Dignan v. Spurr

28 P. 529, 3 Wash. 309, 1891 Wash. LEXIS 160
CourtWashington Supreme Court
DecidedDecember 9, 1891
DocketNo. 303
StatusPublished
Cited by10 cases

This text of 28 P. 529 (Dignan v. Spurr) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dignan v. Spurr, 28 P. 529, 3 Wash. 309, 1891 Wash. LEXIS 160 (Wash. 1891).

Opinion

The opinion of the court was delivered by

Anders, O. J.

The respondent brought this action against appellant to recover damages for an alleged breach of a contract in writing, which is as follows:

“This agreement, made and entered into this 19th day of November, A. D. 1889, by and between James Dignan, of the city of Seattle, King county, State of Washington, party of the first part, and James Spurr, of the same place, the party of the second part:
“Witnesseth, That for and in consideration of the covenants and agreements on the part of said party of the [310]*310second part hereinafter set forth and contained, the said party of the first part agrees to manufacture at his brick yard in West Seattle, in said King county, five hundred thousand (500,000) good merchantable brick, the same to be sold and delivered to the said party of the second part, at the place and for the price hereinafter mentioned.
“Said first party is to commence delivering bricks from the second kiln which he shall burn at his said brick yard, and shall continue to deliver all the brick he shall manufacture from said time until the full amount is delivered.
“Said brick are to be delivered on a scow on such gridirons on the different slips in the city of Seattle water front as shall be most convenient for said second party.
“In consideration of the above, the said party of the second part agrees to buy, purchase and to take from said first party all of said five hundred thousand (500,000) brick upon said terms and conditions above named, and agrees to pay to said party of the first part thirteen dollors ($13) per thousand for all bricks to the amount aforesaid delivered on the gridirons as aforesaid, the said money to be paid when the said second party has promptly taken the brick from the said gridirons, and has delivered them at the buildings in the city of Seattle, where the same are to be used, it being hereby understood and agreed that the said second party is to take them promptly from the said gridirons and is to deliver them promptly at the said buildings aforementioned. In witness whereof,” etc., etc.

The plaintiff alleges in his complaint that he kept and performed all the terms and conditions of the contract on his part, and that between the 11th day of January and the 7th day of May, 1890, he manufactured five hundred thousand good merchantable brick, and as fast as they were manufactured delivered them on gridirons on the water front of the said city of Seattle, at the place designated by defendant as most convenient for him; that the defendant accepted and received two hundred and sixty-seven thousand three hundred and two bricks of the quantity so delivered to him by plaintiff, but wholly failed and refused to accept or receive the remainder thereof, and that [311]*311by reason of such failure and refusal to accept and receive the same the plaintiff was compelled to and did sell the same in such quantities as he could for the best price that the same would bring, of which the defendant had notice; and that by reason of the failure and refusal of defendant to perform his said contract, the plaintiff has sustained damage in the sum of $795.82. The answer of the defendant in substance denies that the plaintiff performed the conditions of the contract on his part; admits that the defendant received and accepted 266,792 brick from the plaintiff; alleges that on or about April 4, 1890, plaintiff and defendant mutually agreed that said contract should be determined and canceled, and accordingly settled and determined the same, and mutually agreed that the settlement then and there had should be considered as a satisfaction in full to both the plaintiff and defendant of all demands and obligations, and of all duties arising under or flowing from the said contract in any manner whatsoever; and sets forth a counter claim for an alleged failure to deliver the brick at the time agreed upon by and between the plaintiff and defendant. Upon the issues raised by the pleadings a trial by a jury was had, resulting in a verdict and judgment for the plaintiff. The defendant appeals.

At the trial the defendant requested the court to instruct the jury to the effect that the parties to a written contract, such as the one sued upon in this case, could, after the same had been partially performed, mutually agree that the same should be canceled and at an end, and that each party should be released from all obligations thereunder. That such an agreement for the annulment and rescission of such a contract need not be in writing. That if the jury believe from the evidence that such an agreement for the annulment or rescission of the contract set out in the plaintiff’s complaint was made, as the defendant in his answer alleges was made, then the parties would be bound by such [312]*312an agreement, and the jury must find for the defendant. That if the jury believe from the evidence that the plaintiff and defendant, as alleged in the affirmative defense pleaded in the defendant's answer, orally agreed between themselves that the contract set out in the plaintiff's complaint should be and was at an end, and that both of the parties thereto should be and were released from all the obligations thereunder, then the jury should find for the defendant. The court refused to so instruct the jury, and failed to give any instructions whatever upon the question of rescission of the contract. In so ruling appellant claims the court erred. And in order to determine the question thus presented it becomes necessary to revert to the testimony.

It appears from the statement of facts in the record that the respondent commenced to deliver the brick to appellant on January 11,1890, and that from that time up to March 28th appellant accepted and received all that were offered, but that he then notified respondent that he would receive no more, for the reason, as he says, that they were not being delivered according to agreement. On April 4-, 1890, the parties had a settlement of their accounts, and appellant gave respondent his check for $650, which he claims were in full payment of all demands up to that date, and which was so stated in the check. Respondent admits the settlement, and also admits that he received the check, but says there was a balance still due him of $6.50, on account. Appellant asserts that at the time he made this payment the contract sued on was rescinded and abandoned by mutual consent. lie specifically testified, in substance, that when he paid the $650 he expected it was accepted in full payment for all brick he had received, and that he was not going to have any more trouble about it; that when lie told respondent he was not going to receive any more brick. the latter did not object to it, but responded that if lie, appellant, had anythhig he would take it out of him, but as [313]*313he had not he would let him go; that he said he did not care whether any more brick were taken by appellant or not, but if he had anything he would take it out of him. He further testified that after the time of the payment by him of the $650, respondent did not deliver or tender to him any more brick, and did not demand any payment for brick delivered or tendered until August 1, 1890, which was just prior to the commencement of this action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allen v. Blyth
23 P.2d 567 (Washington Supreme Court, 1933)
Rowe v. Hosher
193 P. 688 (Washington Supreme Court, 1920)
Wisconsin Lumber Co. v. Pacific Tank & Silo Co.
136 P. 691 (Washington Supreme Court, 1913)
Bamberger Bros. v. Burrows
124 N.W. 333 (Supreme Court of Iowa, 1910)
Garfield & Proctor Coal Co. v. Pennsylvania Coal & Coke Co.
84 N.E. 1020 (Massachusetts Supreme Judicial Court, 1908)
Redlands Orange Growers' Ass'n v. Gorman
54 L.R.A. 718 (Supreme Court of Missouri, 1901)
Redlands Orange Growers Ass'n v. Gorman
76 Mo. App. 184 (Missouri Court of Appeals, 1898)
Hartman v. Fishbeck
18 F. 291 (U.S. Circuit Court for the District of Eastern Wisconsin, 1883)
Forstall v. Consolidated Ass'n of Planters
34 La. 770 (Supreme Court of Louisiana, 1882)
Cook v. Gray
7 Del. 455 (Supreme Court of Delaware, 1862)

Cite This Page — Counsel Stack

Bluebook (online)
28 P. 529, 3 Wash. 309, 1891 Wash. LEXIS 160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dignan-v-spurr-wash-1891.