Froebel v. Meyer

13 F. Supp. 2d 843, 1998 WL 439359
CourtDistrict Court, E.D. Wisconsin
DecidedJuly 30, 1998
Docket97-C-654
StatusPublished
Cited by9 cases

This text of 13 F. Supp. 2d 843 (Froebel v. Meyer) is published on Counsel Stack Legal Research, covering District Court, E.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Froebel v. Meyer, 13 F. Supp. 2d 843, 1998 WL 439359 (E.D. Wis. 1998).

Opinion

DECISION AND ORDER

ADELMAN, District Judge.

Plaintiff Kurt Froebel brings this action under the citizen suit provision of the Federal Water Pollution Control Act, commonly called the Clean Water Act (“CWA” or “Act”), codified as amended at 33 U.S.C. §§ 1251-1387. Froebel alleges that defendants, who include the Wisconsin Department of Natural Resources (“DNR”), two DNR officials and Waukesha County, violat *845 ed and continue to violate the Act by discharging pollutants into the Oconomowoc River and North Lake without the requisite permits, as a result of the DNR’s poorly executed removal of Funk’s Dam 1992.

This case and the defendants’ motions to dismiss raise several novel and the legal issues including: (1) the viability of the Ex 'parte Young doctrine in the context CWA violations after two recent Supreme Court decisions on sovereign immunity 1 ; (2) the DNR’s potential accountability under a federal statute such as the CWA for non-enforcement actions performed under discretionary authority granted by Wisconsin law; and (3) the application of the relevant CWA permitting provisions, 33 U.S.C. §§ 1342 and 1344, to a fact situation involving dam removal, rather than dam construction or operation.

Count I of plaintiffs complaint alleges that defendants failed to secure a permit under 33 U.S.C. § 1342 or the analogous state permit provisions, Wis.Stat. § 283.31-63, for the removal of Funk’s Dam in 1992, or for the consequent and ongoing redeposit of silt and sediment into the downstream waters of the Oconomowoc River and North Lake. The plaintiff alleges that this shifting of sediment constitutes a “discharge of [a] pollutant” under 33 U.S.C. § 1311, or an “addition of [a] pollutant to navigable waters from [a] point source” as defined in § 1362(12)(A), requiring defendants to obtain the necessary permits.

Count II of plaintiffs complaint alleges that defendants failed to secure a permit under 33 U.S.C. § 1344 for the 1992 dam removal or for the same resulting transfer of sediment downstream, which allegedly continues to occur. The plaintiff claims that this transfer constitutes a “discharge of dredged or fill material” under § 1344 requiring defendants to obtain a permit from the Army Corps of Engineers, the entitle that issues and administers this permit provision. See 33 U.S.C. § 1344(d).

All defendants filed motions to dismiss. The state defendants raise defenses of sovereign immunity, claim preclusion growing out of prior state administrative proceedings, and failure to state a claim upon which relief can be granted. Accordingly, they move to dismiss both counts under Rule 12(b)(1), for lack of subject matter jurisdiction; and Rule 12(b)(6), for failure to state a claim. See Fed.R.Civ.P. 12(b). Waukesha County, which purchased the riparian property abutting Funk’s Dam and the dam impoundment in December 1993, also moves to dismiss both counts under Rule 12(b)(6), for failure to state a claim upon which relief can be granted. Id. Based on the following analysis, I will grant the Wisconsin defendants’ 12(b)(1) motion to dismiss because of sovereign immunity as to the DNR, but deny it as to the DNR officials. The remaining defendants’ 12(b)(6) motions to dismiss will be granted on both counts.

I. FACTUAL BACKGROUND

The following facts are taken from the complaint and from the factual findings of Administrative Law Judge Jeffrey D. Boldt (“ALJ Boldt”), incorporated into the complaint by reference. See In re Removal of Funk’s Dam, No. 3-SE-92-322 (Div. of Hearings and Appeals Feb. 21, 1996) (“ALJ Decision”).

Funk’s Dam sits approximately one mile upstream of North Lake on the Oconomowoc River in Waukesha County. Originally built in 1850 and later rebuilt several times, the dam first washed out in 1965. In 1971, the DNR notified the dam owner, Gerald Quinn, that the dam was in poor condition and needed repairs. The dam failed again in March 1975, prompting the DNR to issue an order requiring Quinn to repair the dam. Quinn refused to comply. In 1982, the DNR issued a determination that the dam was unsafe and had been abandoned and gave notice of the agency’s intention to remove it. Quinn challenged the DNR determination. Athough the challenge was ultimately dismissed by the Wisconsin Court of Appeals in 1985, dam removal was delayed.

*846 The Wisconsin legislature appropriated funds for removing abandoned dams in August 1991, and the DNR began preparations to remove Funk’s Dam. On August 17, 1992, the DNR began a drawdown of the reservoir, or impoundment, behind the dam in anticipation of removal. On the following day, a public notice was issued, requesting comments on the dam removal and seeking input on the DNR’s related Environmental Assessment (“EA”). A public informational hearing was held on September 9,1992 regarding the imminent removal of the dam. At the hearing, DNR representatives assured the public that the agency’s removal plan would guard against a significant or harmful environmental impact to downstream waters. In its EA, the DNR did observe that “an increase in sediment load to the lake is expected during drawdown.” An Environmental Impact: Statement (“EIS”) on the dam removal project was never prepared, however, as the DNR determined that one was not needed. See North Lake Management Dist. v. Wisconsin Dep’t of Natural Resources, 182 Wis.2d 500, 503, 513 N.W.2d 703 (Ct.App.1994).

On October 2, 1992, the DNR contractor began the physical removal of the dam. At that time, Funk’s Dam consisted of several 3-foot section gates, a 60-foot emergency spillway, and a 350-foot earthen embankment. No one disputes that the dam was unsafe and a menace to life, health, and property. The DNR’s foremost concern was the potential for flooding due to dam failure. In addition, the agency believed dam removal would reduce sediment transport by stabilizing the impoundment bottom. ALJ .Boldt subsequently found that a clear preponderance of the evidence established that the DNR’s decision to remove the dam was reasonable, given the serious concerns about public safety and sediment transport. ALJ Decision, Findings at ¶ 10.

Plaintiff Froebel cites poor implementation of the decision to remove the dam rather than the decision itself as the source of the environmental consequences giving rise to this litigation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glass v. Robinson
D. Arizona, 2022
West Virginia Highlands Conservancy, Inc. v. Huffman
588 F. Supp. 2d 678 (N.D. West Virginia, 2009)
Ameritech Corp. v. McCann
176 F. Supp. 2d 870 (E.D. Wisconsin, 2001)
Northgate Motors, Inc. v. General Motors Corp.
111 F. Supp. 2d 1071 (E.D. Wisconsin, 2000)
Burnette v. Carothers
192 F.3d 52 (Second Circuit, 1999)
Special Souvenirs, Inc. v. Town of Wayne
56 F. Supp. 2d 1062 (E.D. Wisconsin, 1999)
United States v. Bay-Houston Towing Co., Inc.
33 F. Supp. 2d 596 (E.D. Michigan, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
13 F. Supp. 2d 843, 1998 WL 439359, Counsel Stack Legal Research, https://law.counselstack.com/opinion/froebel-v-meyer-wied-1998.