Osgood Construction Co. v. Claremont

122 A. 346, 81 N.H. 29, 1923 N.H. LEXIS 6
CourtSupreme Court of New Hampshire
DecidedApril 3, 1923
StatusPublished

This text of 122 A. 346 (Osgood Construction Co. v. Claremont) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Osgood Construction Co. v. Claremont, 122 A. 346, 81 N.H. 29, 1923 N.H. LEXIS 6 (N.H. 1923).

Opinion

Plummer, J:

In the spring of 1913, the board of water commissioners of the town of Claremont advertised for proposals or bids for the construction of certain additions to the water system of the town. In response to this advertisement the plaintiffs made a bid, and were awarded the contract. The advertisement, form of proposals, specifications and contract were drawn by Mr. Davis, an engineer employed by the town, who had general charge of the *30 project. The controversy relates to the cost of constructing a concrete dam at the “Dole Reservoir” so called. The material portion of the specifications is as follows: “Broken stone, if used, must be clean and of such size as will pass through-a V/2 ring and over a-half inch mesh screen. . . . Sand, broken stone or gravel will be at all times subject to the approval or rejection of the engineer, and he may require broken stone or gravel to be washed.” For' each cubic yard of concrete at either the Straw or Dole reservoirs, the. sum of eleven dollars and fifty cents was to be paid the plaintiffs.

As stated by the court, it is the contention of the plaintiffs that-in submitting their proposal and signing the contract, by which they agreed to place cement for eleven dollars and fifty cents per cubic yard, they acted upon the understanding that they would be allowed to use in the concrete local stone, crushed at the site of the work to the required size; that-they were not in fact allowed to' do this,, but were required to bring in “foreign stone” by freight at a considerable increase in cost, and that they should, therefore, be allowed to recover from the town for this added expense.

On the day before the plaintiffs’ bid was submitted to the board of water commissioners, Horace E. Osgood and Mr. Dudley, the plaintiffs’ engineer, went to Claremont and looked over the location of the proposed work. Thereafter they undertook the preparation of the plaintiffs’ proposal.

Mr. Osgood testified that when they came to consider the price-for-concrete, they discussed the matter of using local crushed stone, and concluded that the work might be more cheaply done if this were allowed; that then they went to the defendants’ engineer, and asked him if they would be allowed to use local stone, and that he replied that they would. The plaintiffs’ engineer was with Mr. Osgo.od’when the conversation with the defendants’ engineer occurred. He testified in regard to the conversation as follows: “Q. As a result of that talk did you and Mr. Osgood do anything? A. We went down and interviewed the engineer, Mr. Davis. Q. Where did you meet Mr. Davis? A. We found him just outside -of the outer door of the hotel on the left-hand side. Q. What conversation took place there? [Exception by defendants.] A. Mr. Osgood asked Mr. Davis if he could base his proposal on the use of that local stone at the reservoir and about there, and Mr. Davis replied that-h'e knew of no reason why he could not; and then Mr. Osgood asked him if he should base his proposal on that stone, and he said yes. *31 Q. And as a result of that, what did you and Mr. Osgood do? A. We went back and made out the proposal at a lower figure than we had originally arranged to make. The court: How much lower? Witness: I think $1.25 a yard. I think our original proposal was $12.75, and we reduced it to $11.50.”

The defendants’ engineer contradicted the above testimony, but the court found as follows: “The court accepts as true the statement of Mr. Dudley, that Mr. Davis told him and Mr. Osgood that he saw no objection to their basing their bid upon the use of native stone, and assented to their doing so.”

When the work on the Dole reservoir commenced, test blocks were made by the plaintiffs’ employees in which local broken stone was used. These test blocks were broken up by the defendants’ engineer, and it then appeared that the local stone was wholly unsuitable for use in the concrete. The plaintiffs contend that the defendants thereupon forbid their use of the local stone. This is not assented to by the defendants. But the court found in relation to this matter that “it is clear, however, that Mr. Davis would not have permitted the use of local stone if the plaintiffs had undertaken to use it, and it appears to be of little consequence whether or not he had occasion to put this prohibition into words.”

As a result of the test and decision that the local stone was unsuitable for use, the plaintiffs were compelled to buy stone from other places, and have it shipped to Claremont for use in the concrete, at an additional expense which the court has found was $2,428.53. The court rendered a verdict for the defendants, but states that if, upon the facts, it shall be held by the supreme court that the plaintiffs are entitled to recover, there should be judgment for the plaintiffs for the sum of $2,428.53 with interest from the-date of the writ.

It appears that when the plaintiffs were engaged in preparing their proposal for submission to the defendants, it occurred to-them that there might be a question under the specifications whether they could use the local stone in the concrete.

The specifications provided that “in case bidders suspect any possible difference of opinion between themselves and the engineer, as to the meaning and intent of any of these specifications, they must ascertain and bid upon the engineer’s understanding of it, and the engineer’s decision as to any of the foregoing matters shall be final and binding upon the parties hereto.” Therefore the plaintiffs did exactly what the specifications required in such a situation, they *32 applied to the engineer to determine the question. They asked bim if they could base their bid upon the use of native stone, and he told them that they could. Accordingly they did so, reducing their bid $1.25 a yard upon the understanding that they could use local or native stone in the concrete. They were required to use foreign stone at an additional expense, and there seems to be no reason why they should not recover such expense.

The court, after finding that the defendants’ engineer had informed the plaintiffs that they might base their bid upon the use of local stone, said: “This statement, however, falls considerably short of Mr. Osgood’s claim that Mr. Davis told them unconditionally that the local stone might be used, and is rather more consistent with the statement contained in Mr. Davis’s letter, that he told several contractors that local stone might be used if it proved to be suitable.” The court seems to make a distinction between telling the plaintiffs that they might use local stone and that they might base their bid upon using it.

If this were a suit for the contract price which the defendants resisted upon the ground that the plaintiffs had improperly used the local unsuitable stone, the question whether the engineer unconditionally consented to the use of such stone might be material. But the unsuitable stone was not used and no fault appears to be found with the plaintiffs’ performance.

• If the defendants accepted the plaintiffs’ bid upon the basis of the lower price for local stone, they obtained the advantage of the use of such stone if it proved suitable. Making the contract in this way to obtain this advantage in price, they took the risk of the suitability of the local stone.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lambert Hoisting Engine Co. v. Carmody
65 A. 141 (Supreme Court of Connecticut, 1906)
Grant v. New Departure Manufacturing Co.
83 A. 212 (Supreme Court of Connecticut, 1912)
Stoops v. Smith
100 Mass. 63 (Massachusetts Supreme Judicial Court, 1868)
Keller v. Webb
125 Mass. 88 (Massachusetts Supreme Judicial Court, 1878)
Garfield & Proctor Coal Co. v. Pennsylvania Coal & Coke Co.
84 N.E. 1020 (Massachusetts Supreme Judicial Court, 1908)
Putnam-Hooker Co. v. Hewins
90 N.E. 983 (Massachusetts Supreme Judicial Court, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
122 A. 346, 81 N.H. 29, 1923 N.H. LEXIS 6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/osgood-construction-co-v-claremont-nh-1923.