TXO Production Corp. v. Alliance Resources Corp.

125 L. Ed. 2d 366, 7 Fla. L. Weekly Fed. S 536, 113 S. Ct. 2711, 509 U.S. 443, 93 Daily Journal DAR 8072, 93 Cal. Daily Op. Serv. 4755, 61 Empl. Prac. Dec. (CCH) 42,321, 1993 U.S. LEXIS 4403, 126 Oil & Gas Rep. 576, 61 U.S.L.W. 4766
Supreme Court of the United States·Decided June 25, 1993·No. 92-479·Published·Cited by 825 cases

Opinions

[446] Justice Stevens

announced the judgment of the Court and delivered an opinion, in which The Chief Justice and Justice Blackmun join, and in which Justice Kennedy joins as to Parts I and IV.

In a common-law action for slander of title, respondents obtained a judgment against petitioner for $19,000 in actual damages and $10 million in punitive damages. The question we granted certiorari to decide is whether that punitive damages award violates the Due Process Clause of the Fourteenth Amendment, either because its amount is excessive or because it is the product of an unfair procedure.

[447] I

On August 23, 1985, TXO Production Corp. (TXO) commenced this litigation by filing a complaint in the Circuit Court of McDowell County, West Virginia, for a declaratory judgment removing a cloud on title to an interest in oil and gas development rights. Respondents, including Alliance Resources Corp. (Alliance), filed a counterclaim for slander of title that went to trial before a jury in June 1990. The jury verdict in respondents’ favor, which has been affirmed by the Supreme Court of Appeals of West Virginia, makes it appropriate to accept respondents’ version of disputed issues of fact.

In 1984, geologists employed by TXO concluded that the recovery of oil and gas under the surface of a 1,002.74-acre tract of land known as the “Blevins Tract” would be extremely profitable. They strongly recommended that TXO — a large company that was engaged in oil and gas production in 25 States — obtain the rights to develop the oil and gas resources on the Blevins Tract.

Those rights were then controlled by Alliance.1 Prodded by its geologists, TXO approached Alliance with what Alliance considered to be a “‘phenomenal offer.’” 187 W. Va. 457, 462, 419 S. E. 2d 870, 875 (1992). TXO would pay Alliance $20 per acre in cash, pay 22 percent of the oil and gas revenues in royalties, and pay all of the development costs. On April 2, 1985, Alliance accepted TXO’s offer, agreeing to assign its interest in the Tract to TXO. With respect to title to the property, Alliance agreed to return the consider[448] ation paid to it if TXO’s attorney determined that “title had failed.”2

Shortly after the agreement was signed, TXO’s attorneys discovered a 1958 deed conveying certain mineral rights in the Tract from respondent Tug Fork Land Company, a predecessor in interest of Alliance, to a coal operator named Leo J. Signaigo, Jr., who had later conveyed those rights to the Hawley Coal Mines Company, which had, in turn, reconveyed them to the Virginia Crews Coal Company (Virginia Crews). Interviews with Signaigo, and with representatives of Hawley and Virginia Crews, established that the parties all understood that only the right to mine coal had been involved in those transactions; none of them claimed any interest in oil or gas development rights. Moreover, the text of the 1958 deed made it “perfectly clear” that the grantor had reserved “all the oil and gas underlying” the Blevins Tract.3

TXO first advised Alliance of the “distinct possibility or probability” that its “leasehold title fails” in July 1985.4 In the meantime, despite its knowledge that any claim that the 1958 deed created a cloud on title to the oil and gas develop[449] ment rights would have been “frivolous,”5 TXO made two attempts to lend substance to such a claim. First, after unsuccessfully trying to convince Virginia Crews that it had an interest in the oil and gas, TXO paid the company $6,000 for a quitclaim deed conveying whatever interest it might have to TXO. TXO recorded the deed without advising Alliance.6 Second, TXO unsuccessfully attempted to induce Mr. Signaigo to execute a false affidavit indicating that the 1958 deed might have included oil and gas rights.

