, 2020)
Lamprecht v. Schluntz
Nebraska Court of Appeals, 2015
Buck's, Inc. v. City of Omaha
Nebraska Court of Appeals, 2014
Gaytan v. Wal-Mart
289 Neb. 49 (Nebraska Supreme Court, 2014)
Sturzenegger v. FATHER FLANAGAN'S BOYS'HOME
754 N.W.2d 406 (Nebraska Supreme Court, 2008)
Semler v. Sears, Roebuck and Co.
689 N.W.2d 327 (Nebraska Supreme Court, 2004)
Richards v. Meeske
675 N.W.2d 707 (Nebraska Court of Appeals, 2004)
Misle v. HJA, INC.
674 N.W.2d 257 (Nebraska Supreme Court, 2004)
Parizek v. RONCALLI CATHOLIC HIGH SCHOOL
655 N.W.2d 404 (Nebraska Court of Appeals, 2002)
Reeder v. State
649 N.W.2d 504 (Nebraska Court of Appeals, 2002)
Ray v. Argos Corp.
612 N.W.2d 246 (Nebraska Supreme Court, 2000)
Dellinger v. Omaha Public Power District
611 N.W.2d 132 (Nebraska Court of Appeals, 2000)
Holt County School District No. 0025 v. Dixon
594 N.W.2d 659 (Nebraska Court of Appeals, 1999)
Cook v. Nebraska Public Power District
171 F.3d 626 (Eighth Circuit, 1999)
Schweitzer v. American National Red Cross
591 N.W.2d 524 (Nebraska Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
570 N.W.2d 531, 253 Neb. 334, 1997 Neb. LEXIS 226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whalen-v-u-s-west-communications-inc-neb-1997.