This text of 941 S.W.2d 138 (Formosa Plastics Corp. v. Presidio Engineers & Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Formosa Plastics Corp. v. Presidio Engineers & Contractors, Inc., 941 S.W.2d 138, 1995 WL 912435 (Tex. Ct. App. 1995).

Opinion

OPINION

PER CURIAM.

This case involves allegations of fraud, breach of contract, and breach of the duty of good faith and fair dealing, arising from a construction contract and the representations made during pre-contractual bid negotiations. The case was tried before a jury, which found that both the appellants and the appellee were entitled to damages. The trial court rendered judgment in favor of the ap-pellee for $10.9 million after remitting a portion of the appellee’s actual damages and then offsetting the appellants’ damage award. By thirty points of error, the appellants challenge the sufficiency of the evidence and the jury charge. By three cross-points, the ap-pellee challenges the remittitur, the offset, and the method of calculating attorney’s fees. We affirm the judgment of the trial court.

Appellants, Formosa Plasties Corporation, USA and Formosa Plastics Corporation, Texas (collectively “Formosa”), produce resins for use in plastic and other products. Appel-lee, Presidio Engineers and Contractors, Inc. (“Presidio”), is a commercial construction business.

In 1989, Formosa commenced construction to expand its facility in Point Comfort, Texas by adding twelve plants spread over 1860 acres. Formosa contracted with several construction contractors to complete the job. In June 1990, Presidio received a “bid package” from Formosa. The “bid package” contained an invitation to bid on a job involving the construction of some 300 concrete foundations. The “bid package” also contained specifications about the job and a copy of the proposed construction contract. Formosa made several express representations in the “bid package.” Specifically, Formosa represented (i) that, although it would purchase the concrete and other materials, the contractor would have control of, and be responsible for, ordering, scheduling delivery, and storing the concrete materials, (ii) that the construction was scheduled to progress continuously from beginning to end, and (iii) that the job was scheduled to be completed in ninety days.

Presidio submitted a bid of $596,451.97, with an allowance for 120 days to complete the job. Formosa accepted the bid and awarded Presidio the contract.

Presidio commenced construction, but was unexpectedly hindered by numerous delays. Presidio blames Formosa for causing the delays and pinpoints two particular reasons: (1) Formosa frequently restricted Presidio’s access to the work site because of scheduling conflicts with other contractors, and (2) For *143 mosa changed its policy and procedure for ordering and scheduling delivery of concrete materials; as a result, the concrete materials were often unavailable when Presidio was ready to use them to pour foundations.

Presidio notified Formosa that, because of these numerous delays, it would not be able to complete the job by the scheduled completion date. Presidio further notified Formosa that it expected to be compensated for all of its delay expenses. In response, Formosa told Presidio that it would be compensated for its delay expenses.

Presidio completed the job approximately four months after the contracted completion date. Formosa subsequently paid Presidio the contract price of $596,451.97, but refused to pay Presidio’s claim for $356,000 in delay expenses. Formosa, instead, offered to settle Presidio’s claim for as much as $200,000. Presidio rejected Formosa’s offer.

Presidio then filed suit, alleging that Formosa (i) committed fraud, (ii) breached the contract, and (iii) breached its duty of good faith and fair dealing. With respect to its fraud claim, Presidio alleged that Formosa fraudulently induced Presidio to enter into the contract by misrepresenting the job could be completed in ninety days and by failing to disclose material facts concerning restricted access to the job site and the new policy for ordering and scheduling delivery of concrete materials. Further, Presidio alleged that Formosa fraudulently induced Presidio to continue performance on the contract by misrepresenting that Formosa would fully compensate Presidio for its delay expenses.

Formosa filed a counterclaim, alleging that Presidio breached the contract by failing to pour several concrete foundations according to contract specifications.