On July 12, after having recorded the quitclaim deed, TXO wrote to Alliance asserting that there was a title objection and implying that TXO might well have acquired the oil and gas rights from Virginia Crews. It then arranged a meeting in August and attempted to renegotiate the royalty arrangement. When the negotiations were unsuccessful, TXO commenced this litigation. According to the West Virginia Supreme Court of Appeals, TXO “knowingly and intentionally brought a frivolous declaratory judgment action” when its “real intent” was “to reduce the royalty payments under a 1,002.74 acre oil and gas lease,” and thereby “increas[e] its interest in the oil and gas rights.”7

TXO’s declaratory judgment action was decided on the basis of the parties’ written submissions. The court granted [450] respondents’ motion to prohibit TXO from introducing expert and extrinsic evidence concerning the meaning of the 1958 deed to Signaigo because the deed itself was unambiguous. On the basis of the written record, the court found that TXO had asserted a claim to title to the oil aftd gas Uhder the Blevins Tract by virtue of the quitclaim deed from Virginia Crews, App. 15, but that the deed was a “nullity.”8

The counterclaim for slander of title was subsequently tried to a jury. In addition to the evidence that TXO knew that Alliance had good title to the oil and gas and that TXO had acted in bad faith when it advanced a claim on the basis of the worthless quitclaim deed in an effort to renegotiate its royalty arrangement, Alliance introduced evidence showing that TXO was a large company in its own right and a wholly owned subsidiary of an even larger company;9 that the anticipated gross revenues from oil and gas development — and therefore the amount of royalties that TXO sought to renegotiate — were substantial;10 and that TXO had [451] engaged in similar nefarious activities in its business dealings in other parts of the country. 187 W. Va., at 468-470, 419 S. E. 2d, at 881-883.

The jury’s verdict of $19,000 in actual damages was based on Alliance’s cost of defending the declaratory judgment action. It is fair to infer that the punitive damages award of $10 million was based on other evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

TXO Production Corp. v. Alliance Resources Corp., 125 L. Ed. 2d 366, 7 Fla. L. Weekly Fed. S 536, 113 S. Ct. 2711, 509 U.S. 443, 93 Daily Journal DAR 8072, 93 Cal. Daily Op. Serv. 4755, 61 Empl. Prac. Dec. (CCH) 42,321, 1993 U.S. LEXIS 4403, 126 Oil & Gas Rep. 576, 61 U.S.L.W. 4766 (U.S. 1993).

125 L. Ed. 2d 366 (TXO Production Corp. v. Alliance Resources Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Cynthia Horne Cowan
N.D. Georgia, 2020
Onyx Pharmaceuticals, Inc. v. Bayer Corp.
863 F. Supp. 2d 894 (N.D. California, 2011)
Ragland v. Estate of Digiuro
352 S.W.3d 908 (Court of Appeals of Kentucky, 2010)
Sony BMG Music Entertainment v. Tenenbaum
721 F. Supp. 2d 85 (D. Massachusetts, 2010)
Rissler v. Jefferson County Board of Zoning Appeals
693 S.E.2d 321 (West Virginia Supreme Court, 2010)
Ojeda-Rodríguez v. Zayas
666 F. Supp. 2d 240 (D. Puerto Rico, 2009)
City of New York v. Amerada Hess Corp.
644 F. Supp. 2d 310 (S.D. New York, 2009)
JCB, INC. v. Union Planters Bank, NA
539 F.3d 862 (Eighth Circuit, 2008)
Bennett v. Reynolds
242 S.W.3d 866 (Court of Appeals of Texas, 2007)
Berkley v. Dowds
61 Cal. Rptr. 3d 304 (California Court of Appeal, 2007)
Hayes Sight & Sound, Inc. v. Oneok, Inc.
136 P.3d 428 (Supreme Court of Kansas, 2006)
Motorola Credit Corp. v. Uzan
413 F. Supp. 2d 346 (S.D. New York, 2006)
Shand v. Miller
412 F. Supp. 2d 267 (W.D. New York, 2006)
Superior Federal Bank v. Jones & MacKey Construction Co.
219 S.W.3d 643 (Court of Appeals of Arkansas, 2005)
Krysa v. Payne
176 S.W.3d 150 (Missouri Court of Appeals, 2005)
Simon v. San Paolo US Holding Co., Inc.
113 P.3d 63 (California Supreme Court, 2005)
Williams v. Philip Morris Inc.
92 P.3d 126 (Court of Appeals of Oregon, 2004)