Epco Holdings, Inc. v. Chicago Bridge & Iron Co.

352 S.W.3d 265, 2011 Tex. App. LEXIS 8216, 2011 WL 4919749
CourtCourt of Appeals of Texas
DecidedOctober 18, 2011
Docket14-10-01226-CV
StatusPublished
Cited by23 cases

This text of 352 S.W.3d 265 (Epco Holdings, Inc. v. Chicago Bridge & Iron Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Epco Holdings, Inc. v. Chicago Bridge & Iron Co., 352 S.W.3d 265, 2011 Tex. App. LEXIS 8216, 2011 WL 4919749 (Tex. Ct. App. 2011).

Opinions

[267]*267OPINION

SHARON McCALLY, Justice.

Appellants Epco Holdings, Inc. and Enterprise Products Operating, LLC appeal from the trial court’s order dismissing their claims against appellees Chicago Bridge and Iron Company and Howe-Baker Engineers, LTD. In two issues, appellants argue that the trial court abused its discretion when it dismissed some of the claims because appellants complied with the certificate-of-merit filing requirements of section 150.002 of the Texas Civil Practice and Remedies Code. We agree, and we reverse the trial court’s order dismissing appellants’ claims related to the design of catwalks. We affirm the remainder of the trial court’s order1 and remand for further proceedings.

The Statute

Resolution of this appeal depends on the interpretation and application of section 150.002 of the Texas Civil Practice and Remedies Code, titled “Certificate of Merit.” In particular, we must determine whether appellants satisfied the requirements of subsection (c), which would allow for a thirty-day extension of time to file their certificate of merit. The statute appears as follows:

(a)In any action or arbitration proceeding for damages arising out of the provision of professional services by a licensed or registered professional, the plaintiff shall be required to file with the complaint an affidavit of a third-party licensed architect, licensed professional engineer, registered landscape architect, or registered professional land surveyor who:
(1)is competent to testify;
(2) holds the same professional license or registration as the defendant; and
(3) is knowledgeable in the area of practice of the defendant and offers testimony based on the person’s:
(A) knowledge;
(B) skill;
(C) experience;
(D) education;
(E) training; and
(F) practice.
(b) The affidavit shall set forth specifically for each theory of recovery for which damages are sought, the negligence, if any, or other action, error, or omission of the licensed or registered professional in providing the professional service, including any error or omission in providing advice, judgment, opinion, or a similar professional skill claimed to exist and the factual basis for each such claim. The third-party licensed architect, licensed professional engineer, registered landscape architect, or registered professional land surveyor shall be licensed or registered in this state and actively engaged in the practice of architecture, engineering, or surveying.
(c) The contemporaneous filing requirement of Subsection (a) shall not apply to any case in which the period of limitation will expire within 10 days of the date of filing and, because of such time constraints, the plaintiff has alleged that an affidavit of a third-party licensed architect, licensed professional engineer, registered landscape architect, or registered professional land surveyor could not be prepared. In such cases, the plaintiff shall have 30 days after the [268]*268filing of the complaint to supplement the pleadings with the affidavit. The trial court may, on motion, after hearing and for good cause, extend such time as it shall determine justice requires.
(d) The defendant shall not be required to file an answer to the complaint and affidavit until 30 days after the filing of such affidavit.
(e) The plaintiffs failure to file the affidavit in accordance with this section shall result in dismissal of the complaint against the defendant. This dismissal may be with prejudice.
(f) An order granting or denying a motion for dismissal is immediately appeal-able as an interlocutory order.
(g) This statute shall not be construed to extend any applicable period of limitation or repose.
(h) This statute does not apply to any suit or action for the payment of fees arising out of the provision of professional services.

Tex. Civ. Prac. & Rem.Code Ann. § 150.002 (West 2011).

Background

On March 27, 2008, a fire broke out at appellants’ cryogenic processing plant because natural gas escaped from loose bolts on a check valve. Appellants sued appel-lees, among other defendants, due to ap-pellees’ alleged failure to design the plant with sufficient catwalks so the check valve could be properly accessed and maintained. Appellants filed their original petition on March 24, 2010, three days prior to the expiration of the period of limitations on appellants’ negligence claims. Appel-lees answered with a general denial on April 1, 2010

Appellants did not file a certificate of merit contemporaneously with their original petition, see id. § 150.002(a), nor did appellants allege in the petition that a certificate of merit could not be prepared due to time constraints, see id. § 150.002(c). Thirty days later, appellants filed a certificate of merit related to the alleged negligence of appellees’ failure to design the plant with sufficient catwalks. On the same day, appellants filed an amended petition, in which they alleged that they were forced to file the original petition without a certificate of merit because of the impending expiration of the limitations period.

About six months later, appellees filed a motion to dismiss based on section 150.002. In the motion, they argued that dismissal was required because appellants failed to meet “pleading requirements” imposed by section 150.002(c) to trigger the thirty-day extension of time to file a certificate of merit — that is, appellants failed to allege in their original petition that a certificate of merit could not be prepared because of time constraints. After a hearing, the trial court entered a written order dismissing all of appellants’ claims against appellees. This appeal followed. See id. § 150.002(f).

Analysis

Appellants argue that the trial court abused its discretion when it dismissed their claims under section 150.002 because the plain language, legislative history, and objective of the statute do not suggest that a plaintiffs allegation under subsection (c) must be made in an original petition. Ap-pellees respond that the plain language of the statute requires the allegation to be made in an original petition, and a contrary interpretation of the statute would render subsection (d) meaningless.2

[269]*269We hold that the statute does not require a plaintiffs allegation under subsection (c) to be made in the first-filed petition. Appellants complied with the plain language and intent of the statute by filing a certificate of merit and making the subsection (c) allegation in an amended petition within thirty days of filing their original petition. We neither imply nor hold that under the statute a plaintiff may invoke subsection (c) through any amended pleading filed at any time to extend the filing deadline beyond thirty days of filing their original petition.

A. Standard of Review

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CASCO Architects v. CLA Cinco, LLC
Court of Appeals of Texas, 2024
in the Interest of C.E.A.Q.
Court of Appeals of Texas, 2020
Untitled Texas Attorney General Opinion: KP-0243
Texas Attorney General Reports, 2019
Engineering & Terminal Services, L.P. v. TARSCO, Inc.
525 S.W.3d 394 (Court of Appeals of Texas, 2017)
DHM Design v. Catherine Morzak
Court of Appeals of Texas, 2015
In Re COMMITMENT OF William Michael WIRTZ
451 S.W.3d 462 (Court of Appeals of Texas, 2014)
Montrose Management District v. 1620 Hawthorne, Ltd.
435 S.W.3d 393 (Court of Appeals of Texas, 2014)
Dunham Engineering, Incorporated v. the Sherwin-Williams Company
404 S.W.3d 785 (Court of Appeals of Texas, 2013)
Bruington Engineering, LTD. v. Pedernal Energy, L.L.C.
403 S.W.3d 523 (Court of Appeals of Texas, 2013)
Epco Holdings, Inc. v. Chicago Bridge & Iron Co.
352 S.W.3d 265 (Court of Appeals of Texas, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
352 S.W.3d 265, 2011 Tex. App. LEXIS 8216, 2011 WL 4919749, Counsel Stack Legal Research, https://law.counselstack.com/opinion/epco-holdings-inc-v-chicago-bridge-iron-co-texapp-2011.