Bradley Lumber & Manufacturing Co. v. Cutler

148 N.E. 101, 253 Mass. 37, 1925 Mass. LEXIS 1185
CourtMassachusetts Supreme Judicial Court
DecidedMay 28, 1925
StatusPublished
Cited by6 cases

This text of 148 N.E. 101 (Bradley Lumber & Manufacturing Co. v. Cutler) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bradley Lumber & Manufacturing Co. v. Cutler, 148 N.E. 101, 253 Mass. 37, 1925 Mass. LEXIS 1185 (Mass. 1925).

Opinion

Carroll, J.

The plaintiff manufactures lumber in South Carolina. The defendants are lumber merchants in Boston. The action is in contract to recover damages for the breach of a contract for the purchase of lumber by the defendants. In the Superior Court there was a verdict for the plaintiff. The case is here on the defendants’ exceptions to the court’s rulings, and to the admission of evidence.

On May 10, 1920, the defendants made a written contract with the General Electric Company to supply it with lumber at its plants in Schenectady in the State of New York, Pittsfield in this Commonwealth, Erie in the State of Pennsylvania, and Bloomfield in the State of New Jersey; provision was made therein for a modification in price in the event of a general price revision. To fulfil the contract the defendants made the contract in suit to purchase lumber from the plaintiff, dated July 2, 1920; it was executed by the plaintiff on July 27, 1920, and a short time thereafter was signed by the defendants. It required a minimum of three million feet of lumber, with a maximum of four million feet, at the defendants’ option. Deliveries were to be in such [47]*47quantities and at such times as the defendants ordered, shipments to be in “approximately equal monthly quantities during the contract period,” the seller agreeing to make extra heavy shipments “during the fall months.” There was no provision in the contract between the plaintiff and defendants for a price reduction in the event of a general price revision in the market. The purchaser had the right to route all shipments. No time limit was set for performance but it seems to have been assumed that it was to be completed in one year. One of the clauses was, “This contract subject to delay from strikes, accidents, wreck of cars containing goods, or other causes beyond our control, and subject to cancellation from destruction of our mill.” The defendants gave various orders for lumber; in August, September and October the plaintiff shipped a total of twenty-five cars. The defendants wrote the plaintiff, requesting more deliveries of lumber in August. The plaintiff’s sales manager wrote excusing delay on the ground of continued rain. At the trial the plaintiff relied upon a car shortage as the reason for its delay. The defendants granted a price revision to the General Electric Company in October, 1920, and wrote the plaintiff asking it to revise its price for the lumber. The plaintiff refused, and later, by letter of October 25, repeated its refusal. The defendants telegraphed the plaintiff’s mill to stop all shipments, and on October 26, notified the plaintiff that owing to its failure to perform the contract and make deliveries, the defendants cancelled the contract.

There was evidence that in August the plaintiff was ready to ship additional lumber, but was prevented by railroad embargoes and a shortage of railroad cars; that in September it endeavored to make more deliveries, but found it impossible for the same reasons; and that like conditions existed in October. We consider the defendants’ exceptions in the order they are argued in their brief.

1. The defendants moved for a directed verdict. The refusal to allow this motion raises the main question in the case. The plaintiff relies for its failure to make shipments on the clause in the contract excusing delay because of [48]*48“causes beyond our control.” In answer, the defendants contend that by relying on this clause the plaintiff is suing on a defence, and not on a performance. If the contract contained no clause excusing the plaintiff from performance, and the delay was so important that it amounted to a breach of the contract, the defendants could have refused to go on and could have brought an action for the plaintiff’s nonperformance. Whether the breach was serious enough to justify the1 defendants in refusing further performance, as a general rule, is a question of fact for the jury. Casavant v. Sherman, 213 Mass. 23, 27. National Machine & Tool Co. v. Standard Shoe Machinery Co. 181 Mass. 275. Eastern Forge Co. of Massachusetts v. Corbin, 182 Mass. 590, 593. Dudley v. Wye, 230 Mass. 350. Miller v. Benjamin, 142 N. Y. 613, 617. If the plaintiff’s failure were not so serious as to go to the root of the contract, an action for the defendants’ breach would he. A delay not going to the essence of the contract would not prevent a recovery if the defendants refused to go on with the agreement.

The parties agreed that deliveries of lumber were subject to delay from causes beyond the plaintiff’s control. The shortage of cars and the embargo, the jury could find, were beyond its control and were not occasioned by any act or omission of the plaintiff. On this finding the plaintiff was excused from performance within the time agreed. Durden-Coleman Lumber Co. v. William H. Wood Lumber Co. 221 Mass. 564. See Garfield & Proctor Coal Co. v. Pennsylvania Coal & Coke Co. 199 Mass. 22, 42. An embargo or shortage of cars might be so permanent and extensive “that the foundation of what the parties are deemed to have had in contemplation has disappeared, and the contract itself has vanished with that foundation.” F. A. Tamplin Steamship Co. Ltd. v. Anglo-Mexican Petroleum Products Co. Ltd. [1916] 2 A. C. 397, 406, 407. See North German Lloyd v. Guaranty Trust Co. 244 U. S. 12; Allanwilde Transport Corp. v. Vacuum Oil Co. 248 U. S. 377; Metropolitan Water Board v. Dick, Kerr & Co. Ltd. [1918] A. C. 119. These cases, however, are not applicable. The conditions were not such that the foundations of the contract were taken away and its per[49]*49formance rendered impossible for such a length of time that the defendants could repudiate it.

2. The defendants contend that there was error in the instruction given the jury, to the effect that time was of the essence if the plaintiff entered into the contract with knowledge of the contract of the defendants with the General Electric Company for the deliveries of lumber, “in the same amounts of the same sizes ... at the same times,” and if it was made for the purpose of supplying the material to enable “the defendants to meet their obligations . . . with the General Electric.” We do not find that the defendants excepted to this instruction. It was sufficiently favorable to them. The contract in suit contained no reference to the contract of the defendants with the General Electric Company. The plaintiff’s knowledge of such contract was a question of fact. There was no error of law in this instruction.

3. The judge correctly instructed the jury on the question of waiver. The waiver of a claim for damages was not involved. See Garfield & Proctor Coal Co. v. Fitchburg Railroad,. 166 Mass. 119. In the case at bar one of the issues before the jury was the defendants’ waiver of the plaintiff’s failure to perform. The defendants accepted slow deliveries. The effect of this could be considered by the jury on the question of the defendants’ waiver of the right to rescind the contract because of nonperformance by the other party. Norrington v. Wright, 115 U. S. 188.

4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanford v. Boston Edison Co.
64 N.E.2d 631 (Massachusetts Supreme Judicial Court, 1946)
Reid v. Bacas
57 N.E.2d 632 (Massachusetts Supreme Judicial Court, 1944)
Lander v. Samuel Heller Leather Co.
50 N.E.2d 962 (Massachusetts Supreme Judicial Court, 1943)
Hurwitz v. Lakson
6 Mass. App. Div. 350 (Mass. Dist. Ct., App. Div., 1941)
Barton v. Automobile Insurance
5 Mass. App. Div. 457 (Mass. Dist. Ct., App. Div., 1940)
Zarthar v. Saliba
185 N.E. 367 (Massachusetts Supreme Judicial Court, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
148 N.E. 101, 253 Mass. 37, 1925 Mass. LEXIS 1185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bradley-lumber-manufacturing-co-v-cutler-mass-1925.