McDonnell v. Wasenmiller

74 F.2d 320, 1934 U.S. App. LEXIS 3951
CourtCourt of Appeals for the Eighth Circuit
DecidedNovember 26, 1934
DocketNo. 10048
StatusPublished
Cited by8 cases

This text of 74 F.2d 320 (McDonnell v. Wasenmiller) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDonnell v. Wasenmiller, 74 F.2d 320, 1934 U.S. App. LEXIS 3951 (8th Cir. 1934).

Opinion

WOODROUGH, Circuit Judge.

This is an appeal by Robert E. McDonnell from a judgment for $20,000 against him entered upon the verdict of a jury in favor of plaintiff, the personal representative of Alexander Wasenmiller, deceased, in an action for damages for .alleged negligence resulting in death. The decedent died from injuries inflicted by the escape of steam in the steam tunnel of the heating plant which supplies the University of Nebraska and the State Capitol, at Lincoln, Nob.

The action was begun in the state court against Robert E. McDonnell, senior member of the copartnership engaged in the business [322]*322o£ civil engineering under the firm name of Burns & McDonnell Engineering Company (Rowland v. Shephard, 27 Neb. 494, 43 N. W. 344; First Nat. Bank v. Sloman, 42 Neb. 350, 60 N. W. 589, 47 Am. St. Rep. 707; Stone v. Neeley, 42 Neb. 567, 60 N. W. 965; Hanna v. Emerson, 45 Neb. 708, 64 N. W. 229; Independent Elevators v. Davis, 116 Neb. 397, 217 N. W. 577), the copartnership of Grant & Fulton and its individual members, and the Board of Regents of the University of 'Nebraska, the employer of the deceased, by reason of the right of subrogation which accrues to the Board under the Nebraska Workmen’s Compensation Act. Comp. St. Neb. 1929, § 48-118; Bronder v. Otis Elevator Co., 121 Neb. 581, 237 N. W. 671. On Saturday, March 11, 1933, an order dismissing the case without prejudice was entered in the state court reciting that it was “by stipulation” and requiring each party to pay his own costs. On the following Monday, March 13th, at the same term of the court, motions were filed by the plaintiff and the defendant, University of Nebraska, to vacate the order of.dismissal and reinstate the ease. Objections were filed to the motions and after a hearing the state court sustained the motions and reinstated the ease. Thereupon Robert E. McDonnell obtained removal to the federal court and some months .later filed a so-called supplemental answer to the plaintiff’s petition in which he alleged that the order of the state court vacating the dismissal and reinstating the ease was void for want of jurisdiction of the court and that the order of dismissal should be held to bar further proceedings in the case. The Federal District Court sustained a motion to. strike the supplemental answer from the files and there was a jury trial resulting in the judgment against Robert E. McDonnell, from which he prosecutes this appeal.

It appears that a Joint Commission, consisting of the Capitol Commission and the Board of Regents of the University of Nebraska, was created, pursuant to statute, for the purpose of providing a heating plant to serve the University and the State Capitol at Lincoln. In May, 1929, the Commission engaged the services of Burns & McDonnell Engineering Company to make the necessary preliminary estimates, surveys, and investigations of the proposed power, heat, and -light plant improvements; to “prepare detailed working plans and complete specifications covering all parts of the final 'work for which funds are authorized”; “to furnish the contract forms for contractors”; “to attend the letting of contracts and construction”; to advise the Joint Commission in the “proper selection of materials and equipment”; “to furnish a competent and experienced engineer for the supervision of the proposed improvement,” such supervising engineer’s services to begin “at the notification of the owner that the contractor is ready to begin construction work” and to “terminate at the final completion of construction work.” Upon completion of the construction work the engineers agreed to conduct final operating tests of the entire completed works.

Grunwald & Co. was awarded a contract for the construction and installation of the heating plant equipment in a building on the campus of the University and W. H. Pearce Company was awarded a contract for the construction and installation of the underground conduit system from the Capitol to the heating plant. The north end of the conduit piping ran through a concrete tunnel 7 feet high and 8 feet wide for about 1,100 feet and the 'conduit system when connected with the heating plant formed the complete heat generating and conveyor system.

Burns & McDonnell Engineering Company made all the preliminary surveys and estimates and prepared the plans and specifications for the construction work on the whole project. A representative of the-company met with and advised the Commission on the letting of the contracts, approved the contract with W. H. Pearce Company, prepared the Grunwald contract, and, through their supervising engineer, Mr. Meseck, had constant supervision of the work from September 23, 1929, until December, 1930.

The Commission also entered into an agreement with Grant & Fulton, local engineers, by which the latter were to inspect the materials and,supervise the installation of the conduit line. The agreement provided that they were to collaborate with the firm of Burns & McDonnell, “who are to furnish consultant service on the conduit work which firm will specify the sizes of pipe and conduit and approve design.”

W. H. Pearce Company completed the conduit line from the Capitol to the heating plant about February 1, 1930. The north end of this conduit line consisted of a section of 10-ineh pipe about 20 feet long extending from the last expansion joint in the tunnel to a point just beyond the south wall of the basement of the heating plant. At that time construction of the heating plant by the Grunwald Company had not begun, hence no connection or joinder could be made with the pipe line thus completed by the Pearce Com[323]*323pany. In February, 1930, Mr. Lambert, of Burns & McDonnell Engineering Company, inspected the eonduit work done under the Pearce contract and approved it for final payment. On June 19, 1930, after another inspection, Mr. Lambert directed the W. II. Pearce Company to do certain work of tightening, replacing, and packing of joints. Inspection of the conduit was made after the accident by representatives of the same company and it submitted a formal report to the Commission containing recommendations for certain alterations.

The construction of the heating plant by Grunwald & Co. was begun in March, 1930, and continued until September 6, 1930 (the date of the explosion here involved), under the constant supervision of Mr. Meseck, supervising engineer for Burns & McDonnell. The connection between the main pipe line in the heating plant with the north end of the conduit line, installed by Pearce Company, was made in August, 1930. The pipe within the plant, as installed by Grunwald & Co., ran from the boilers west along the ceiling of the basement. It then dropped down from the ceiling at a right angle for about 7 feet and turned horizontally to join with the end of the conduit line left open by the Pearce Company just inside the wall of the plant. There the connection with that end of the conduit pipe was made by means of a steel flange. The other end of this last section of eonduit pipe rested in an expansion joint in the tunnel, but no anchorage of any kind had been installed by the Pearce Company to hold it in the expansion joint. It was ultimately joined to the pipe connecting the heating plant by some workmen in the employ of the University.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peredia v. HR Mobile Services, Inc.
California Court of Appeal, 2018
Peredia v. HR Mobile Servs., Inc.
236 Cal. Rptr. 3d 157 (California Court of Appeals, 5th District, 2018)
Davis v. United States
395 F. Supp. 793 (D. Nebraska, 1975)
Hand v. RORICK CONSTRUCTION COMPANY
206 N.W.2d 835 (Nebraska Supreme Court, 1973)
Pastorelli v. Associated Engineers, Inc.
176 F. Supp. 159 (D. Rhode Island, 1959)
Marine Insurance Company v. Strecker
100 So. 2d 493 (Supreme Court of Louisiana, 1958)
Goade v. Vollrath
81 F. Supp. 971 (W.D. Missouri, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
74 F.2d 320, 1934 U.S. App. LEXIS 3951, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdonnell-v-wasenmiller-ca8-1934.