Garfield & Proctor Coal Co. v. Pennsylvania Coal & Coke Co.

84 N.E. 1020, 199 Mass. 22, 1908 Mass. LEXIS 779
CourtMassachusetts Supreme Judicial Court
DecidedMay 20, 1908
StatusPublished
Cited by25 cases

This text of 84 N.E. 1020 (Garfield & Proctor Coal Co. v. Pennsylvania Coal & Coke Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Garfield & Proctor Coal Co. v. Pennsylvania Coal & Coke Co., 84 N.E. 1020, 199 Mass. 22, 1908 Mass. LEXIS 779 (Mass. 1908).

Opinion

Sheldon, J.

We are of opinion that the contract in suit called for a shipment of twenty-five hundred tons of coal per month from September 1, 1902, to April 1, 1903. The express language of the,defendant’s agreement was that the shipments of coal were to be “ 2500 tons per month ” during that time, at a price of $2.80 per ton; and this is followed by the stipulation that the remainder of the coal should be shipped “in about equal monthly proportions ” during the remainder of the period stated, at a lower price. The contract made a clear distinction between the absolute engagement for the shipment of a fixed quantity during the first months of the time provided for and the qualified stipulation for subsequent shipments “ in about equal monthly proportions,” although each part of the undertaking was made subject to strikes, etc. The subsequent stipulation providing a mode for the assessment of damages if shipments were not made in “ about equal monthly quotas,” cannot control the express stipulation with which the contract opens. This latter clause was inserted, not for the purpose of defining8 the obligation assumed by the defendant, but to provide a ready means of settling the damages and making a resort to litigation unnecessary if the defendants should fail to ship in about equal monthly quotas the amount stipulated for during the first period. The utmost effect that can be given to the words “ in about equal monthly quotas ” in this clause is to treat them as giving to the defendant liberty to ship somewhat more than twenty-five hundred tons in any particular month. This was the construction [37]*37of the contract adopted by the learned judge of the Superior Court before whom the case was tried; and it was correct. The defendant was in default for a failure to ship the stipulated amount of twenty-five hundred tons during any one of these months, and would be liable therefor in damages unless there was some legal excuse for such default.

The correspondence and negotiations between the parties before the making of the contract were indeed competent under the circumstances of the case as an aid in construing the language in which they finally embodied their contract. Smith v. Vose & Sons Piano Co. 194 Mass. 193. United States v. Bethlehem Steel Co. 205 U. S. 105. But it remains true, as was stated in both of these cases, that this evidence is received, not to frame a new contract between the parties, but to enable the court to understand the subject matter of the agreement as it lay in their minds, and to determine the meaning which they themselves put upon any doubtful or ambiguous terms which may have been used, and so to apply their language correctly to the subject matter which was in their contemplation. Merely tentative offers made by either party while they were endeavoring to reach an agreement cannot control the plain meaning of the contract which they finally concluded.

Accordingly the defendant’s first and second requests for rulings were rightly refused.

The judge refused to give the defendant’s fourth and fifth requests, but did rule that the defendant was not bound to load more than twenty-five hundred tons per month upon any vessel or vessels which the plaintiffs might furnish. The coal was all actually shipped at Greenwich Piers in Philadelphia, in accordance with the option given in the contract. The facts found by the auditor and the rulings made by him, which were substantially adopted by the judge, were as follows: “ Was the date when the coal was put on the vessel at Greenwich Piers the date of shipment? Greenwich Piers is a shipping point for coal, and is located on the Delaware River in Philadelphia. There is no storage for coal on the piers, and the method of loading vessels is briefly as follows: A vessel arriving for coal anchors in the stream to await her turn to load. As soon as opportunity offers, she takes her place at the piers and the coal is dumped into her [38]*38from the railroad cars which have brought it from the mines. When the vessel is loaded, the coal is billed to the consignee, and the vessel leaves the piers. This method was followed by the defendant in the present case. The plaintiff was bound to furnish vessels for the coal which the defendant had contracted to ship, and, when coal was dumped by the defendant into the plaintiff’s vessel, a delivery of coal was made. I am not, however, able to find, in accordance with the defendant’s claim, that the date of dumping the coal was the date of shipment. If this were so, then the dumping of a hundred tons of coal in October into a twenty-five hundred ton vessel which was not loaded until some time in November would constitute an October shipment of coal. The intention and clear meaning of the contract was that the defendant should place twenty-five hundred tons of coal each month on vessels to be furnished by the plaintiff, so that the vessel or vessels could, during the month, sail for their destination with at least twenty-five hundred tons. It was the plaintiff’s duty to furnish each month vessels capable of carrying the twenty-five hundred tons, and failure to do so would excuse the defendant. On the other hand, if the plaintiff, in any one month, sent a vessel capable of carrying more than twenty-five hundred tons, the defendant’s obligation for that month ceased upon its loading twenty-five hundred tons into such vessel during the month. If the plaintiff saw fit to hold the vesssel over for a full cargo, it could not afterwards claim as to that month that the defendant had failed to live up to its obligations. The defendant billed no coal to the plaintiff until the vessels were loaded and ready to sail. I find, in accordance with what was evidently the understanding of both parties, that the date when the vessels were loaded and ready to sail was the date of the shipment.”

