Alpena Portland Cement Co. v. Backus

156 F. 944, 84 C.C.A. 444, 1907 U.S. App. LEXIS 4751
Court of Appeals for the Eighth Circuit·Decided November 8, 1907·No. No. 2,515·Published·Cited by 5 cases

Opinion

HOOK, Circuit Judge.

Backus sued the cement company to recover damages for breach of contract in failing to deliver cement it [945] had sold him. He recovered judgment. The case turned upon the construction of tire writing which fixed the relations of the parties, and the company claims that the trial court erred in that particular, By a written contract made in January, 1905, the company which was engaged in manufacturing cement at Alpena, Mich., sold and agreed to deliver 100,000 barrels of its product, and Backus purchased and agreed to receive and pay for the same. It was provided that one-half of the number of barrels of cement should he delivered in 1,905, and the other half in 190G, and that the deliveries should be made at either Duluth, Minn., or Port Arthur, Ontario, at the option of Backus. The contract contained this provision:

“Shipments to be made [by the company] after navigation opens and continue throughout the season in 5,000 to 10,000 barrel lots as required by said second party [Backus]; shipments to be made on or before October 35th of each year. Said second party shall give BO days’ notice of shipments to be made, in advance.”

In the latter part of July, 1905, 5,000 barrels were ordered and duly delivered; and at the request of Backus and with consent of the company the delivery of 25,000 barrels was postponed from 1905 to the season of 190(5. This left 20,000 barrels to be delivered in '1905 and 75,000 barrels in the following year. In June and July, 1905, the company wrote Backus for orders for shipment of partial lots, assuming the contract was to be filled in ms<aiíments, and stating that if was hampered as to storage capacity and was being pressed by boats in which transportation had been engaged. Backus, without denying the correctness of the assumption, gave reasons connected with his business for failing to give the orders. Backus gave no orders for shipment, excepting as mentioned, until September 26, 1905, when he ordered 5,000 barrels to he shipped to Duluth, one of the points named in the contract. The company refused to ship, claiming Backus had delayed too long — that it was entitled to 30 days” 'notice in advance, which could not then be given before October 15th, the close oí the season for shipment. In November, 1905, the company notified Backus it had declared the contract forfeited for the reason that he had committed a breach of it and" that it would make no more deliveries. Shortly afterwards Backus brought the action. There was much correspondence between the parties, but all the facts material to our inquiry have been stated. We may add, however, that a letter from Backus, dated September 14, 1905, is not regarded as containing a direction for shipment under the contract.

Did the contract contemplate fulfillment by continuous shipments throughout the season of 5,000 to 10,000 barrel lots, and that Backus should give 30 days’ notice in advance of each shipment ordered? If so, Backus was in default in September when he pressed the company for delivery. On the other hand, was the-provision for shipments in the lots specified for the benefit and convenience of Backus alone, and was the company obligated to ship on October 15th, without previous notice, all of the 1905 cement not previously sent on orders from Backus? If so, Backus was not in default. The trial court adopted the latter view, and so instructed the jury that, after disposing of an[946] other question not necessary to mention, nothing was left them but the assessment of damages. The court held that the words “in advance,” at the end of the above excerpt from the contract, applied to the shipments and not to the notice, and as so construed it provided that 30 days’ notice should be given of advance shipments required; that is. to say, only such shipments as were ordered to be made prior to October 15th.

It was contemplated that the company should make shipments by water, and the period therefor was limited from the opening of navigation to the 15th of October. It could not have been required to ship earlier or later than the time mentioned. Two places of delivery were specified, the option of selection being with Backus; 'but he could not require delivery elsewhere. It was provided that shipments were to be made, after navigation opened and to continue throughout the season, in 5,000 to 10,000 barrel lots as required by Backus. There is reason for saying that the option of Backus in this respect was as to the size of the shipments within the limits specified, and perhaps, also, as to just when they should be made, but not whether there should be shipments at all before the end'of the season. Otherwise, why should it have been provided that the shipments were to continue throughout the season? If Backus alone had control of the matter of time, he could have required continuous shipments without definite provision to that effect in the contract. Backus was required to “give 30 days’ notice of shipments to be made, in advance.” It can as well be said that the notice was to be in advance of shipments required as that it applied only to advance shipments. We do not think the structure of the sentence makes the latter construction preferable. It is said that “in advance” would be unnecessary to the notice as it would be implied — that 30 days’ notice means 30 days’ notice in advance. It is common practice, however, in drafting instruments providing for notice, to say that it shall be given before or prior to or in advance of the day or happening to which it relates. It is certain that some sort of notice by Backus was always and in every event necessary; otherwise, the company would not know whether to ship to Duluth or to Port Arthur. The warehousing of such a large quantity of cement at the factory after it was manufactured and the securing of space in vessels for water carriage furnish substantial arguments that the provision for shipments from time to time during the season and notice was in part at least for the benefit of the company.

Free access — add to your briefcase to read the full text and ask questions with AI

Alpena Portland Cement Co. v. Backus, 156 F. 944, 84 C.C.A. 444, 1907 U.S. App. LEXIS 4751 (8th Cir. 1907).

156 F. 944 (Alpena Portland Cement Co. v. Backus) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related