At trial, the court submitted twelve questions to the jury. In answer to Question Nos. 1 and 2A, the jury found that Formosa committed fraud against Presidio, causing Presidio to incur $1,500,000 in actual damages. In answer to Question Nos. 3 and 4, the jury found that Formosa breached its duty of good faith and fair dealing, causing Presidio to incur $1,500,000 in actual damages. In Question Nos. 2B, 5, and 8, the jury found that, because Formosa committed fraud and breached its duty of good faith and fair dealing, Formosa should be assessed punitive damages in the amount of $10,000,000 to be awarded to Presidio. In Question Nos. 6 and 7, the jury found that Formosa breached the contract, causing Presidio to incur $1,267,000 in damages. In Question No. 9, the jury further found that, because Formosa breached the contract, Presidio should recover statutory attorney’s fees equal to 40% of the breach of contract damages. Finally, in Question Nos. 10 and 11, the jury found that Presidio also breached the contract, thereby causing Formosa to incur $107,000 in damages.

Presidio elected the greater remedy of $1,500,000 in actual damages, which corresponded with either the fraud or breach of duty of good faith and fair dealing liability theories. The trial court subsequently remitted the lost profits component of the actual damage awards for all three liability theories, reducing each award by $800,000. Thus, the fraud and breach of good faith and fair dealing actual damage awards were reduced to $700,000, and the breach of contract actual damage award was reduced to $467,000. The court then offset Formosa’s damages and rendered final judgment, awarding Presidio the sum of $10,920,998.03. This sum reflects $700,000.00 in actual damages, $10,000,000.00 in punitive damages, $160,562.05 in prejudgment interest, $186,800.00 in attorney’s fees, and the $107,000.00 offset plus $19,364.02 in offset prejudgment interest. Formosa now appeals the trial court’s judgment.

By point of error 9, Formosa challenges the legal and factual sufficiency of the evidence to support the finding that Formosa defrauded Presidio. In reviewing a legal sufficiency or “no evidence” point, we must view the evidence in a light that tends to support the jury’s finding and disregard all evidence and inferences to the contrary. Weirich v. Weirich, 833 S.W.2d 942, 945 (Tex.1992); Stafford v. Stafford, 726 S.W.2d 14, 16 (Tex.1987). If there is some evidence to support the jury’s finding, then Formosa’s legal sufficiency challenge fails. Stafford, 726 S.W.2d at 16. In reviewing a factual sufficiency point, we must consider and *144 weigh all the evidence and should set aside the verdict only if it is so contrary to the overwhelming weight of the evidence as to be clearly wrong and unjust. Cain v. Bain, 709 S.W.2d 175, 176 (Tex.1986); Dyson v. Olin Corp., 692 S.W.2d 456, 457 (Tex.1985).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CBE Grp v. Lexington Law Firm
993 F.3d 346 (Fifth Circuit, 2021)
Husky International Electronics, Inc. v. Ritz
513 B.R. 510 (S.D. Texas, 2014)
Plains Builders, Inc. v. Steel Source, Inc.
408 S.W.3d 596 (Court of Appeals of Texas, 2013)
Lundy v. Masson
260 S.W.3d 482 (Court of Appeals of Texas, 2008)
in Re Lisa Gore and Glenn Alan Gore, Relator
Court of Appeals of Texas, 2007
Playboy Enterprises, Inc. v. Editorial Caballero, S.A. De C.V.
202 S.W.3d 250 (Court of Appeals of Texas, 2006)
Spethmann v. Anderson
171 S.W.3d 680 (Court of Appeals of Texas, 2005)
City of Corpus Christi v. Taylor
126 S.W.3d 712 (Court of Appeals of Texas, 2004)
Samedan Oil Corp. v. Intrastate Gas Gathering, Inc.
78 S.W.3d 425 (Court of Appeals of Texas, 2001)
Kajima International, Inc. v. Formosa Plastics Corp., USA
15 S.W.3d 289 (Court of Appeals of Texas, 2000)
Bradford v. Vento
997 S.W.2d 713 (Court of Appeals of Texas, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
941 S.W.2d 138, 1995 WL 912435, Counsel Stack Legal Research, https://law.counselstack.com/opinion/formosa-plastics-corp-v-presidio-engineers-contractors-inc-texapp-1995.