Elgin Builders, Inc. v. United States

33 Cont. Cas. Fed. 74,381, 10 Cl. Ct. 40, 1986 U.S. Claims LEXIS 871
CourtUnited States Court of Claims
DecidedMay 20, 1986
DocketNo. 579-82C
StatusPublished
Cited by13 cases

This text of 33 Cont. Cas. Fed. 74,381 (Elgin Builders, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elgin Builders, Inc. v. United States, 33 Cont. Cas. Fed. 74,381, 10 Cl. Ct. 40, 1986 U.S. Claims LEXIS 871 (cc 1986).

Opinion

OPINION

YANNELLO, Judge.

The defendant has filed a Motion for Summary Judgment. The material facts are not in dispute.

Plaintiff was awarded a contract with the United States Postal Service (USPS) on April 7, 1977, for the construction of a postal facility. See 39 U.S.C. §§ 401(6) and 404(a)(3). Plaintiff had numerous claims against the government before construction was completed. .These, claims sought additional compensation and time extensions on the grounds that: (1) there had been changes in the scope of the contract and/or in the method of work required by the contract; and (2) changed conditions were present.

These claims were submitted to the contracting officer (CO) who issued the first group of decisions on March 20, 1980, and the last decision on April 25, 1980. Some of the claims were resolved by the parties; the remaining claims now in issue were denied by the CO. In addition, the CO assessed liquidated damages of $54,000 against plaintiff for alleged failure to complete the facility on time.

The claims now in issue were pending before the CO on March 1, 1979, the date on which the Contract Disputes Act of 1978 (“CDA”), 41 U.S.C. §§ 601 et seq., became effective. That Act made provision for such pending claims (or claims initiated thereafter) under contracts entered into be[42]*42fore its effective date. It provided that the contractor could elect either to proceed under the new Act or to proceed under other applicable pre-Act provisions. The Act contains no requirements as to when or how such election is to be made. See, e.g., S.E.R., Jobs For Progress, Inc. v. United States, 759 F.2d 1 (1985).

Prior to the CDA, and under the terms of the instant contract, the contractor was bound to present the types of claims here involved, i.e., for equitable adjustment under the contract, to the CO, and thereafter to appeal to an agency board of contract appeals. Under the Tucker Act, 28 U.S.C. § 1491, and subject to the provisions of the Wunderlich Act, 41 U.S.C. §§ 321 and 322, an appeal from the board’s decision would lie in this court. With respect to contracts with the U.S. Postal Service, the Postal Reorganization Act confers jurisdiction on the district courts. 39 U.S.C. § 409(a). See also 28 U.S.C. § 1339. (The provisions of 28 U.S.C. § 1346, conferring concurrent jurisdiction on the district court and this court, are not applicable to claims in excess of $10,000.)

The CDA provides that all claims must be submitted to the CO, and that claims in excess of $50,000 must be certified. A contractor may appeal from a CO’s decision either to an agency board or may initiate suit directly in this court.

The CO, in his decisions, advised plaintiff that it could appeal the decisions to the agency board of contract appeals within 90 days or to the Court of Claims (predecessor of the Claims Court) within 12 months. Both of these avenues of appeal are specified in the Contract Disputes Act. The Disputes Clause of the contract, entered into before the CDA, and applicable if the contractor did not elect to proceed under the CDA, provided that appeal to the agency board must be taken within 30 days of the decision. This provision was not referenced in the CO’s decision.

Plaintiff filed suit in the United States District Court for the Eastern District of Michigan on March 19, 1981, within one year of the CO’s decisions. The complaint cited 39 U.S.C. § 409, and made no reference to the Contract Disputes Act. The plaintiff contends that it filed that suit with a view to electing to pursue its rights under the CDA.

On January 22, 1982, the United States District Court for the Central District of California, issued a decision in Consumers Solar Electric Power Corporation v. United States Postal Service, 530 F.Supp. 702 (C.D.Cal.1982).1 That decision held that the contracts of the Postal Service should be governed by the CDA and that the CDA conferred jurisdiction solely on the Court of Claims (now Claims Court), preempting the jurisdiction of the district courts conferred by the Postal Reorganization Act, 39 U.S.C. § 409, with respect to suits under the CDA.

In July 1982, the defendant, the United States Postal Service (USPS) moved for judgment in plaintiff’s district court action. Defendant in that action argued alternatively that: (1) if plaintiff was initiating suit without recourse to the CDA, it had failed to exhaust its administrative remedies (namely, the appeal of the CO’s decisions to the agency board); and (2) if plaintiff was attempting to invoke the provisions of the CDA, it could make such election only by filing a timely suit in the Court of Claims (now Claims Court) since the district courts had no jurisdiction under the Postal Reorganization Act, 39 U.S.C. § 409, to hear suits under the CDA, citing Consumers Solar Electric, supra.

The plaintiff, in its district court action, agreed with defendant, noting the change in its perception of jurisdiction as a result of the decision in Consumers Solar Electric, and asserted that the action should be transferred to the Claims Court. See 28 U.S.C. § 1631. The defendant argued that the “interest of justice” did not require a transfer and that the action should be dismissed. The district court entered an Or[43]*43der on November 4, 1982, transferring the case to this court, noting that it apparently lacked subject matter jurisdiction.

In the instant action, defendant moved for summary judgment in December 1983. The matter was briefed, oral argument was held, and supplemental briefs were submitted by the parties. Essentially, defendant urges two points.

First, defendant argues that this court lacks jurisdiction on the ground that the plaintiff, by initiating its action in the district court, did not elect to proceed under the CDA. Defendant argues that such an election could be made only by a timely initiation of suit in this court.

Second, defendant argues that, in any event, this court lacks jurisdiction under the CDA with respect to those claims exceeding $50,000 which plaintiff has not certified before the CO.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stormwater Plans, LLC dba SWP Contracting & Paving
Armed Services Board of Contract Appeals, 2025
Sikorsky Aircraft Corp. v. United States
102 Fed. Cl. 38 (Federal Claims, 2011)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
M. Maropakis Carpentry, Inc. v. United States
84 Fed. Cl. 182 (Federal Claims, 2008)
Tiger Natural Gas, Inc. v. United States
61 Fed. Cl. 287 (Federal Claims, 2004)
Boeing Co. v. United States
38 Cont. Cas. Fed. 76,332 (Court of Claims, 1992)
Sun Eagle Corp. v. United States
37 Cont. Cas. Fed. 76,119 (Court of Claims, 1991)
Engle Investors v. United States
35 Cont. Cas. Fed. 75,757 (Court of Claims, 1989)
Mega Construction Co. v. United States
34 Cont. Cas. Fed. 75,445 (Court of Claims, 1988)
Ralcon, Inc. v. United States
34 Cont. Cas. Fed. 75,377 (Court of Claims, 1987)
Swager Tower Corp. v. United States
34 Cont. Cas. Fed. 75,320 (Court of Claims, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,381, 10 Cl. Ct. 40, 1986 U.S. Claims LEXIS 871, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elgin-builders-inc-v-united-states-cc-1986.