Rausch v. Julius B. Nelson and Sons, Inc.

149 N.W.2d 1, 276 Minn. 12, 1967 Minn. LEXIS 976
CourtSupreme Court of Minnesota
DecidedFebruary 3, 1967
Docket40060
StatusPublished
Cited by18 cases

This text of 149 N.W.2d 1 (Rausch v. Julius B. Nelson and Sons, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rausch v. Julius B. Nelson and Sons, Inc., 149 N.W.2d 1, 276 Minn. 12, 1967 Minn. LEXIS 976 (Mich. 1967).

Opinion

Nelson, Justice.

In this action for death by wrongful act, there was a jury verdict for plaintiff against both defendants. Plaintiff appeals from an order setting aside the verdict and granting judgment in favor of defendants. The trial court held that the conduct of the decedent in voluntarily exposing himself to a known or obvious hazard which the ordinarily prudent person would not do required findings that decedent was guilty of assumption of risk and contributory negligence as a matter of law and that his conduct was the proximate cause of his death.

The fatal accident which resulted in this litigation occurred during the *14 construction of the Nine Mile Creek School in the city of Bloomington, Minnesota. The general construction contractor for this school was defendant Adolfson and Peterson, Inc., hereinafter referred to as A & P. A & P subcontracted the painting and decorating to defendant Julius B. Nelson and Sons, Inc., hereinafter referred to as Nelson. Separate contracts were made by the school district with another contractor for the mechanical work and with Tieso Electric Company for the electrical wiring. Tieso’s foreman was Donald Rausch, plaintiff’s decedent, who had been employed by Tieso for 7 or 8 years. Another employee of Tieso, who was subordinate to decedent, was Arthur Brophy.

There is very little dispute as to the basic facts. As the building neared completion, some 90 doors were delivered and placed in the school’s auditorium. These doors were approximately 3x7 feet in size, 2 inches thick, and weighed about 90 pounds each. Nelson was notified of their arrival since it had the job of staining and sealing the doors and the frames in which the doors were to be hung. James Nelson, Nelson’s chief executive officer, determined the method of performance of the painting contract and coordinated Nelson’s activities with those of the other contracting trades. On Monday, June 25, 1962, two of Nelson’s employees stained the doors. When each door had been stained, it was placed upright with a top corner touching the north wall of the auditorium and a lower corner as near the wall as possible. A space of about 8 inches was left between the doors as they were so placed. Stacking of doors in this manner is customarily done to facilitate proper drying, especially in hot and muggy weather. After the doors were stained, they were then sealed and again placed against the north wall in the same manner and for the same reason. The doors stood in that position without difficulty from Monday until late Wednesday afternoon.

The painters completed their work on the doors about 1:30 p. m. Tuesday. On Wednesday morning, June 27, they began painting the door frames preparatory to installation of the doors. The doors could not be hung until the frames were dry, so the carpenters were scheduled to hang the doors on Thursday morning.

Late Wednesday afternoon plaintiff’s decedent, Donald Rausch, decided that he wanted to feed wires from one electrical box to another in *15 the auditorium where the doors had been stacked. One of these boxes was in the wall behind the stacked doors and the other box was located just beyond the row of doors. Rausch asked Joseph Scott, A & P’s foreman, to remove the doors. Scott informed Rausch that there was not time to move them that afternoon but that they would be moved the next day, Thursday. Rausch, nevertheless, decided to go ahead and to work in the midst of the stacked doors. He and his helper, Arthur Brophy, decided on their own to remove the doors in front of the box, each carrying one door away. The space left by the removal of these two doors made an opening 23 to 27 inches wide between the angled standing doors.

Rausch went into the opening they had created in the row of doors and pushed a “fish tape” into the box and through the conduit embedded in the wall to the other box, where Brophy was waiting. Brophy then left the auditorium to obtain the proper electrical wires which they were about to use. When Brophy returned he found that Rausch had moved to the box where Brophy had been, so Brophy went to the opening in the row of doors, attached two electrical wires to a hook at the end of the “fish tape,” and began feeding the wires through the box into the conduit while Rausch pulled the “fish tape” out of the other box. In order to do this Brophy, on one knee, crouched down to the box, which was 14 inches above the floor, and pushed the wires, draped over his shoulder, into the box while Rausch pulled at the other end. Brophy’s shoulders were in the narrow oblique opening between the doors and his hands were about 14 inches from the box in the wall.