Undoubtedly the defendant is right in its contention that the general rule is that goods are shipped when they are put on board of the vessel or vehicle in which they are to be carried, and that an agreement to deliver goods previously unascertained free on board of a vessel or other vehicle of transportation is satisfied and the title passes to the purchaser and the goods are at his risk when the proper goods are actually loaded on board for shipment. The cases cited by the defendant’s counsel fully support this general doctrine. Bowes v. Shand, 2 App. Cas. 455. Ex parte [39]*39Rosevear China Clay Co. 11 Ch. D. 560, 569. Brown v. Hare, 4 H. & N. 822, 829. Mora y Ledon v. Havemeyer, 121 N. Y. 179. Congdon v. Kendall, 53 Neb. 282. Clark v. Lindsay, 19 Mont. 1. But in these decisions the courts were dealing with cases in which all the goods that then were to be shipped had been delivered on board of the cars or vessels, and the seller had done all that he could do to secure the dispatch of all the goods that he was bound then to deliver. A very different state of affairs would have been presented if in Mora y Ledon v. Havemeyer, ubi supra, for example, the plaintiffs had seasonably put on board of the vessel only a portion of the quantity of sugar which they had agreed to deliver within thirty days; and a like statement may be made of the other cases above cited. Here, it was the duty of the plaintiff to furnish vessels of sufficient capacity to carry the coal which the defendant was to ship, and the defendant was under obligation to ship upon such vessels the stipulated amount of coal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sullivan v. O'CONNOR
296 N.E.2d 183 (Massachusetts Supreme Judicial Court, 1973)
Rosenston v. Bickford Shoes, Inc.
166 N.E.2d 698 (Massachusetts Supreme Judicial Court, 1960)
Rizzo v. Cunningham
20 N.E.2d 471 (Massachusetts Supreme Judicial Court, 1939)
Murphy v. Kelley
19 N.E.2d 538 (Massachusetts Supreme Judicial Court, 1939)
Bradley Lumber & Manufacturing Co. v. Cutler
148 N.E. 101 (Massachusetts Supreme Judicial Court, 1925)
Detroit Edison Co. v. Main Island Creek Coal Co.
295 F. 781 (Fourth Circuit, 1924)
Osgood Construction Co. v. Claremont
122 A. 346 (Supreme Court of New Hampshire, 1923)
Boehme & Rauch Co. v. Lorimer
191 N.W. 8 (Michigan Supreme Court, 1922)
Raw Silk Trading Co. v. Katz
201 A.D. 713 (Appellate Division of the Supreme Court of New York, 1922)
Weston v. Ball
116 A. 99 (Supreme Court of New Hampshire, 1922)
Krug Coal Co. v. C. G. Blake Co.
218 Ill. App. 85 (Appellate Court of Illinois, 1920)
American Fuel Co. v. Interstate Fuel Agency
261 F. 120 (Ninth Circuit, 1919)
Acme Mfg. Co. v. Arminius Chemical Co.
264 F. 27 (Fourth Circuit, 1919)
Davison Chemical Co. v. Baugh Chemical Co.
106 A. 269 (Court of Appeals of Maryland, 1919)
New England Concrete Construction Co. v. Shepard & Morse Lumber Co.
107 N.E. 917 (Massachusetts Supreme Judicial Court, 1915)
Canton Co-operative Bank v. American Central Insurance
219 Mass. 132 (Massachusetts Supreme Judicial Court, 1914)
Bigelow Carpet Co. v. Wiggin
95 N.E. 938 (Massachusetts Supreme Judicial Court, 1911)
Derby Desk Co. v. Conners Bros. Construction Co.
90 N.E. 543 (Massachusetts Supreme Judicial Court, 1910)
Nickerson v. Weld
90 N.E. 589 (Massachusetts Supreme Judicial Court, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
84 N.E. 1020, 199 Mass. 22, 1908 Mass. LEXIS 779, Counsel Stack Legal Research, https://law.counselstack.com/opinion/garfield-proctor-coal-co-v-pennsylvania-coal-coke-co-mass-1908.