Fuessenich v. DiNardo

487 A.2d 514, 195 Conn. 144, 1985 Conn. LEXIS 678
Supreme Court of Connecticut·Decided February 5, 1985·No. 12236·Published·Cited by 96 cases

Opinion

Arthur H. Healey, J.

The defendants, Pasquale DiNardo, Trustee, and Pat DiNardo & Associates, appeal from a judgment for the plaintiffs rendered by the trial court, Sullivan, J., in this case involving a road construction contract. The defendants were held jointly and severally liable to the plaintiffs in the amount of $40,240 plus costs.

The plaintiffs, John C. Fuessenich and Barry Construction Co., both have thirty years of experience as excavating contractors. On May 4,1978, the plaintiffs entered into a contract with the defendant Pasquale DiNardo, under which the plaintiffs agreed to construct in accordance with certain plans four town roads, designated as Roads A, B, C and D, in the Avalon Farms subdivision located in the town of Litchfield. These roads were to be “built to Town of Litchfield highway specifications.” The contract was signed by the plaintiffs and “Pat DiNardo, Trustee.” The trial court found that Pat DiNardo, also known as Pasquale DiNardo, was trustee for Myron Chapko, Ralph DiNardo and himself. The contract was submitted by the plaintiffs to the defendant “Pat DiNardo & Associates” which was also comprised of Pasquale DiNardo, Ralph DiNardo and Myron Chapko. The defendants owned the Avalon Farms subdivision.

The contract provided for the completion by the plaintiffs of nine listed items, and the price was specified “for payment purposes” for each item as follows:

“Clearing & grubing [sic] [$]8,000.00
“Rough excavating 25,000.00
“Catchbasins & storm drainage 25,000.00
[146] “Ledge 5,000.00
15.000. 00 “Under drain
15.000. 00 “Rip Rap
25.000. 00 “Gravel on roads
12.000. 00 “Top soil in place
95,000.00” “Paving & curbs

The total price provided in the contract for completed performance by the plaintiffs was $225,000. The parties did not expressly provide in the contract for progress payments or any kind of a payment schedule; nor was a completion date stated for any of the work to be performed thereunder.

The plaintiffs commenced performance of the contract about one week after it was signed and subsequently terminated their work in June, 1979. During that period, the plaintiffs completed the first six items specified in the contract, the contract price of which totalled $93,000. The plaintiffs also completed performance of parts of each of the remaining three contract items. In June, 1979, the plaintiffs refused to do any further work under the contract as there was “zero cash flow” from the defendants who could no longer make payments to the plaintiffs for the work being performed. At the time work ceased, roads B and C were completed.

In May, 1979, the plaintiffs had subcontracted out the paving portion of the contract to the Waters Construction Company, Inc. Because the defendants had ceased payments, the plaintiffs themselves each had to pay this subcontractor $18,120, for a total payment of $36,240. Meanwhile, the defendants had “paid the plaintiffs a total of $120,000 toward the contract price.” No indication exists in the record that the town of Litchfield or the defendants were dissatisfied with the quality of the plaintiffs’ completed work.

[147] The plaintiffs initiated this action by a complaint in one count seeking an additional $53,300 above the $120,000 sum already paid them by the defendants. The defendants denied the amount claimed was due, and in a special defense they alleged that the plaintiffs were in breach for refusing “to perform the remainder of the work outlined in the contract” and that “Pat DiNardo, Trustee” had paid them “the full amount due and owing under the aforesaid contract.” The defendants also counterclaimed against the plaintiffs seeking a refund of $27,000 from the $120,000 originally paid to the plaintiffs and other damages allegedly flowing from the claimed breach. The record discloses that at no time did the defendants challenge the lack of specificity of the plaintiffs’ pleadings nor did the defendants claim at trial ambiguity or confusion as to the nature of the plaintiffs’ claim.

At trial, the plaintiffs claimed due a total of $40,240 for the seventh, eighth and ninth contract items. For the first six items the trial court found the plaintiffs were due $93,000 “on the contract between the parties.” The trial court further found that the plaintiffs were due $25,000 for gravel, $6000 for topsoil and $36,240 for paving and curbs. In total, the plaintiffs were owed the amount of $160,240, $120,000 of which had already been paid, leaving a balance of $40,240. The trial court rendered judgment in that amount plus costs for the plaintiffs against the defendants, Pasquale DiNardo, Trustee, and Pat DiNardo Associates, jointly and severally. The trial court subsequently amended its memorandum of decision and judgment to include judgment for the plaintiffs on all of the counts set forth in counterclaims, which the defendants do not contest on this appeal.