After about 10 feet of wire had been fed into the box, the door adjacent to Brophy began to fall, striking the door next to it, which in turn struck the one next to it, and so on, domino fashion, with the result that some 43 doors fell. Rausch was struck by the last door in the row and received fatal injuries.

At the trial Brophy first stated that neither he nor the wires touched the doors, and he also said that he could not recollect having said that the wires hit the doors. Later, however, he admitted signing and initialing a statement and further testified that the statement was true and accurate when given. In the statement Brophy had declared that the wire became difficult to pull, there was a jerk of the wire, following which the *16 wire behind him hit the door and caused it and the rest of the row of doors to fall in Rausch’s direction.

After this portion of his statement had been read to him, Brophy was asked whether the report he gave was a correct description of the facts as he had them in mind when he gave the statement, to which he answered, “As I remember them, yes, I suppose.” He later admitted that the jerk of the wire on his shoulders “may have” caused the doors to fall and reiterated that in doing what he did he was following decedent’s instructions.

The record also reveals that defendant A & P, the general construction contractor, did not have general supervision over the premises, nor was it in control of them, although it would require trespassers to leave. Its responsibility was to see that the work progressed properly. It notified the subcontractors when to begin, but the subcontractors determined their own work methods and procedures. The various prime contractors kept in touch with each other to determine the progress of the work but each prime contractor determined the methods of accomplishing its work and came and went as it pleased. Thus no one contractor had any right to supervision or control over the project or over other contractors.

The ultimate question before the court on this appeal is the propriety of the trial court’s order granting judgment non obstante. It is clear that under certain circumstances judgment notwithstanding the verdict may properly be ordered.

“* * * A verdict may be directed only in those unequivocal cases where it clearly appears to the court on the trial that it would be its manifest duty to set aside a contrary verdict as not justified by the evidence or as contrary to the law applicable to the case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eischen v. Crystal Valley Cooperative
835 N.W.2d 629 (Court of Appeals of Minnesota, 2013)
Presbrey v. James
781 N.W.2d 13 (Court of Appeals of Minnesota, 2010)
State Ex Rel. Hatch v. Cross Country Bank, Inc.
703 N.W.2d 562 (Court of Appeals of Minnesota, 2005)
Banovetz v. King
66 F. Supp. 2d 1076 (D. Minnesota, 1999)
Cosgrove v. McDonnell Douglas Helicopter Co.
847 F. Supp. 719 (D. Minnesota, 1994)
Buer v. Atwater State Bank
477 N.W.2d 782 (Court of Appeals of Minnesota, 1991)
Rockney v. Pako Corp.
734 F. Supp. 373 (D. Minnesota, 1988)
Conover v. Northern States Power Co.
313 N.W.2d 397 (Supreme Court of Minnesota, 1981)
Keith Vagle v. Pickands Mather & Company
611 F.2d 1212 (Eighth Circuit, 1980)
Bigham v. J. C. Penney Co.
268 N.W.2d 892 (Supreme Court of Minnesota, 1978)
Hite v. Maritime Overseas Corporation
380 F. Supp. 222 (E.D. Texas, 1974)
Hand v. RORICK CONSTRUCTION COMPANY
206 N.W.2d 835 (Nebraska Supreme Court, 1973)
Keefer v. Al Johnson Construction Co.
193 N.W.2d 305 (Supreme Court of Minnesota, 1971)
Olson v. Kilstofte and Vosejpka, Inc.
327 F. Supp. 583 (D. Minnesota, 1971)
Ford v. Stevens
157 N.W.2d 510 (Supreme Court of Minnesota, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
149 N.W.2d 1, 276 Minn. 12, 1967 Minn. LEXIS 976, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rausch-v-julius-b-nelson-and-sons-inc-minn-1967.