Consumers' Bread Co. v. Stafford County Flour Mills Co.

239 F. 693, 152 C.C.A. 527, 1917 U.S. App. LEXIS 2259
CourtCourt of Appeals for the Eighth Circuit
DecidedJanuary 23, 1917
DocketNo. 4677
StatusPublished
Cited by5 cases

This text of 239 F. 693 (Consumers' Bread Co. v. Stafford County Flour Mills Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consumers' Bread Co. v. Stafford County Flour Mills Co., 239 F. 693, 152 C.C.A. 527, 1917 U.S. App. LEXIS 2259 (8th Cir. 1917).

Opinion

AMIDON, District Judge.

On August 15, 1911, the parties to this action entered into a contract in writing by which the defendant, the Stafford County Flour Mills Company, agreed to sell and deliver to the plaintiff, the Consumers’ Bread Company, 10,000 barrels of flour, at $4.25 a barrel, 2,500 barrels to be shipped in each of the four months of January, February, March, and April, 1912, with draft payable on sight to accompany bills of lading. Concessions as to time of delivery were made by each party to the other during and subsequent to the entire period covered by the contract, first at the request of the mills company, and then at that of the bread company. Neither treated the defaults of the other as abrogating any part of the contract. Down to June 1, 1912, only 3,425 barrels of flour had been delivered. The negotiations between the parties were carried on by correspondence which was put in evidence. It leaves no doubt as to the manner in which the parties themselves interpreted their contract, and the waiver of its provisions as to the time of performance. In May and June, however, the mills company began to indicate its inability to complete the delivery of the remaining part of the flour. It did not say that it would not deliver, but, in answer to the-urgent requests of the bread company for shipments, wrote explaining that they had sent their rolls away to be reground, and added:

“We will do all we possibly can to hurry matters up. We will make shipment as soon as we possibly can, hut cannot state exact date.”

May 28th, in answer to a request for shipment, the Mills Company wired, “Will ship car flour to-morrow.” May 29th it again wrote, in answer to a similar request:

“We are very sorry to not be able-to ship as fast as we would like, but wheat has moved out faster than what we had any idea. Trusting that you will hold with us we will do the very best possible.”

At no time did the mills company assert any right of forfeiture under the contract, or treat it as otherwise than in full force. They simply failed to perform. Finally, on June 15th, no further shipments having been made, the bread company purchased flour to supply the balance of the contract, and subsequently brought this action to recover the difference in price.

[ 1 ] The trial court disregarded the interpretation put upon the contract by the parties, and held each installment a distinct obligation, and time the essence of its performance, and, as the bread company failed to buy in the balance of each installment at the end of each month in [695]*695which it was to he delivered, it forfeited all right to damages. There was no conflict in the evidence. Both parties moved for a directed verdict. The trial court directed a verdict in favor of the defendant, and the plaintiff brings error.

The action of the trial court was wrong. Beyond question the contract was entire. Norrington v. Wright, 115 U. S. 188, 6 Sup. Ct. 12, 29 L. Ed. 366; Cleveland Rolling Mills v. Rhodes, 121 U. S. 255, 7 Sup. Ct. 882, 30 L. Ed. 920; McDonald v. Kansas City Nut & Bolt Co., 149 Fed. 360, 79 C. C. A. 298, 8 L. R. A. (N. S.) 1110; Alpena Portland Cement Co. v. Backus, 156 Fed. 944, 84 C. C. A. 444.

“The provisions as to shipping in different months, and as to paying for each shipment upon its delivery, do not split up the contract into as many contracts as there shall be shipments or deliveries.” 115 U. S. 203, 6 Sup. Ct. 14 [29 L. Ed. 366].

[2] Upon default by either party as to any installment, the other party might, if it saw fit, treat the contract as abandoned by the other party. Neither party, however, was obliged to do this. It was open to them to waive strict performance. That is especially true in regard to the matter of time. There is no element of a contract with which parties are so free to deal as the time of performance. Waiver of a breach as to that element will be more readily inferred than as to any other, feature. Here correspondence between the parties leaves no room for doubt as to the waiver. Both parties treated the entire contract as in force. Each continued to express in unequivocal terms its desire and purpose to adhere to the performance of the balance of its terms. . Surely parties have the right to thus modify a contract as to the time of performance. It was only when the breach took the form that it did in June, of a total failure, that either party insisted upon its rights. The bread company then gave reasonable notice to the mills company that it required the shipment of the balance of the flour. Failure to meet that requirement was a breach of the contract, and authorized the bread company to do what it did, and it was clearly entitled to recover the difference between the contract price and. the market price of the flour. A verdict should have been directed in its favor.

The questions involved in this case have not been much considered by American courts, but were directly presented to the Exchequer Chamber in England in Tyres v. Rosedale & Ferry Hill Iron Company, L. R. 10 Ex. 195. The facts and the law are briefly stated in the opinion by Chief Justice Cockburn as follows:

“There was a contract to purchase 2,000 tons of iron to he delivered in monthly installments. It did not suit the purchasers to take the iron in the installments originally contemplated by the parties, and they proposed to the sellers to postpone from! time to time the delivery of the monthly installments. Now, it would have been perfectly competent to the defendants to say: ‘We will 'not acquiesce in that proposal of yours. You are bound to take the iron month by month, and you must so take it, or consider the contract at an end.’ Instead of doing that, the defendants, as I read the letters, acquiesced, not in holding the contract at an end, but in postponing the period of delivery. The iron was to be -delivered in the course of the year 1871, and there was, by reason of this postponement, a very considerable arrear at the end of this [696]*696year. Then the plaintiffs call on the defendants to deliver at once the whole of what remained undelivered. I think that this was a demand which they were not entitled to make.' I think that the postponement had the effect of carrying the period of delivery over the year 1872, but that the defendants could not he called upon to deliver 1,000 tons of iron at one time, but only in such quantities as was originally provided for. Therefore the defendants might have said, ‘We shall not deliver the whole that remains in one mass, but we will deliver it according to the terms of the contract.’ But they did. not say this. What they said was, We will not deliver you anything at all.’ There I think they were wrohg. Consequently there was a breach of the contract, for which the defendants are liable in damages.
“The question of the damages might have been a matter of nice calculation, as to what was the damage in respect of each, monthly installment of the period which still remained for delivery. But, fortunately, that question does not arise here, for the assessment of damages at the December market price is advantageous to the defendants, and not to the plaintiffs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hummel v. United States
58 Ct. Cl. 489 (Court of Claims, 1923)
Brevard Tannin Co. v. J. F. Mosser Co.
288 F. 725 (Fourth Circuit, 1923)
Screw MacHine Products Corp. v. Cutter & Wood Supply Co.
117 A. 659 (Supreme Court of Rhode Island, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
239 F. 693, 152 C.C.A. 527, 1917 U.S. App. LEXIS 2259, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consumers-bread-co-v-stafford-county-flour-mills-co-ca8-1917.