The defendants claim on appeal that the trial court erred: (1) in allowing the plaintiffs to recover both on the express contract and for quantum meruit; (2) [148] because the allegations of the plaintiffs’ complaint do not provide a basis for recovery; (3) because the plaintiffs did not prove damages; (4) in admitting into evidence the contract and other transactions between the plaintiffs and the subcontractor, Waters Construction Company; and (5) in admitting into evidence testimony regarding Pasquale DiNardo’s associates and by rendering judgment against the defendant Pat DiNardo & Associates. We find no error.

I

The defendants challenge first the sufficiency of the plaintiffs’ pleadings. Specifically, they claim that the plaintiffs impermissibly recovered damages under a single count complaint for both express contract and quantum meruit which the defendants contend are two mutually exclusive theories of recovery. Additionally, they claim that the allegations of the plaintiffs’ complaint do not provide any basis for recovery. The plaintiffs, on the other hand, argue that the allegations in the complaint set forth a claim under an express contract and that the present case was tried by the parties and heard and decided by the trial court on an express contract theory. The plaintiffs also contend that the defendants waived any right to complain about the sufficiency of the pleadings by not raising these claims with the trial court. We find these claims of the defendants unpersuasive.

Free access — add to your briefcase to read the full text and ask questions with AI

Fuessenich v. DiNardo, 487 A.2d 514, 195 Conn. 144, 1985 Conn. LEXIS 678 (Colo. 1985).

487 A.2d 514 (Fuessenich v. DiNardo) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In re Jacob W.
172 A.3d 1274 (Connecticut Appellate Court, 2017)
Edmands v. Cuno, Inc.
892 A.2d 938 (Supreme Court of Connecticut, 2006)
Pocevic v. Connecticut Distributors, No. Cv98 035 70 30s (Jan. 16, 2003)
2003 Conn. Super. Ct. 1561 (Connecticut Superior Court, 2003)
Daly v. Blinstrubas, No. Cv99-015 65 84 S (Dec. 12, 2002)
2002 Conn. Super. Ct. 15796 (Connecticut Superior Court, 2002)
Oppenheim v. Erwin, No. Cv 00 044 16 11 (Apr. 9, 2001)
2001 Conn. Super. Ct. 4961 (Connecticut Superior Court, 2001)
Checkers Intl. v. Southwest Comm. Hlth., No. Cv00 037 50 92 (Oct. 12, 2000)
2000 Conn. Super. Ct. 12647 (Connecticut Superior Court, 2000)
Krt v. Just the Kitchen, No. 550778 (May 4, 2000)
2000 Conn. Super. Ct. 5321 (Connecticut Superior Court, 2000)
Nettleton Mechanical Cont. v. City of Meriden, No. Cv 0146838 (Feb. 3, 2000)
2000 Conn. Super. Ct. 1579 (Connecticut Superior Court, 2000)
Rosow v. Heise, No. Cv-98-0582956-S (Jun. 17, 1999)
1999 Conn. Super. Ct. 7969 (Connecticut Superior Court, 1999)
Testa v. Hill Top Realty, Inc., No. Cv89 0102492 S (Oct. 2, 1997)
1997 Conn. Super. Ct. 9970 (Connecticut Superior Court, 1997)
Schoonmaker v. Brunoli, No. Cv 96-0472829 (Mar. 17, 1997)
1997 Conn. Super. Ct. 3122 (Connecticut Superior Court, 1997)
Sheff v. O'Neill
678 A.2d 1267 (Supreme Court of Connecticut, 1996)
Clock Tower Mill Dev. v. Cambridge Dev. Corp., No. 0555348 (Apr. 23, 1996)
1996 Conn. Super. Ct. 3676 (Connecticut Superior Court, 1996)
Raposo v. Mills, No. Cv93 0132638 S (Mar. 14, 1996)
1996 Conn. Super. Ct. 2398 (Connecticut Superior Court, 1996)
The Golden Hill Paugussett T. v. State, No. Cv93 053 10 96 (Aug. 24, 1995)
1995 Conn. Super. Ct. 9878 (Connecticut Superior Court, 1995)
Commissioner of Motor Vehicles v. DeMilo
659 A.2d 148 (Supreme Court of Connecticut, 1995)
Dube v. Larson, No. Cv 93-0457778s (Jan. 11, 1995)
1995 Conn. Super. Ct. 42-A (Connecticut Superior Court, 1995)
Bryant v. Duke Travel Service, Inc., No. Cv910504508 (Dec. 6, 1994)
1994 Conn. Super. Ct. 12311 (Connecticut Superior Court, 1994)
Pia Sons Tile Co. v. H M Sachse, Inc., No. Cv94-0245453s (Nov. 21, 1994)
1994 Conn. Super. Ct. 11661 (Connecticut Superior Court, 1994)
Lapadula v. City of Middletown, No. 67942 S (Aug. 16, 1994)
1994 Conn. Super. Ct. 8191 (Connecticut Superior Court, 1994)