Consolidation Coal Co. v. Peninsular Portland Cement Co.

272 F. 625, 1921 U.S. App. LEXIS 1660
Court of Appeals for the Sixth Circuit·Decided May 3, 1921·No. No. 3429·Published·Cited by 16 cases

Opinion

KNAPPEN, Circuit Judge.

On April 11, 1916, the Peninsular Portland Cement Company, of Jackson, Mich., contracted with the Consolidation Coal Company of Baltimore, Md., for the purchase of “55,000 to 60,000 tons of Consolidation Fairmont slack coal, less such amount as said Coal Company is unable to ship or Peninsular Portland Cement Company is unable to receive, on account of any strikes, accidents, contingencies of transportation or navigation, or causes beyond the control of either party affecting the shipment, delivery, or receipt of coal to be shipped under this contract,” shipments to be made to the Cement Company, at Cement City, Mich., “in as nearly equal monthly installments as possible during the period beginning at once, 1916, and ending April 15, 1917, subject to above-mentioned contingencies. Failure to- ship or receive coal on account of any of the above-named contingencies shall not require (or give option to) either party to ship or receive in subsequent months the amount of coal not shipped or received during the period of such contingency.” The price of the coal was 75 cents per ton f. o. b. cars at the mines, payment to be made in cash “on the 15th of each month for the preceding month’s shipments”; the terms of payment being made of the “essence of contract,” and noncompliance therewith giving the seller the privilege of cancellation. During the remainder of April, 1916, and throughout the months of May, June, July, and August, shipments were made only as ordered by plaintiff, which in fact received all the coal it desired during those months, unless, perhaps, to the extent of one car in August. The aggregate amount actually shipped, however, lacked about 4,446 tons of a 'full 5,000 tons per month. In September, 1916, and thereafter, a substantial car shortage existed and coal prices advanced.

A controversy arose as to the amount of future deliveries, plaintiff claiming it was entitled to the entire undelivered remainder of the 60,-000 tons, viz. about 42,000 tons, to be ratably distributed during the remaining 7}/¿ months of the contract period, viz. nearly 5,600 tons per month. Defendant, while admitting plaintiff’s right to 5,000 tons per month during the remaining period (subject to defendant’s asserted right to distribute available cars proportionately among all its customers), denied its obligation to make up1 the deficiencies accumulating during the first 4'l/¿ months, due solely to plaintiff’s failure to order. Shipments were continued throughout the contract period, but in no month to the full amount of even 5,000 tons; the total shortage (including that accruing during the first 4% months) being about 19,-492 tons. Plaintiff sued for its damages on account of this shortage. The ultimate issues upon the trial related to, first, plaintiff’s right to cumulate the shortages for the first 4% months; and, second, defendant’s asserted right to: prorate shipments according to car supply. The jury was instructed that it was defendant’s duty from October 21, 1916, to ship to plaintiff the entire theretofore undelivered remainder [628] of the total 60,000 tons (in installments of nearly 5,600 tons per month), unless prevented by car shortage, as to which defendant was allowed relief, provided (1) it used good faith and reasonable care in the taking of contracts, so that it might reasonably expect to be able to secure sufficient cars to fill the contract here in question; (2) and made an honest effort and used reasonable diligence to secure sufficient cars to fill that contract; and (3) distributed the cars which it actually did get among its different customers, so that plaintiff received its fair share — the prescribed measure of damages being the difference between the contract price and the market price of the coal which should have been delivered, taken by months and at the market price ■on the last day of the respective months (less what tire plaintiff could have saved by buying coal below the market), with interest at 5 per cent, from the last day of each month to the time of the trial, deducting from such aggregate $2,560.92, which admittedly plaintiff owed for coal actually delivered.1 Plaintiff recovered verdict and judgment for $39,442.35. Defendant’s motion for new trial was denied.

[1] 1. Except as the situation may be affected by the question of car shortage, it was not error, in our opinion, to instruct the jury, as matter of law, that plaintiff was entitled to the entire undelivered remainder of the 60,000 tons, distributed ratably throughout the remainder of the contract period. While the language of the contract suggests a degree of flexibility in shipments, dependent upon plaintiff’s manufacturing requirements, and while we are not prepared to say that the original contract, standing alone, should be construed, as matter of law, to give plaintiff the right to cumulate deficiencies in the amounts ordered from month to month, although there are considerations strongly suggesting such construction,2 in our opinion it at least cannot be said that the written agreement clearly and unambiguously denied such right, and we think the District Judge correctly held that the parties had themselves practically construed the contract as giving it to plaintiff. We so conclude for these reasons:

Free access — add to your briefcase to read the full text and ask questions with AI

Consolidation Coal Co. v. Peninsular Portland Cement Co., 272 F. 625, 1921 U.S. App. LEXIS 1660 (6th Cir. 1921).

272 F. 625 (Consolidation Coal Co. v. Peninsular Portland Cement Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Haley v. Van Lierop
64 F. Supp. 114 (W.D. Michigan, 1945)
Amsden Lumber Co. v. Stanton
294 P. 853 (Supreme Court of Kansas, 1931)
Edwardsville Coal Co. v. Crown Coal & Coke Co.
20 F.2d 890 (Eighth Circuit, 1927)
Indiana Flooring Co. v. Grand Rapids Trust Co.
20 F.2d 63 (Sixth Circuit, 1927)
Bader Coal Co. v. Quemahoning Coal Co.
14 F.2d 743 (Third Circuit, 1926)
Diamond Alkali Co. v. Henderson Coal Co.
134 A. 386 (Supreme Court of Pennsylvania, 1926)
Corona Coal Co. v. Robert P. Hyams Coal Co.
9 F.2d 361 (Fifth Circuit, 1925)
Kalamazoo Ice & Fuel Co. v. Gerber
4 F.2d 235 (Sixth Circuit, 1924)
Boehmer Coal Co. v. Burton Coal Co.
2 F.2d 526 (Eighth Circuit, 1924)
Deupree v. United States
2 F.2d 44 (Ninth Circuit, 1924)
Detroit Edison Co. v. Main Island Creek Coal Co.
295 F. 781 (Fourth Circuit, 1924)
Robilio v. United States
291 F. 975 (Sixth Circuit, 1923)
Everett v. Emmons Coal Mining Co.
289 F. 686 (Sixth Circuit, 1923)
Boehme & Rauch Co. v. Lorimer
191 N.W. 8 (Michigan Supreme Court, 1922)
Ranney-Davis Mercantile Co. v. Shawano Canning Co.
206 P. 337 (Supreme Court of Kansas, 1922)