Dellinger v. Omaha Public Power District

611 N.W.2d 132, 9 Neb. Ct. App. 307, 2000 Neb. App. LEXIS 158
CourtNebraska Court of Appeals
DecidedMay 30, 2000
DocketA-99-210, A-99-211
StatusPublished
Cited by7 cases

This text of 611 N.W.2d 132 (Dellinger v. Omaha Public Power District) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dellinger v. Omaha Public Power District, 611 N.W.2d 132, 9 Neb. Ct. App. 307, 2000 Neb. App. LEXIS 158 (Neb. Ct. App. 2000).

Opinion

Irwin, Chief Judge.

I. INTRODUCTION

Bobby G. Dellinger appeals from a judgment entered in favor of Omaha Public Power District (OPPD), Standard Sheet Metal, Inc. (Standard), Foley Company (Foley), A.L.M. Corporation (A.L.M.), and John Wichman in this action for injuries sustained while Dellinger was employed by Foley’s subcontractor, Standard, on a construction project on OPPD property. We find that OPPD did not maintain sufficient control over the construction project to be liable for Dellinger’s injuries, that the injuries were not the result of a peculiar risk sufficient for Foley to be liable for Dellinger’s injuries, and that A.L.M. and Wichman did not breach any duty owed to Dellinger. Accordingly, we affirm the judgment of the district court.

II. BACKGROUND

According to the record, Dellinger was a sheet metal worker for over 30 years. On August 19, 1992, Dellinger was working on a project on OPPD property in Nebraska City, Nebraska. Foley had contracted with OPPD, and Foley was the general contractor on the project.

On August 19, 1992, Dellinger was working on the roof of an OPPD powerhouse. Dellinger testified that he was using a wheel hoist to pull cable up to the roof. As Dellinger was guiding the *309 cable, the wheel hoist came loose from an I-beam. Dellinger grabbed the cable with his right hand to keep it from falling and experienced pain in his arm, neck, and back.

On November 8, 1994, Dellinger filed an amended petition alleging negligence on the part of OPPD and Foley. On December 27, 1996, Dellinger filed an amended petition alleging negligence on the part of A.L.M. and Wichman. The two cases were consolidated for trial, and a jury trial was waived.

On September 24, 1998, the parties filed a stipulation of facts. The parties stipulated that OPPD and Foley entered into a contract for work to be performed at the Nebraska City power plant, that Foley entered into a subcontractor agreement with Standard to build “explosion panels,” and that the incident which formed the basis of Dellinger’s claim occurred on August 19, 1992. The parties stipulated that Dellinger was performing his job duties for Standard and that the wheel hoist involved in the incident was owned by Standard.

On January 15, 1999, the district court entered a judgment in these consolidated cases. The court found that OPPD did not retain control of the project or of Foley and did not exercise actual control during the project. The court found that Foley did not maintain control of work done by Standard or Standard’s employees. The court also found that A.L.M. and Wichman did not exercise any control, but were hired by OPPD to conduct inspections for quality control purposes only. The court found that neither OPPD nor Foley failed to provide a safe workplace and found that no special risk or danger was involved in this case. The court entered judgment in favor of the defendants.

On January 25, 1999, Dellinger filed a motion for new trial. The court overruled the motion on February 3. This timely appeal followed.

III. ASSIGNMENTS OF ERROR

On appeal, Dellinger has assigned three errors. First, Dellinger asserts that the district court erred in finding that OPPD did not retain sufficient control to have a nondelegable duty to provide a safe workplace. Second, Dellinger asserts that the district court erred in finding that Foley did not have a nondelegable duty to ensure the wheel hoist was safe. Third, *310 Dellinger asserts that the district court erred in finding that A.L.M. and Wichman owed no duty to Dellinger.

IV. ANALYSIS

1. Standard of Review

In a bench trial of a law action, a trial court’s factual findings have the effect of a jury verdict and will not be set aside on appeal unless clearly erroneous. General Fiberglass Supply v. Roemer, 256 Neb. 810, 594 N.W.2d 283 (1999). The appellate court does not reweigh the evidence but considers the judgment in a light most favorable to the successful party and resolves evidentiary conflicts in favor of the successful party, who is entitled to every reasonable inference deducible from the evidence. Id.

For actionable negligence, there must be a defendant’s legal duty to protect the plaintiff from injury, a failure to discharge that duty, and damage resulting from such undischarged duty. Parrish v. Omaha Pub. Power Dist., 242 Neb. 783, 496 N.W.2d 902 (1993). “Duty” is a question of whether the defendant is under any obligation for the benefit of the particular plaintiff, and in negligence cases, the duty is to conform to the legal standard of reasonable conduct in light of the apparent risk. Id. A duty in negligence cases may be defined as an obligation to which the law will give recognition and effect to conform to a particular standard of conduct toward another. Id. The question of whether a legal duty exists for actionable negligence is a question of law dependent on the facts in a particular situation. Id.

2. OPPD

Generally, one who employs an independent contractor is not liable for the contractor’s negligence. Parrish v. Omaha Pub. Power Dist., supra. However, the employer of an independent contractor may be liable if the employer retains control over the contractor’s work, or if, by rule of law or statute, the employer has a nondelegable duty to protect another from harm caused by the contractor. Id. As such, a property owner who employs a general contractor may be held liable for injuries to a subcontractor’s employee where the property owner retains suf *311 ficient control over the work done on the premises, or if there is a nondelegable duty to protect the subcontractor’s employee from harm. See id.

In the present case, Dellinger’s assigned error challenges the district court’s finding that OPPD did not retain control over the work. Dellinger does not assign anything concerning any nondelegable duty owed by OPPD, and we, accordingly, will not further consider any nondelegable duties OPPD may have owed to Dellinger.

In Parrish v. Omaha Pub. Power Dist., supra, the Supreme Court held that OPPD, as owner of the premises, could be held liable for injuries to a subcontractor’s employee if OPPD was found to have retained control over the contractor’s work. Generally, the court has required that the owner retain control of the premises before liability is imposed and that an owner might be considered to maintain adequate “possession” if the owner’s involvement in overseeing the construction is substantial. See Hand v. Rorick Constr. Co., 190 Neb. 191, 206 N.W.2d 835 (1973). See, also, Parrish v. Omaha Pub.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Buresh v. Reinke
28 Neb. Ct. App. 47 (Nebraska Court of Appeals, 2020)
Gaytan v. Wal-Mart
289 Neb. 49 (Nebraska Supreme Court, 2014)
Eastlick v. Lueder Construction Co.
741 N.W.2d 628 (Nebraska Supreme Court, 2007)
Reeder v. State
649 N.W.2d 504 (Nebraska Court of Appeals, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
611 N.W.2d 132, 9 Neb. Ct. App. 307, 2000 Neb. App. LEXIS 158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dellinger-v-omaha-public-power-district-nebctapp-2000.