Dube v. Larson, No. Cv 93-0457778s (Jan. 11, 1995)

1995 Conn. Super. Ct. 42-A
CourtConnecticut Superior Court
DecidedJanuary 11, 1995
DocketNo. CV 93-0457778S
StatusUnpublished

This text of 1995 Conn. Super. Ct. 42-A (Dube v. Larson, No. Cv 93-0457778s (Jan. 11, 1995)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dube v. Larson, No. Cv 93-0457778s (Jan. 11, 1995), 1995 Conn. Super. Ct. 42-A (Colo. Ct. App. 1995).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION I. Factual and Procedural Background

On July 19, 1993, the plaintiff filed a complaint against the defendant to foreclose a mechanic's lien in the amount of $8,764.00. The plaintiff claimed that he had performed work for the defendants by virtue of a written excavation contract, and he had not been paid. The contract (Plaintiff's Exhibit 1) provides for interest at the rate of one and one-half percent per month from the billing date, plus all costs of collection, including reasonable attorney's fees. Plaintiff's claim for relief does not specifically ask for interest, costs, or attorney's fees, however. Paragraph five of his prayer does request "such other and further equitable relief as may be required".

On November 12, 1993, the defendants answered the complaint, denying that the plaintiff completed the work and denying CT Page 42-C that they owed him any money. As special defenses the defendants alleged that the plaintiff did not complete the work and the work he did complete was deficient; they already paid the plaintiff; the contract was void "ab initio" as the defendants' signatures were obtained by fraud and misrepresentation; the contract was void "ab initio" as the defendants' signatures were obtained under duress; and there were no written change orders for additional work which the plaintiff claims he did. The defendants also filed a six count counterclaim, alleging two CUTPA violations, three counts of fraudulent misrepresentation and/or duress rendering the contract void "ab initio" or simply void, and one count of breach of contract, based on plaintiff's failure to complete the work or completion of the work in an unworkmanlike manner. The defendants seek money damages from the plaintiff for monies they claim they had to expend to correct and/or finish the work. The plaintiff denied all the special defenses and each count of the counterclaim.

The defendants own a piece of land at 14 Horseshoe Lane in Farmington, Connecticut, and were acting as their own general contractor in building a house on that land. They CT Page 42-D personally interviewed and hired all the subcontractors, including the plaintiff.

Trial commenced in this matter on December 13, 1994, and completed on December 14, 1994. Both parties were represented by counsel. The plaintiff testified in his own behalf and was called as a rebuttal witness in his own behalf at the conclusion of the defendants' case. The defendant, Mary T. Larson, testified in her own behalf. No other witnesses were called by either party. Both parties waived final argument to the court.

II. Discussion

A. The existence of a contract.

Prior to the court reaching the issue of whether or not a debt is owed to the plaintiff from the defendants, the court must first address defendants' claims that there was no contract. During trial, the defendant Mary T. Larson testified she and her husband did sign the contract (Plaintiff's Exhibit CT Page 42-E 1) but that she was upset with the plaintiff because the written document which he presented to them to sign did not represent their oral discussions. She also testified that on the morning she and her husband were to meet the plaintiff on the defendants' property regarding the contract's execution, the plaintiff had already commenced work, removing stumps from the lot. Ms. Larson testified that she felt forced to sign the document, even though she felt it contained misrepresentations, because the plaintiff was there and working.

The plaintiff testified that he and the defendants had reached an oral agreement regarding the terms of the contract, he was going to reduce it to writing, he would meet them on the lot the morning they requested him to commence work, and the defendants would sign it then.

A contract in order to be valid must be the result of the free assent of the parties making it. McCarthy v. Taniska,84 Conn. 377, 381 (1911). The classical or common law definition of duress is "any wrongful act of one person that compels a manifestation of apparent assent by another to a transaction CT Page 42-F without his own volition." Jenks v. Jenks, 34 Conn. App. 462,465-66 (1994). "The duress must be imposed on the defendant at or about the time the defendant enters into the contract. Any wrongful act or threat which actually compels the victim to act against his will constitutes duress." Id.

This court had an opportunity to view both the plaintiff and the defendant, Mary T. Larson, during their individual testimony over two days of trial. In order for this court to believe that Ms. Larson and her husband, defendant Roy E. Larson, were forced to sign the contract presented by the plaintiff, this court would have to find that the defendants were somehow coerced by the plaintiff. After this court's personal observation, the court is not persuaded that the defendants were in any way intimidated by the plaintiff. The Larsons did not have to sign the contract. As the plaintiff, Gil Dube, testified, if the contract was not signed, he would have packed up his equipment and gone home. While it is true that the plaintiff started work before the contract was signed, there would have been no damage to the defendants — Mr. Dube would have gone home and several of the stumps would have already been removed CT Page 42-G from the defendants' property.

Ms. Larson testified that certain terms in the contract were not true representations of what had been discussed between the parties. If that were the case, clearly the parties could have amended that written contract and initialed it, prior to signing the document. This was not done.

Based on the testimony from both parties, the court finds that the contract is a valid contract and any claims by the defendants of fraud, misrepresentation or duress have not been proven. Consequently, defendant's third and fourth special defenses are dismissed. Similarly, counts two, four, and five of the defendants' counterclaim are dismissed.

B. Connecticut Unfair Trade Practices Act.

In determining whether a practice violates CUTPA, the following criteria are used: (1) whether the practice without necessarily having been previously considered unlawful, offends public policy as it has been established by statutes, the common CT Page 42-H law, or otherwise — whether in other words, it is within at least the penumbra of some common law, statutory, or other established concept of unfairness; (2) whether it is immoral, unethical, oppressive, or unscrupulous; (3) whether it causes substantial injury to consumers. Daddona v. Liberty Mobile HomeSales, Inc., 209 Conn. 243, 354 (1988).

As previously indicated, the defendants claimed that plaintiff's business dealings with them were fraudulent misrepresentations which induced them to execute the written contract. The defendants further allege that this behavior on plaintiff's part constituted a prohibited conduct which violates the Connecticut Unfair Trade Practices Act, Connecticut General Statutes, Section 42-100, et seq. While it is true that such behavior on the part of the plaintiff, if proven, might fall within a CUTPA violation, as this court stated, there was no evidence from any of the testimony that the plaintiff misrepresented anything to the defendants or that the defendants were forced to sign this contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCarthy v. Taniska
80 A. 84 (Supreme Court of Connecticut, 1911)
First Hartford Realty Corp. v. Ellis
434 A.2d 314 (Supreme Court of Connecticut, 1980)
Fuessenich v. DiNardo
487 A.2d 514 (Supreme Court of Connecticut, 1985)
Maturo v. Gerard
494 A.2d 1199 (Supreme Court of Connecticut, 1985)
Daddona v. Liberty Mobile Home Sales, Inc.
550 A.2d 1061 (Supreme Court of Connecticut, 1988)
Jenks v. Jenks
642 A.2d 31 (Connecticut Appellate Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
1995 Conn. Super. Ct. 42-A, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dube-v-larson-no-cv-93-0457778s-jan-11-1995-connsuperct-1995.