American Fuel Co. v. Interstate Fuel Agency

261 F. 120, 1919 U.S. App. LEXIS 1729
CourtCourt of Appeals for the Ninth Circuit
DecidedOctober 27, 1919
DocketNo. 3352
StatusPublished
Cited by3 cases

This text of 261 F. 120 (American Fuel Co. v. Interstate Fuel Agency) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Fuel Co. v. Interstate Fuel Agency, 261 F. 120, 1919 U.S. App. LEXIS 1729 (9th Cir. 1919).

Opinion

HUNT, Circuit Judge

(after stating the facts as above). The principal assignments of error are based upon the refusal of the court to give instructions adopting a construction of the contract in accord with the contentions of the shippers. The more important points are involved in the following discussion:

[1, 2] It is argued by the shipping company that the provision in the contract concerning the 2,500 tons per month to be delivered is for the purpose of protecting the shippers against being “swamped” with orders from the jobbers, and was not for the purpose of giving to the jobbers the right to any specific amount of coal. The pertinent clause is:

“The shippers will use diligence to till said orders, but shall not be obligated to ship during any month in excess of 2,500 tons; that this contract snail end and terminate whenever 15,000 tons have been furnished.”

Our understanding of this language is that, if the jobbers should order more than 2,500 tons per month, the shippers would use diligence to fill such order, but that there would be no obligation upon the shippers to ship more than 2,500 tons. The shippers were obligated to ship as much as 2,500 tons per month, if that amount were ordered by the jobbers. “Obligated” means bound to do; and the jobbing company proved to the satisfaction of the jury that 2,500 tons per month never were, but could have been, shipped. On principle, too, if the argument of the shippers is sound, and the provision concerning the 2,500 tons was inserted in the contract with a view to protect the shippers, then a construction should be adopted which would be against the shipper, if the contract is ambiguous in its terms. Page on Contracts, § 1122; Byron v. First Nat. Bank, 75 Or. 296, 146 Pac. 516; Metropolitan Building Co. v. Seattle, 92 Wash. 660, 159 Pac. 793.

[3] It is argued that the court erred in refusing to permit the shipping company during the trial to amend its answer, so as to allege specifically a waiver by the jobbing company of any alleged breach. The argument is that before the conclusion of the evidence certain letters written by the jobbing company to the shipping company were introduced, which tended to show that, if there had been any breach of the contract up to the time of the trial of the present suit, the jobbing company had waived the same. Stress is laid upon a letter by the jobbers, dated August 25, 1917, in which the jobbers stated that they un[124]*124dersiood the difficulties which the shipping company had encountered in meeting the requirements of the railroad for coal, and that the shipping company had the full permission of the jobbing company to “catch up” all back shipments by shipping mine run coal. The letter also states:

“How about sending a few cars right now to help catch up7"

The error of the shipping company lies, we think, in construing the contents of this letter as going to show a Waiver of any damages which had theretofore been sustained by the jobbing company on account of the failure of the shipping company to deliver coal on time. Permission to “catch up” all back shipments by shipping mine run coal merely extended a privilege without consideration; the privilege being revocable at the pleasure of the jobbing company. In Phillips & Colby Construction Co. v. Seymour, 91 U. S. 646, 23 L. Ed. 341, the Supreme Court said:

“If the builder has done a large and valuable part of the work, but yet has failed to complete the whole, or any specific part, of the building or structure within the time limited by his covenant, the other party, when that time arrives, has the option of abandoning tbe contract for such failure, or of permitting tbe party in default to go on. If he abandons the contract and notifies tbe other party, the failing contractor cannot recover on the covenant, because be cannot make or prove tbe necessary allegation of performance on bis own part. * * * But if tbe other party says to him, ‘I prefer you should finish your work,’ or should impliedly say so by standing by and permitting it to be clone, then he so far waives absolute performance as to consent to be liable on his covenant for the contract price of the work whdn completed. For the injury done to him by the broken covenant of the other side, he may recover in a suit on the contract to perform within time; or, if he wait to be sued, be may recoup tbe damage thus sustained in reduction of the sum due by contract price for the completed work.”

See Jessup & Moore Paper Co. v. Piper (C. C.) 133 Fed. 108.

The question of allowing the amendment was discretionary, and we find no error in denying tíre request, especially considering that the shipping company based its defense on the ground that the contract had been performed in compliance with its terms and denied any breach.

[4] Error is assigned to the refusal of the court to give a requested instruction to the effect that the shipper was entitled to an allowance by way of credit for coal which it was obligated to deliver — not for that which it had delivered. The provision of the contract referring to coal shipped to outside firms was that the shippers should have credit “on said 15,000 tons for any coal shipped by them to said firms or corporations under said contracts.” The language, “shipped” by them, makes a distinction between coal actually shipped and that which the shipping company was obligated to ship. This distinction was recognized by the learned District Judge when, in charging the jury, he stated that, if they were satisfied that the existing outside contract between the parties was one for 5,000 tons, then the shipping company would be entitled to a credit for the full amount delivered. The jury found, however, that the contract was not for 5,000 tons, as contended by the shipping company; wherefore any instructions based upon the [125]*125theory that the contract was for 5,000 tons became immaterial, and under no circumstances could they have operated to the prejudice of the shipping company.

It is next argued that the court erred in refusing certain requests for instructions with respect to the measure of damages. The argument is that in one of the affirmative defenses interposed by the shipping company it set up that after the beginning of the action, and before the expiration of the year within which the coal was to be furnish • ed, the shipping company furnished certain coal under the contract to the jobbing company, which coal was received by the latter. We think that the coal transactions had between the shipping company and the jobbers in February and March of 1918 should not. be considered as directly relating to the determination of the controversy, because it was expressly stated in a communication by the jobbers to the shippers that shipments made in February and March should be “accepted without prejudice to this action.” While it is tine that the jobbing company slated to the shipping company that they would only consent to the shipping company being credited in the suit “for any coal so shipped with any profit” made by the jobbing company thereon, it does not appear that the shipping company agreed to ship under such terms. Therefore there was no acceptance of the offer of the jobbing company. Nor did the shipping company plead what the profit was on the February and March shipments by way of lessening damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Detroit Edison Co. v. Main Island Creek Coal Co.
295 F. 781 (Fourth Circuit, 1924)
Boehme & Rauch Co. v. Lorimer
191 N.W. 8 (Michigan Supreme Court, 1922)
Jones v. Heinzle
130 N.E. 815 (Indiana Court of Appeals, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
261 F. 120, 1919 U.S. App. LEXIS 1729, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-fuel-co-v-interstate-fuel-agency-ca9-1919.