Miller v. Weinberg

190 A.2d 27, 56 Del. 87, 6 Storey 87, 1962 Del. Super. LEXIS 104
CourtSuperior Court of Delaware
DecidedAugust 28, 1962
Docket1404
StatusPublished
Cited by3 cases

This text of 190 A.2d 27 (Miller v. Weinberg) is published on Counsel Stack Legal Research, covering Superior Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. Weinberg, 190 A.2d 27, 56 Del. 87, 6 Storey 87, 1962 Del. Super. LEXIS 104 (Del. Ct. App. 1962).

Opinion

Lynch, Judge.

*88 The defendants, Bernard Weinberg and Harry Ruben-stein, compose a partnership; they trade as Atlantic Engineering & Construction Co. (they will be referred to hereafter as Atlantic). Atlantic was the general contractor, constructing a number of houses at a sub-division near Wilmington, Delaware, known as Alban Park. Chesin Roofing Company, Inc. (referred to hereafter as Chesin) was the roofing sub-contractor on the project. The plaintiff Miller was one of its employees, and foreman of Chesin’s crew.

Miller alleges he fell on October 12, 1959 while working on a scaffold at the construction site. When he fell he claims to have sustained allegedly serious physical injuries, and he has sued.

Miller charges in his complaint that “a scaffold plank on which he was standing broke in half, thereby causing him to fall approximately twenty-five (25) feet to the ground”.

I have noted that Miller has had wide and long experience in roofing work; he had been so engaged for some fifteen years prior to the accident. He had at times been in that business for himself. He had himself (as was sometimes customary for roofers) built scaffolds of the type involved in this case. Prior to his accident he had been working off and on on the Alban Park job for some six or seven months. I find these matters as facts on which this case is to be determined.

The record demonstrates that Atlantic engaged the services of Zeglin Carpentry (referred to hereafter as Zeglin) to do all the carpenter work at the building project and that Zeglin constructed the scaffolding from which Miller fell. Miller concedes that Zeglin erected the scaffolding and that Zeglin was an independent contractor.

*89 Neither Zeglin nor Ghesin is a party to this suit, either at the suit of Miller or through Third Party Proceedings instituted by Atlantic.

Miller has contended that Atlantic undertook to furnish the scaffold. Miller points to a contract between Atlantic and Chesin and he argues that this contract shows Atlantic agreed to furnish the scaffolding.

This contract between Atlantic and Chesin was made a part of the record by stipulation; to say the least it is ambiguous, and some analysis and construction is in order to determine its precise meaning.

Paragraph 1, inter alla,, provided that “The Subcontractor [Chesin] will, * *, provide all the materials and perform all of the following work:

“Do all Roofing, Siding, Flashing and Spouting work. * * *”

Paragraph 2 obligated the “contractor” [Atlantic] to furnish drawings, plans and specifications necessary or useful to facilitate progress of the work.

Paragraph 8 provided:

“The Contractor will, at all times * * * provide a sufficient number of workmen [and] will at all times during the progress of said work furnish and supply all needful materials * * * in accordance with the plans and specifications covering said work.” (Emphasis supplied)

The use of the word “Contractor” in this paragraph 3 creates the ambiguity. Paragraph 1, it is to be noted, required Chesin to “provide all the materials” and toi “perform the work” described. Paragraph 3 also obligated someone to “furnish and supply all needful materials”. *90 Paragraph 1 and paragraph 3 are seemingly in conflict; this makes the entire contract ambiguous and its meaning doubtful.

After study of the entire contract I venture the observation that the term “Contractor” in paragraph 3 should read “Sub-Contractor”, and I so construe the contract because to so read the contract better expresses the otherwise expressed intent of the parties and what they seemed to have contemplated. There are no provisions other than those mentioned in the contract which spell out any obligation by Atlantic to supply scaffolding. Using the term “Sub-contractor” makes the contract read with more sense and purpose, and as so read it tends to destroy many of Miller’s factual contentions. I, therefore, rule there was no expressed assumption of responsibility on Atlantic to furnish the scaffold.

Miller arrived at the job around 8:00 o’clock on the morning of October 12, 1959, — the day of the accident. He worked on the scaffold, from which he later fell, throughout most of the day until the time of the accident. It is clear, therefore, that he had bad a chance to look at and over the scaffold from which he fell. He testified that in his opinion the construction of the scaffold was adequate; in fact, he testified that the construction of the scaffold was in the usual form. It appears too that if Miller had not liked the construction of the scaffold, or wanted to move the planks around for whatever purpose he desired, he was perfectly free to do so.

At about 3:30 P. M. the plank on which Miller was standing allegedly broke in half, causing him to fall approximately twenty-five feet to the ground. He was injured by reason of such fall.

Miller’s complaint charges several acts of alleged negligence on the part of Atlantic. Atlantic’s answers deny *91 the factual background of these alleged acts of negligence, and the answer affirmatively pleads contributory negligence on Miller’s part.

Both sides engaged in pre-trial discovery and the case is now before the Court on Atlantic’s motion for summary judgment, based on the matters developed in the course of discovery.

Plaintiff charges as one of his grounds of alleged negligence that Atlantic violated Title 16, Del. C., § 7701, in that Atlantic failed to furnish the plaintiff a safe, suitable and proper scaffold from which to work. The cited statute reads:

“(a) A person employing or directing another to perform labor of any kind in the erection, repairing, altering or painting of a house, building or structure shall not furnish or erect, or cause to be furnished or erected for the performance of such labor, scaffolding, hoists, stays, ladders or other mechanical contrivances which are unsafe, unsuitable or improper, and which are not so constructed, placed and operated as to give proper protection to the life and limb of a person so employed or engaged.” (Emphasis supplied)

It is to be noted that this statute applies only to a person employed by the person who allegedly furnished the “scaffolding” or other specified equipment or the “mechanical contrivances” which are “unsafe, unsuitable or improper” or which are so “constructed, placed and operated” as to fail “to give proper protection to the life and limb of a person so employed * * The statute may also apply if the person furnishing the scaffolding, specified equipment or mechanical contrivances “directs” the labor of a person using such scaffolding, equipment or mechanical contrivances.

*92

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hand v. RORICK CONSTRUCTION COMPANY
206 N.W.2d 835 (Nebraska Supreme Court, 1973)
Balma v. Tidewater Oil Company
214 A.2d 560 (Supreme Court of Delaware, 1965)
Slovin v. Gauger
193 A.2d 452 (Superior Court of Delaware, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
190 A.2d 27, 56 Del. 87, 6 Storey 87, 1962 Del. Super. LEXIS 104, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-weinberg-delsuperct-1962.